  832   Thursday, January 08, 2015, 15:24 Anders MjosConditioning StationDevelopmentTM2 Fault 2 on chiller unit

 Found both VFDs with OF3 fault (over voltage during constant speed operation).

Thursday, January 08, 2015, 16:37: Cycled power on the chiller to clear faults.

Attachment 1: Capture.PNG
Capture.PNG
Attachment 2: VFD_Fault.jpg
VFD_Fault.jpg
  836   Wednesday, January 28, 2015, 10:42 Anders MjosConditioning StationMaintenanceTM2 TCS shut down for site wide power outage
  863   Monday, March 16, 2015, 14:16 Travis CaveConditioning StationStandard OperationTM4No targetModule move

TM#4 from south hot cell to the conditioning station no target is attached to the module.

  868   Tuesday, March 24, 2015, 08:46 Travis CaveConditioning StationStandard OperationTM4No targetModule move

TM#4  with no target has been moved from conditioning station to the south hot cell.

  873   Wednesday, March 25, 2015, 14:34 David WangConditioning StationStandard OperationTM4Ta#45 TM4 and CS turbo- pumps are started .

I connected TM4 and CS vacuum system after TM4 move. CS roughing pump was started first this morning. Later, Anders, Bill and I started 3 turbo pumps on TM4 and CS. The pumping down is good so far. The CS vacuum system ion gauges are turned on also.

  874   Thursday, March 26, 2015, 09:20 Travis CaveConditioning StationStandard OperationTM4Ta#45Electrical check

Electrical check of TM#4 with Ta#45 at the conditioning station, see attached pdf for details.

Attachment 1: TM4_Ta#45_tgt_elec_chk_CS.PDF
TM4_Ta#45_tgt_elec_chk_CS.PDF
  875   Friday, March 27, 2015, 10:03 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CS

The helium pressure test on TM4 HS line at conditioning station is done. No leak. I also leak checked all vacuum seals on TM4 service cap. They are all good.

Attachment 1: 001.JPG
001.JPG
Attachment 2: 005.JPG
005.JPG
Attachment 3: 006.JPG
006.JPG
  876   Friday, March 27, 2015, 11:29 David WangConditioning StationStandard OperationTM4Ta#45TM4 is connected at CS

TM4 has been connected at CS which includes high current cables, water lines, EE cable, and Enizel lens cable. The HV cover has been  installed onto the TM4 service cap.The CS water system is started. All water signals are good so far.   Anders will start  HV and heaters conditioning on next Monday.

Attachment 1: 010.JPG
010.JPG
Attachment 2: 013.JPG
013.JPG
Attachment 3: 012.JPG
012.JPG
  878   Monday, March 30, 2015, 09:03 Anders MjosConditioning StationStandard OperationTM4Ta#45Ta#45 Conditionoing

Monday, March 30, 2015, 08:59: Reset chiller by switching on off power (fault 2)

Monday, March 30, 2015, 09:02: Switched on CHILL:CP2, TS5 at 34 C

Monday, March 30, 2015, 10:24 : Cage locked. EE to GND. BIAS and EL ON.

Troubleshooting BIAS current limiting. Turned out to be a EPICS initialization issue. Resolved by setting/changing the current limit again in EPICS.

Monday, March 30, 2015, 14:00: BIAS/EL 18 / 9 kV

Monday, March 30, 2015, 14:16: BIAS/EL 24 / 12 kV

Monday, March 30, 2015, 16:03: BIAS/EL 30 / 15 kV. Occasional sparking while stepping up since 26 kV

Monday, March 30, 2015, 16:13: BIAS/EL 30.8 / 15 kV. 110% of scheduled 28 kV. BIAS/EL 0.04 / 0.09 mA

Monday, March 30, 2015, 17:26 : Maintained BIAS over 1 hour. One spark after.

Monday, March 30, 2015, 17:27 : BIAS / EL off.


Tuesday, March 31, 2015, 08:12: Cage access. EE to EE PS. Cage locked.

