Entry  Wednesday, January 19, 2022, 13:36, David Wang, Crane, Standard Operation, , , Targe hall crane below hook attachment pins and plates annual inspection.  2022-01-19_174.jpg2022-01-19_172.jpg

Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01. He certified the use of these pins and plates. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08.  After inspection, The inspection tag  was issued and attached to pin. Tom has an inspection record on this job. See attachments.

Entry  Thursday, January 20, 2022, 11:09, Travis Cave, Spent Target Vault, Standard Operation, , Ta#63, Spent Target Move Target_Index_2022-01-20.pdf
The spent Ta#63 has been moved from the north hot cell to the spent target vault. It was place in pail#266 and 
placed in spot #3B of the vault. see attached PDF for more details.
Entry  Monday, January 24, 2022, 11:18, David Wang, ITE/ITW, Standard Operation, , , TH emergency exit hatch functional check 

TH emergency exit hatch which is located on TH west end roof is opened and closed for functional check. The hatch works fine. The limit switch on hatch is in position. No obstacle on hatch way to the roof. 

Entry  Tuesday, January 25, 2022, 08:57, David Wang, ITE/ITW, Standard Operation, , , ITE/ITW have been cleaned with vacuum canister.  

ITE/ITW  are cleaned with vacuum canister. HV  cage inside and blue nylon insulators are wiped.  Garbage inside the pits are cleaned out.

Entry  Tuesday, January 25, 2022, 12:49, David Wang, ITE/ITW, Standard Operation, , , Target station vacuum system visual inspection.  

Two shielding blocks  above vacuum station at TH west end were opened for inspection. Checked ITH:MP1, MP2 lubricant color and level through sight gauge on pumps. They are still ok.  Restored the shielding blocks.  Checked ITM:MP1 by decay tank (Mirror checked  sight gauge by north wall). Added lubricant to ITM:MP1 to middle level on sight gauge.  

Entry  Wednesday, February 02, 2022, 11:05, David Wang, Crane, Standard Operation, , , Target hall overhand crane annual insepection.  

Tom Kauss finished target hall overhead crane annual inspection today. The crane works fine. He issued new inspection tag and e-logged the job. 

Entry  Thursday, February 10, 2022, 11:45, David Wang, Spent Target Vault, Standard Operation, , UCx#33., Spent target UCx #33 has been repacked with a new pail and lid in NHC.  

Spent target UCx #33 has been repacked with a new pail and lid in NHC. Old pail #255. New pail # 267. Location: Vault slot 1C.  it is an investigation job for  a possible leak pail in vault.  

Entry  Thursday, February 10, 2022, 12:24, David Wang, ITW, Standard Operation, , , ITW HV test without mdoule.  

  Carla did the test. and reported the result as following: HV testing of ITW is complete. It was pretty well behaved up to 59.5kV, and sat at 59kV for 30mins with no sparks (that EPICS caught). There was some strange behaviour of the current between 51kV and 53kV - it was jumping by 20uA or more - but there didn't seem to be any voltage response, and it went away after 53kV (though it returned on the way back down). The test was done in Feb 02.

Entry  Thursday, February 10, 2022, 12:42, David Wang, ITE, Standard Operation, , , ITE HV test woithout mdoule was done. 

Carla did the test. That is what she wrote in Feb 04th:  "I am done with the HV testing at ITE - the results were the same as at ITW. It stayed at 59kV for 30 mins with no issues. Trying to go above 59.5kV is probably possible but a bit more risky. ITE also has a band, from 54-56kV, where the current jumps around like crazy".

Entry  Tuesday, February 15, 2022, 11:18, Frank Song, Cooling, Repair, , , Replace 2 leak valves on high active water system v10_v11.jpgv10.jpgv11.jpg

 The valves #V10 & V11 beside high active water pumps were replaced in Target Hall, pics attached.

 

Entry  Wednesday, February 16, 2022, 15:19, Frank Song, Cooling, Repair, , , high active cooling water valves repaired/replaced RETURN_drain_valve_in_ITE.jpgFEBIAD_COIL_in_ITW.jpgENTRANCE_COLLIMATOR_RETURN_in_ITW.jpgMAIN_S_and_R_VALVES_in_ITW.jpg

 A 3/8 inch drain valve on return cooling line was replaced in ITE. In the meantime two 1/2 inch valves labeled FEBIAD COIL and ENTRANCE COLLIMATOR RETURN at ITW were replaced . The 2 inches leaky supply/return water valves in ITW were repaired as well. Pls check pics

attached here for detail.

Entry  Thursday, February 17, 2022, 13:24, David Wang, Spent Target Vault, Maintenance, , UCx #34, Repackage of UCx #34in NHC. 

UCX34# in pail 258(Vault lot 7C) has been repacked today. It is an investigation to find a possible leak source of radioactive Iodine in vault. The new pail number is 268. It is back to vault 7c . I wrote down the information in log book. The job is smooth today. I retrieved UCx 34 old pail and liner to TH. The liner from UCx#34 only has 3000 counts.  I bagged it. It could be used later. However, the pail has 500K counts contamination on bottom outside rim. It may accidently be slided out of plastic bag and touched the NHC table during the repackage. I bagged it and store it in silo area. When we do drum clean up, I will throw it in the drum.

Entry  Thursday, February 24, 2022, 13:23, David Wang, ITE/ITW, Maintenance, , , Polyurethane water cooling lines replacement in ITE and ITW.  

