Entry  Tuesday, March 07, 2017, 14:41, David Wang, ITE, Maintenance, , , ITE dump plug water circuit is closed for ITE IG1S small surge. 
It is closed @ 2:35PM by closing supply side valve first , the return side valve of ITE dump plug .
Opened ITE dump plug circuit valves @4:28PM. ITE IG1S still at 1XE-6. No change before and after of circuit closing and reopeneing.
Entry  Friday, March 10, 2017, 09:19, chad fisher, South Hot-Cell, Standard Operation, , , South Hot Cell Field Measurements 
The fields in the hot cell have been measured by means of a pole monitor through the tool port. Field was measured to be 25 uSv/h.
Entry  Tuesday, March 14, 2017, 07:34, chad fisher, South Hot-Cell, Maintenance, , , Hot Cell Fields 
I have re-measured the fields in the hot cell. Fields at shield door Al cover are 101 uSv\h, in cell at the east manipulator are 245 uSv\h, and the largest
field is 1.84 mSv\h...this appears to be the high current fasteners removed from the last target.
Entry  Tuesday, March 14, 2017, 11:46, chad fisher, South Hot-Cell, Maintenance, , , 'Z' motion cable dry run 
Did a dry run with the latest procedure with Dan Mcdonald. Elapsed time was approximately 30 min.
Entry  Wednesday, March 15, 2017, 07:45, chad fisher, South Hot-Cell, Maintenance, , , South Hot Cell Fields 
I have moved the suspected "hot" items in the hot cell and placed them under some lead bricks. I have re-measured the fields and it has been
reducded to 90 uSv\h at the manipulator repair area and 110 uSv/h at the previous 1.82 mSv\h area.
Entry  Thursday, March 16, 2017, 12:24, chad fisher, South Hot-Cell, Maintenance, , , West 'Z' motion cable replacement 
The west 'Z' motion cable on the east manipulator has successfully been replaced. The job took slightly less than an hour (including inspection of the
scissor table hoses) and I received 0.075mSv. Scissor table hoses appear to be fine and also didn't "shed" or flake at all when checked by hand.
Entry  Tuesday, March 21, 2017, 10:05, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target assay. Vault_Storage_March_20_2017.pdf
All target in the ISAC spent target vault have been either assayed or had their fields measured or both.
Entry  Thursday, March 23, 2017, 11:22, Grant Minor, Crane, Maintenance, , , Target Hall crane 20 ton hoist noise / smell - inspection by Gordon Crane & Hoist Target_Hall_crane_main_hoist_problem_-_A_Mjos_-_22_Mar_2017.pdfUpdate_-_Target_Hall_20T_Hoist_Inspection_-_G_Minor_-_23_Mar_2017.pdfRe__Update__Target_Hall_20T_Hoist_Inspection_-_David_Wang_-_23_mar_2017.pdf
Strange noise and a burning brake type smell was observed yesterday by David and Anders when running the main 20 ton hoist locally.  A service call
was arranged today with Gordon Crane.  No major issues were found.  A more detailed summary is in the attached e-mail correspondence.  Gordon
Crane will issue a formal report, but they recommend replacing both sets of brake disks and brake calipers. - Grant
Entry  Friday, March 24, 2017, 11:12, Keith C Ng, Spent Target Vault, Standard Operation, , , 2A window transfer 2017mar24_vault_tunnel_storage_form(1).pdf
Transfered the 2A window from the ISAC Storage Vault to the Cyclotron Vault Tunnel Storage area. RPG storage form attached.
    Reply  Friday, March 24, 2017, 11:19, Keith C Ng, Spent Target Vault, Standard Operation, , 2A3 window, Window now in vault 2017mar24_vault_tunnel_storage_form(1).pdf


    
        
            Travis Cave wrote:
        
        
            