Tuesday, March 31, 2015, 08:24: BIAS/EL/EE at 30.8 / 15 / 1 kV

Tuesday, March 31, 2015, 08:26 : EE to 2 kV, 1.96 mA

Tuesday, March 31, 2015, 08:46: No sparks for 20 min.

Tuesday, March 31, 2015, 08:48 : BIAS/EL/EE at 20 / 9.3 / 1.5 kV

Tuesday, March 31, 2015, 08:57: Started auto ramping of heaters to 580 / 230 A at 2 A/min.

Tuesday, March 31, 2015, 10:54: TBHT at 230 A

Tuesday, March 31, 2015, 14:05: TGHT at 580 A

Tuesday, March 31, 2015, 14:21: BIAS/EL/EE to 30.8 / 15 / 2 kV

Tuesday, March 31, 2015, 17:48: Source stable for 4h

Tuesday, March 31, 2015, 18:20: Lowered IAS/EL/EE to 20 / 9.3 / 1.5 kV. IG2 at 6.2E-6 T

Tuesday, March 31, 2015, 21:27: Starting ramp down at 15/12 A/min. IG2 at 6.8E-6 T

Tuesday, March 31, 2015, 21:51: BIAS/EL/EE to zero and off. IG2 at 6.6E-6 T

Tuesday, March 31, 2015, 22:17: TGHT and TBHT off

Tuesday, March 31, 2015, 22:41: Turbos off.

Tuesday, March 31, 2015, 22:42: Water off.

Attachment 1: Ta#45_Conditioning.docx
  880   Wednesday, April 01, 2015, 06:56 David WangConditioning StationStandard OperationTM4Ta#45TM4 has been disconnected at CS.

TM4 has been disconnected at CS. The CS and TM4 is venting for move. Anders stopped vacuum and water system yesterday.

  886   Wednesday, April 15, 2015, 09:01 Anders MjosConditioning StationDevelopment  Archiver variables added by Controls

 

 

 

 

 

 

 

 

 

 

The following variable have been added to the archiver (as per work request)

TCS:TS5:RDTEMP 
TCS:TCM1:EE:RDTEMP 
TCS:TCM1:COIL1:RDTEMP 
TCS:TCM1:TBHT:RDTEMP 
TCS:TCM1:TGHT:RDTEMP 
TCS:TCM1:MSP:RDTEMP 
TCS:TCM1:HVC1:RDTEMP 
TCS:TCM1:HS:RDTEMP 
TCS:FC:SCALECUR 
TCS:COL:SCALECUR 
TCS:TK2:RDLEVEL 
TCS:TK2:RDLEVEL 
TCS:DIF1:RDFLOW 
TCS:CHILL:RDHRS

The archiver was restarted.

 

 

  891   Monday, April 20, 2015, 10:12 Anders MjosConditioning StationStandard OperationTM1UC#12Conditioning UC#12

Monday, April 20, 2015, 09:35: Started cooling water circulation

HV cover did not fit due to interference with the air sampling valve. Target Hall will have to be locked out for conditioning to proceed. WP I2015-04-20-2

Monday, April 20, 2015, 10:09: Started chiller staging

Target hall and HV enclosure has been locked out.

Monday, April 20, 2015, 13:45: 22 kV, 0.04 mA BIAS 

Monday, April 20, 2015, 14:58: No sparks observed. BIAS off


Tuesday, April 21, 2015, 08:26:  Starting heater auto-ramp to 500 / 230 A at 2 A/min

Tuesday, April 21, 2015, 08:32: BIAS/EE to 20 / 1.5 kV

Tuesday, April 21, 2015, 12:59: TGHT / TBHT at 327 / 230 A. Pausing the auto-ramping. Bill will be monitoring TCS while I am off-site.

Tuesday, April 21, 2015, 15:56: Continue auto-ramping

Tuesday, April 21, 2015, 17:34: Auto-ramping finished. TGHT / TBHT at 500 / 230 A


Wednesday, April 22, 2015, 08:43: Vacuum tripped heaters and BIAS over night. Switching off to do a leak check on the service cap.