Polyurethane  water cooling lines in ITE and ITW  HV shroud are replaced.  Both stations Ta, Tu, MSP, HS, Coil , EE in HV shroud are new lines.

Entry  Friday, February 25, 2022, 10:22, Adam Newsome, South Hot-Cell, Development, , , Addition of E-Stops and Turntable Vertical Motion Limit Switch 

Two changes have been made to the control system to the South Hot Cell:

  1. Addition of two emergency stop buttons: one located in the Target Hall on the wall adjacent to the hot cell, and one located on the control panel adjacent the operator station.
  2. Addition of limit switches to the turntable's vertical drive system to prevent over-travel at both the upper and lower limits.

 

The emergency stops will both stop all turntable motion: vertical and rotational.

An update to operating procedures: in order for the vertical motion system to function, the limit switch cable must be plugged in. When plugging in the vertical drive motor to the wall outlet as per normal operating procedure, it is now required to also connect the limit switch (which is mounted near the motor on the driveshaft) to the cable coming from the appropriately labelled junction box on the South wall (M12 connector).

 

These changes are based on electrical drawings IRH2083 - IRH2085 and mechanical assembly drawing ITA6739. The changes have been commissioned according to commissioning plan Document-218490. The commissioning report will be uploaded to DocuShare. The work permit for this upgrade was I2022-02-15--3.

 

Entry  Tuesday, March 01, 2022, 11:51, David Wang, Spent Target Vault, Maintenance, , , UCx #32 has been repacked in NHC.  

UCx 32# P2N target in vault slot 1B is repacked is morning for Ferran to take out his samples( in two small plastic containers) stored in pail last July when Chad did the spent target job. The job went well.  Old pail # is 254# and new pail # is 233. It is put back to 1B in vault.

Entry  Wednesday, March 02, 2022, 10:51, David Wang, ITE/ITW, Standard Operation, , , Replaced old turbopump and 2A3M20 wire scanner are transferred to cyclotron tunnel.  

Replaced 9 old turbo pumps from ITE/ ITW and  one 2A3M20 wire scanner from ITE are transferred to cyclotron tunnel for storage. It is TH RAD waste cleanup task in winter shut down.

Entry  Monday, April 04, 2022, 10:44, Nadia Jorgenson, South Hot-Cell, Repair, , , Turntable Chain Repair Hot_Cell_Chain_1.jpgHot_Cell_Chain_2.jpg

 Last week we repaired the South Hot Cell turntable chain/sprocket. Chain was loose and there was a few section where the chain was not lining up properly with the sprockets.

3 issues were discovered:

 

-        One of the pins was bent. It’s been replaced but is a temporary fix. Need to replace them with stronger pins.

 

-        The smaller sprockets near the motor were too far from the main turntable sprocket which was causing the links to not immediately line up with the teeth on the turntable sprocket. With too much slack in the chain, it’s likely that this is were the misalignment was starting. This was fixed by adjusting the motor position and the position of the yellow plate bolted to the floor.

 

-        The yellow plate that is bolted into the floor has oversized holes relative to the bolts/washers used. This allows us to adjust the position, but the washers are to thin and are being bent/pulled into the holes. Should be replaced with thicker washers that can withstand the tension and this will help prevent the plate from sliding out of position.

Entry  Friday, May 06, 2022, 10:12, Adam Newsome, Spent Target Vault, Maintenance, , , Annual Inspection of Mini-Storage Vault 

The annual inspection of the mini-storage vault was performed today. The following items were checked:

  • Cabling and cable management
  • Connectors
  • Controls box - internal wiring and components, functionality
  • Limit switches - functionality, wiring, mounting
  • Motor
  • Bearings
  • Set screws
  • Miscellaneous fasteners (some loose, but were tightened)

Everything appears to be in good working order.

Note: in the near future, the bearings should be greased. This is planned to take place during the next inspection of the main storage vault.

Entry  Wednesday, May 11, 2022, 16:15, Nadia Jorgenson, Spent Target Vault, Standard Operation, , , Emergency Close Mechanism Test 

 The emergency close mechanism for the Storage Vault door was tested by Travis Cave, Nadia Jorgenson, and Dan McDonald. The door was opened to its fully open limit, then closed with the emergency system. 

The test was successful.

Entry  Wednesday, May 11, 2022, 16:29, Nadia Jorgenson, Spent Target Vault, Standard Operation, , , Routine mechanical inspection: storage vault Motor_wiring_ISAC_storage_vault.jpg

 An inspection was performed on drive systems for the main storage vault by Dan McDonald, Travis Cave and Nadia Jorgenson. The functionality was not tested. Some areas for improvement noted, but otherwise nothing concerning was discovered. 

 

Notes:

  • The wire insulation to the motor is showing wear and tear. Should be replaced in the future. For now was patched with electrical tape, see picture. May be beneficial to add an e-chain for the portion of the wiring that moves when door is opening and closing

  • Emergency close mechanism cable should be changed to have a 5/32” Nico Sleeve

  • Moving parts still need to be lubricated


  • Chain inspected (OK)

  • Gearbox inspected - OK

  • All drive system set screws checked and tightened

  • Sprocket alignment checked - OK

  • Limit switches checked - OK

  • Emergency close mechanism cable checked - OK

 

 

 