ID Date Author Category Type Module Target/Number Subject Text Attachments
  108   Tuesday, May 22, 2012, 08:33 Travis CaveConditioning StationStandard OperationTM4SiC#27Electrical checkElectrical check of TM#4 with SiC#27 under
vacuum at that conditioning station. See
attached PDF for details.
 TM#4_SiC#27_pre_beam_under_vac.PDF 
  107   Friday, May 18, 2012, 08:37 David WangSouth Hot-CellStandard OperationTM4sic 27leak check on heat shield circuitChad and I leak checked the heat shield
circuit after sic 27 target  installed.
It took 20minutes  to pump down
  
  106   Friday, May 18, 2012, 08:29 Travis CaveSouth Hot-CellStandard OperationTM4SiC#27Electrical checkTM#4 with SiC#27 has had its electrical
check. See attached PDF for details.
 TM#4_SiC#27_pre_beam.PDF 
  105   Friday, May 18, 2012, 08:17 chad fisherSouth Hot-CellStandard OperationTM4SiC#27SiC#27 InstalledSiC#27 has been installed onto TM4. Fit
was very good. All electrical connections
double checked with mirror.
  
  104   Thursday, May 17, 2012, 14:08 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 has been moved from the north east
silo to the south hot cell for target installation. 
No problems with the move.
  
  103   Wednesday, May 16, 2012, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#26Spent target moveSiC #26 was moved from the south hot cell
into storage today. The target was is in
pail # 94 and was placed in slot 1B in the
 Vault_Storage_May_16_2012.pdf 
  102   Tuesday, May 15, 2012, 14:29 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 moved from the south hot cell to the
north east storage silo. No issues with the
move.
  
  101   Tuesday, May 15, 2012, 12:14 chad fisherSouth Hot-CellStandard OperationTM4SiC#26SiC#26 removal TM4 degredationSiC#26 was removed from target module #4
this morning. Target shows the now standard
arc marks on the 9 pin connector housing...pictures
 19x 
  100   Tuesday, May 15, 2012, 11:45 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26Electrical checkResults of the electrical check of TM#4
with SiC#26 attached post beam.
 TM#4_SiC#26_FEBIAD_post_beam.PDF 
  99   Monday, May 14, 2012, 12:37 Travis CaveITEStandard OperationTM4SiC#26module moveTM#4 with SiC #26 was moved from the East
Station to the South Hot Cell. Bevan was
at the helm of the PLC. There was no issue
  
  98   Tuesday, May 08, 2012, 10:28 David WangITEStandard OperationTM4 Disconnected TM4 in ITE.I disconnected TM4 in ITE. The heat shield
water circuit is purged. I  closed the
water supply to ITE.Now, the water system
  
  97   Wednesday, May 02, 2012, 11:27 David WangITWStandard OperationTM1  ITW is ready for taking proton beam. I moved 5 shielding blocks from ITE
to ITW .  I checked  all ITW water
signals strength and frequency in electrical
  
  96   Thursday, April 26, 2012, 13:01 David WangITERepairTM4 Replaced TM4 EE water flow wheel in ITE.Due to weak magnetic field on TM4 EE water
flow wheel, we have two times  intermittent
water signal on this circuit this morning.
  
  95   Thursday, April 26, 2012, 09:23 David WangITERepairTM4 changed flow wheel on ITE TM4 contaiment box water circuitThe the magnetic field on ITE TM4 flow
wheel  was gone yesterday.So there is
no water signal on this circuit. The water
  
  94   Tuesday, April 24, 2012, 10:38 David WangConditioning StationStandard OperationTM1 LP SIS Nb6TM1 heat shield circuit leak check with Nb5
 

 Normal
  0

 
   
  
  93   Tuesday, April 24, 2012, 10:36 Bevan MossConditioning StationStandard OperationTM1Nb#6HV test April 23 A HV test was complete on TM1 with
Friedhelm, David, and Myself. The module
behaved as it has in other tests. The vacuum
  
  92   Tuesday, April 24, 2012, 10:02 Travis CaveITWStandard OperationTM1Nb#6module moveTM#1 with Nb#6 from the conditioning station
to the west target station, move was uneventful.
Mike LaRoss was there today for move in place
  
  90   Friday, April 20, 2012, 14:07 Travis CaveConditioning StationStandard OperationTM1Nb#6module moveTM#1 with Nb#6 is now in the conditioning
station. The fields of the module at the
south cell was 15.8mSv/hr. The move was uneventful.
  
  89   Thursday, April 19, 2012, 09:48 David WangSouth Hot-CellStandard OperationTM1LP SIS Nb 6leak check heat shield circuitChad and I did a leak check on TM1 Nb5
target heat shield circuit. The leak detector
was connected to heat shield circuit.The
  
  88   Thursday, April 19, 2012, 09:36 Travis CaveSouth Hot-CellStandard OperationTM1Nb#6Electrical checkElectrical check has been completed of
TM#1 with Nb#6 attached. Our new micro-ohm
meter was also used for the first time for
 Elec_Check_TM1_Nb6.PDF 