ID Date Author Categorydown Type Module Target/Number Subject
  1359   Friday, September 23, 2016, 07:49 David WangConditioning StationStandard OperationTM4 TM4 has been moved and connected at TCS

All TCS and TM4 turbo-pumps were started yesterday. Overnight pumping down is good so far.

  1360   Friday, September 23, 2016, 08:55 Travis CaveConditioning StationStandard OperationTM4SiC#34Electrical Checks

The bundle of electrical checks, first one is the Iglis that failed, the second is the everything passed at the hot cell and the third is a the conditioning station under vacuum.

Attachment 1: TM4_elechk_SiC34_SHC.PDF
TM4_elechk_SiC34_SHC.PDF TM4_elechk_SiC34_SHC.PDF TM4_elechk_SiC34_SHC.PDF TM4_elechk_SiC34_SHC.PDF TM4_elechk_SiC34_SHC.PDF TM4_elechk_SiC34_SHC.PDF
  1361   Saturday, September 24, 2016, 11:23 Anders MjosConditioning StationStandard OperationTM4SiC#34Conditioning SiC#34

Conditioning by ISAC operations

Saturday, September 24, 2016, 11:15: RGA on for heater conditioning. (kept off during HV conditioning)


Sunday, September 25, 2016, 07:44: TGHT and TBHT voltage jumps during heater ramping. Likely contact between target and heat shield. Contacted ISAC operations and asked to abort ramping at current values. TGHT/TBHT 500 /270 A


Monday, September 26, 2016, 08:22: ISAC operations resuming ramping to 550 A. Corrected TGHT voltage at ISAC TS was ~6.2 V at 580 A. Expected voltage at TCS would then be 6.2 + (3.4+2.9)E-3*580 = 9.9 V. Limit set at 9.5 V.

Monday, September 26, 2016, 09:09: Increased TGHT voltage limit to 9.6 V to allow it to reach 550 A.

Monday, September 26, 2016, 10:17: Voltage limit increased to 10.2 V which allowed the current to go to 575 A


Tuesday, September 27, 2016, 08:08: Conditioning complete. Ran at 575 / 270 A and 47 kV for about 1 hour. Conditioned cold to 49 kV.

Attachment 1: SiC#34.docx
Attachment 2: TCS-2016-09-22_SiC#34.rga
Attachment 3: TCS-2016-09-24_SiC#34.rga
  1363   Tuesday, September 27, 2016, 07:30 David WangConditioning StationStandard OperationTM4 TM4 has been disconnected at TCS

TCS water system and vacuum system are turned  off this morning. The TCS and TM4 are vented.

  1366   Wednesday, September 28, 2016, 13:47 David WangConditioning StationStandard Operation  TCS pumping down during mini-shut down.

A steel plate  is covered on TCS. TCS roughing pump  is started now. The TCS will be pumping down during mini-shut down.

  1367   Friday, September 30, 2016, 14:34 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Weekly update TH schedule for beam schedule 131. See attachments 1,2

Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1371   Wednesday, October 12, 2016, 10:01 David WangConditioning StationStandard Operation  TCS pumps are stopped

Argon venting is started

  1384   Wednesday, October 26, 2016, 12:33 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Update TH schedule after job delay on TM2 Febiad target. Everything should be back to schedule on last two targets. See attachments.

Attachment 1: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 3: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1388   Wednesday, November 02, 2016, 09:12 Travis CaveConditioning StationStandard OperationTM4Ta#50module moved

TM#4 with Ta#50 has been moved from the south hot cell to the conditioning station.

  1389   Wednesday, November 02, 2016, 13:41 David WangConditioning StationStandard OperationTM4 TM4 has been connected at TCS.

All turbo-pumps are started. The pumping down is good so far.

  1390   Thursday, November 03, 2016, 08:57 David WangConditioning StationStandard OperationTM4 Helium pressure test on TM4 HS line at TCS

70 psi helium ,2minutes to  TM4 HS line. LD base leak rate 0.0xE-9 atm.cc/sec. No leak.

  1391   Thursday, November 03, 2016, 09:01 David WangConditioning StationStandard OperationTM4 TCS water system has been started for TM4.

The system works fine. All water signals to TM4 at TCS are normal. HV cover is installed on to TM4 at TCS.

  1393   Tuesday, November 08, 2016, 07:47 David WangConditioning StationStandard OperationTM4 TCS water and vacuum pumps are switched off

TCS is vented. TM4 is disconnected and TCS.

  1397   Tuesday, November 15, 2016, 07:53 David WangConditioning StationStandard OperationTM4 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Update TH schedules . See attachments

Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 3: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
  1400   Tuesday, November 22, 2016, 14:26 David WangConditioning StationStandard Operation  TCS vacuum pumps are switched off

TCS will be vented tomorrow morning for TM2 moving.

  1401   Wednesday, November 23, 2016, 14:21 Travis CaveConditioning StationStandard OperationTM2UC#18module moved

TM#2 with UC#18 has been moved from the south hot cell to the conditioning station.

  1404   Wednesday, November 23, 2016, 16:21 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

All vacuum pumps have been started. Air ballast 50seconds on roughing pump. Everything is good  so far.

  1405   Thursday, November 24, 2016, 09:33 Anders MjosConditioning StationStandard OperationTM2UC#18Conditioning UC#18

Thursday, November 24, 2016, 09:33: Water package on

Thursday, November 24, 2016, 09:43: TCS:WPV1 shows only 12% open. A visual inspection confirms the valve is fully opened. Controls will be contacted to troubleshoot

 

  1406   Thursday, November 24, 2016, 10:30 David WangConditioning StationStandard OperationTM2 HV cover is installed on TM2 at TCS

Interlock key  are returned back to B2 level.TM2 is ready for HV conditioning and heating up at TCS.

  1408   Tuesday, November 29, 2016, 06:27 David WangConditioning StationStandard OperationTM2 TCS water pumps are stopped

Argon venting on TCS and TM2 is processing