Thursday, February 25, 2016, 06:52, David Wang, Conditioning Station, Standard Operation, , , stop CS vacuum pumps.
|
I stopped the conditioning station vacuum pumps. The CS is still under vacuum without venting. |
Friday, March 04, 2016, 13:58, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule 8x
|
Update Schedule according to changes.See attachment1, 2.
Re-post it after some minor correction See attachment 3,4.
Update schedule according changes. See attachments 5,6 |
Monday, March 14, 2016, 15:22, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule
|
update schedule according to change. See attachment 1,2
|
Friday, March 18, 2016, 08:34, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved
|
TM#2 with no target has been moved to the conditioning station from the south hot cell. |
Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep)
|
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for beam schedule
130 is under construction, and will be posted later. |
Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS
|
TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far. |
Friday, March 18, 2016, 13:13, Travis Cave, Conditioning Station, Standard Operation, TM2, SiC#32, Electrical Check
|
Electrical checks of the TM#2 with the old SiC#32 and without the target. See attached PDFs. |
Monday, March 21, 2016, 10:25, David Wang, Conditioning Station, Repair, TM2, , TM2 Helium pressure Test Result in TCS and ITW
|
TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes.
The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr for both ITW and TCS. The test results are:
|
Monday, March 21, 2016, 11:30, David Wang, Conditioning Station, Repair, TM2, , TM2 and TCS vacuum pumps are stopped
|
I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow moving. |
Monday, March 21, 2016, 15:27, David Wang, Conditioning Station, Repair, TM2, , TM2 has been disconnected at TCS
|
TM2 vacuum system has been disconnected at TCS. Venting is in process now. |
Thursday, March 24, 2016, 13:15, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 and TCS vacuum system has been connected
|
TM1 and TCS vacuum system have been connected. All turbo-pumps are started. The pumping down is fine. |
Thursday, March 24, 2016, 13:55, Travis Cave, Conditioning Station, Standard Operation, TM1, no target, module moved
|
TM#2 has been moved from the south hot cell to the south west silo and TM#1 was moved from the north east silo to the conditioning station. All done
by 10AM. |
Tuesday, March 29, 2016, 08:38, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 water lines helium pressure check at TCS
|
TM1 water lines helium pressure check at TCS is done. 70 psi helium was applied to water circuits. Leak detector base leak rate 0.0 x E-9 atm.cc/sec,
base pressure 0.0 x E-4 torr. The result shows as below:
|
Wednesday, March 30, 2016, 08:40, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule
|
update the schedule according to changes.See attachment1, 2. |
Wednesday, March 30, 2016, 11:00, Travis Cave, Conditioning Station, Standard Operation, TM1, no target, Electrical Check
|
The results of the TM#1 electrical check from the 29th of March 2016 |
Friday, April 01, 2016, 13:58, Travis Cave, Conditioning Station, Standard Operation, TM1, UC#15, module moved
|
TM#1 has been moved from the conditioning station to the south hot cell, had UC#15 installed and then moved back to the conditioning station. |
Friday, April 01, 2016, 14:41, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 and TCS vacuum system has been connected. TCS control page white out.
|
I can not start the TCS pumps due to control page white out. Control group is working on this issue.
Control group fixed the white out problem. I started all turbo-pumps. The pumping down is good so far. The TM1 IG1 is broken. I will check it on
next Monday. It could be a broken filament. Then, the filament will be replaced. |
Monday, April 04, 2016, 11:14, David Wang, Conditioning Station, Standard Operation, TM1, , Helium pressure test on TM1 HS line at CS
|
New UCx target is installed on the module. 70psi helium,3 minutes. NO response on LD. LD is pumped to bottom LR and LP during test. |
Tuesday, April 05, 2016, 07:12, David Wang, Conditioning Station, Standard Operation, TM1, UC#15, stop CS vacuum pumps.
|
Stop TCS vacuum pumps . Preparing argon venting on TM1 and TCS.
7:34 AM, Disconnected TM1 at TCS, argon venting now. |
Thursday, April 07, 2016, 09:24, Travis Cave, Conditioning Station, Maintenance, TM4, Ta#47, module moved
|
TM#4 has been moved from the south hot cell to the conditioning station. |
|