            The 2A3 window now has a lid, and lift yolk on it and it has been installed in the spent target vault
Entry  Friday, March 24, 2017, 13:21, Travis Cave, Spent Target Vault, Standard Operation, , 2A window, 2A window has been removed from the vault. Vault_Storage_March_24_2017.pdf
2A window has been removed from the vault and moved over the cyclotron vault tunnels.  Attached is the updated storage vault list.
Entry  Monday, March 27, 2017, 06:33, David Wang, ITE, Standard Operation, , , ITE clean up 
ITE clean up is done.  HV cage inside is wiped.
Entry  Monday, March 27, 2017, 12:55, David Wang, Spent Target Vault, Repair, , , S/W silo rust clean up rust_removal_at_sw_silo_001.JPGrust_removal_at_sw_silo_002.JPGrust_removal_at_sw_silo_003.JPGrust_removal_at_sw_silo_004.JPGrust_removal_at_sw_silo_005.JPG
Rust on S/W silo and cover plate stored at silo area are cleaned up.
Entry  Tuesday, April 04, 2017, 14:39, David Wang, Crane, Standard Operation, , , Crane check main hoist on jogging with shielding plug lifted.  
Today, I checked TH crane main hoist  when shielding plug is installed into ITE pit. I did  some jogging actions on main hoist during the operation.
Everything looks fine. No burning smell, no strange noise. An outside crane expert suggest that jogging is the worst working situation for crane. We have
to use jogging actions during our crane operation. But, we could try to use less jogging when operate the crane.
Entry  Wednesday, April 05, 2017, 11:57, David Wang, ITE, Maintenance, , , ITE target module flange o-ring repalcement 
ITE target module tank flange o-ring was replaced yesterday before TM4 moving. ITE: IG1S reading looks fine so far. 
Entry  Thursday, April 06, 2017, 15:11, Grant Minor, Crane, Maintenance, , , Target Hall Crane 20 ton hoist - Report by Gordon Crane 5-Apr-2017 


v\:* {behavior:url(#default#VML);}
o\:* {behavior:url(#default#VML);}
w\:* {behavior:url(#default#VML);}
.shape {behavior:url(#default#VML);}








Normal
0




false
false
false
Entry  Thursday, April 06, 2017, 15:16, Anders Mjos, Conditioning Station, Maintenance, , , Installation of new break out box to accommodate both ITM:MP2 and TCS:MP1 
Installation by Marshall. Dave M from controls adjusted circuitry to get TCS:MP1 to start.
Work is being done in preparation for the Module Move Ventilation SAS project
Entry  Thursday, April 13, 2017, 14:16, David Wang, Crane, Repair, , , TH crane: east side main hoist brake assembly is replaced.  
Gordon Crane technician Tom Kauss finished the replacement of the east side main hoist brake assembly. A new set up is installed. he adjusted gap too
close during first time try. So, the smell appeared when operate the brake. He increased the gap to a proper distance then. It looks like everything works
fine now. Still, The brake need to be tested with 10K lBS load on it. We will do the load test on next Thursday when he come here to replace west side
Entry  Wednesday, April 19, 2017, 08:29, David Wang, Conditioning Station, Standard Operation, , , TH schedule 132 update in first beam week  Target_Hall_shedule_132_Apr_to_Sep.pdfTarget_Hall_shedule_132_Apr_to_Sep.mpp
Update schedule to show job process in TH. See attachment 1,2.
Entry  Friday, April 21, 2017, 08:19, David Wang, Conditioning Station, Repair, , , Low frequency on TCS TGHT flow sensor. TCS_water_lines_001.JPGTCS_water_lines_002.JPGTCS_water_lines_003.JPG
Anders and I found a low frequency issue(13hz only) on TCS TGHT flow sensor when doing TM4 conditioning. By trouble shooting, We found the module water
lines are good. the restriction cause this problem in on TCS supply or return water lines to TGHT.  I switched  TGHT lines with MSP water lines. The
wheel frequency on TGHT is 67.0hz  which is pretty high. Now, MSP is using the original TGHT water  line(flow sensor frequency 13hz). Flow sensors and