  ID Date Author Category Type Module Target/Number Subjectdown Text Attachments
  1751   Wednesday, July 11, 2018, 15:06 Anders MjosITWStandard OperationTM2Nb#8Block moveMaico and Travis moved blocks from ITE
to ITW yesterday
  
  1823   Thursday, November 22, 2018, 08:53 Anders MjosITWStandard OperationTM2UC#25Block moveFrank and Anders moved blocks from ITE
to ITW yesterday
  
  1840   Tuesday, December 11, 2018, 14:35 Anders MjosITEStandard OperationTM4UC#26Block moveBlocks were moved from ITW to ITE by Frank
and David. ITE water flow to dump was re-opened
(ITW remains open). A dose badge was installed
  
  1148   Thursday, December 10, 2015, 13:17 Anders MjosConditioning StationStandard Operation  Blank off flangeThursday, December 10, 2015, 13:17: Roughing
Thursday, December 10, 2015, 14:56:
Started TP1S
 TCS_Blank_Off.png 
  661   Thursday, May 15, 2014, 14:38 David WangITERepairTM3TM3Bias short on ITEAnders and I opened the HV cover in ITE
and did  a visual check inside ITE HV 
cover and top of TM3.Bill was with us and
  
  2451   Tuesday, May 30, 2023, 14:19 David WangITE/ITWStandard Operation  BL2A MAA primary beam exclusion area ASU test. MAA ASU test have been done following document
154779. All three tests in document are passed.
DCR Jas has all test documents.
  
  2598   Thursday, May 23, 2024, 11:10 David WangMAAStandard Operation  BL2A MAA ASU test.MCR Travis Curucz and I finished BL2A MAA
ASU test per document 154779. everything
works fine. Travis kept  the test document.
  
  822   Monday, December 15, 2014, 13:25 Anders MjosConditioning StationMaintenanceTM2 BIASSW1 temperature and flow removed from interlock chain

    

       
            
  
  347   Wednesday, May 15, 2013, 16:21 Bevan MossConditioning StationRepair  BIAS Current readings off by a factor of 5 A special thanks to Kazuya, Jane
and Ray who jumped on this issue right  away!
The limit of the BIAS PS was set as 20000uA
  
  515   Monday, October 21, 2013, 12:29 Bevan MossConditioning StationRepairTM4 BIAS Canbus There is something wrong with the
BIAS canbus controller. It says that it is
not alive and has timed out. I have tried
  
  2206   Friday, March 26, 2021, 12:22 Adam NewsomeCraneDevelopment  Aux Hoist Pendant UpgradeThe crane pendant for the auxiliary hoist
was upgraded to a FLEX EX2 style  pendant
by Canco Cranes. The installation work was
  
  2636   Tuesday, July 09, 2024, 16:14 Carla BabcockITERepair  Attempts to reduce ITE:EL trips from HV sparksITE:EL has been tripping off due to HV
sparks. Usually this also trips ITE:Q1/2.
These are sitting in side-by-side racks.
 8x 
  1939   Monday, June 10, 2019, 18:12 Carla BabcockConditioning StationMaintenanceTM4No targetAttempt to push bias > 56kVMonday, June 10, 2019, 16:59 : TM4 back
up to BIAS / EL = 56.1kV / 29.5kV
Monday, June 10, 2019, 17:14 : After
 Screenshot_-_06102019_-_06_43_17_PM.png 
  2431   Friday, April 14, 2023, 10:01 Adam NewsomeAssembly/Bench TestRepair  Assaying Turntable RepairThe spent target assaying turntable was
repaired. It was tested today with a load
exceeding the maximum it would need to handle
  
  1838   Friday, December 07, 2018, 10:37 chad fisherNorth Hot-CellRepair  Ariel connector testCompleted testing of connectors for Ariel
using the north hot cell.
Video can be found on docushare;
  
  1056   Tuesday, September 01, 2015, 06:25 David WangConditioning StationStandard OperationTM2ZrCArgon venting TM2 at CSArgon venting TM2 at CS.   
  2437   Wednesday, May 03, 2023, 13:22 David WangITEStandard Operation  Argon vented ITE station. Argon vented ITE station. ITEVV1S and ITGT
SV3 were closed after venting. 
  
  218   Monday, December 03, 2012, 19:34 Grant MinorITEStandard OperationTM4LpUCxArgon supply opened for ITE ventAround 7pm tonight I opened the main valve
approximately 1.5 turns on  the Argon bottle
used for venting ITE, located in the ISAC
 Argon_Vent_ITE_Cylinder_Pressure_3Dec2012.jpgArgon_Vent_ITE_Secondary_Regulator_Pressure_Relief_3Dec2012.jpgArgon_Vent_ITE_Needle_Valve_3Dec2012.jpg 
  26   Thursday, September 01, 2011, 09:11 Don JacksonITWStandard OperationTM1UCx#2Argon Venting West StationWest target station is setup to use argon
for tank venting.  There is 1200 PSI
remaining on argon bottle in electrical room. 
  
  368   Monday, May 27, 2013, 16:36 Bevan MossConditioning StationStandard OperationTM4Ta#40Argon Venting Started Argon venting has started. It will
be left to vent over night. 
  