Wednesday, April 22, 2015, 09:03: Stopping turbo and roughing pump for David. David is preparing a leak check.

Wednesday, April 22, 2015, 09:06: Started roughing pump.

Wednesday, April 22, 2015, 09:22: Roughing pump trips off after a few minutes of pumping.

Wednesday, April 22, 2015, 13:11: Stopped water flow.

Wednesday, April 22, 2015, 16:07: Starting turbos 

Wednesday, April 22, 2015, 16:15: All turbos at speed.


David found a leak on the window line this morning.
https://elog.triumf.ca/TIS/RH-ISAC/896

Thursday, April 23, 2015, 11:12 : Starting cooling pack

Good vacuum limit on IG1 changed from 7E-5 T to 1E-5 T

Thursday, April 23, 2015, 12:53 : Starting heater auto-ramp to 500 / 230 A at 2 A/min. Bad vacuum limit reduced to 8E-6 T

Thursday, April 23, 2015, 13:03 : BIAS/EE to 15/ 1.5 kV

Thursday, April 23, 2015, 13:28 : BIAS/EE to 20/ 1.5 kV. No sparking observed

Thursday, April 23, 2015, 17:23: Auto-ramping finished. TGHT / TBHT at 500 / 230 A

Thursday, April 23, 2015, 17:51: Fault on cooling circuit (Fault 2).. Manually starting CP1

Thursday, April 23, 2015, 18:01: Cycled power of chiller unit. System recovered. Enabled staging.

Thursday, April 23, 2015, 18:42 : One minor spark observed. Starting cool down at 12 and 9 A/min

Thursday, April 23, 2015, 19:51 : Heaters and BIAS off


Friday, April 24, 2015, 08:21 : Water cooling off

  892   Monday, April 20, 2015, 10:22 David WangConditioning StationStandard OperationTM1UCx12TM1 with UCx12 has been connected to CS and ready for conditioing.

The TH will be locked during the TM1 conditioning time due to  an interference issue between CS HV cover and a gas analysis valve on top of TM1. A work permit has been issued for the conditioning job because of it.

  895   Wednesday, April 22, 2015, 11:05 David WangConditioning StationStandard OperationTM1 electrical check on TM1 at CS under vacuum

I did an electrical check on TM1 at CS. The resistance check:A-B 3.918m ohm, A-C 5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m ohm. They are very close to the check we did in SHC. The only unusual thing I found during the check is the ohmmeter reading between A and 60 KV common (6.2K )and the Megga reading between them  at 250 V which is 0. I repeated 4 times and always got the same readings. However, after so many times check, the Megga reading between A and 60KV   suddenly went back to normal(300 M at 250V) at the final check.  And,it stays at 300M now.  All other measurements are same as we did at SHC before.         

  896   Thursday, April 23, 2015, 09:08 David WangConditioning StationMaintenanceTM1UCx12Huge Leak on TM1 contaiment box window.

There is a huge leak on TM1 containment box window. I did a 70 psi helium pressure test on all TM1 water circuits this morning. The LD base leak rate was 0.0XE-9 atm.cc/sec. When applying the 70 psi helium to containment box window circuit, the leak rate on LD jumped to 1XE-4 atm.cc/sec in 5 seconds.I released the helium source right away,t but the conditioning station is full of helium  molecules already, and the leak rate on LD stays at 1xE-5 atm.cc /sec.  The leak on this circuit is huge.    Other water lines are good.        

Attachment 1: 006.JPG
006.JPG
Attachment 2: 008.JPG
008.JPG
Attachment 3: 011.JPG
011.JPG
Attachment 4: 009.JPG
009.JPG
Attachment 5: TM1_leak_check_at_CS_2015-04-23.pdf
TM1_leak_check_at_CS_2015-04-23.pdf
  897   Thursday, April 23, 2015, 12:56 Anders MjosConditioning StationMaintenanceTM1 IG1 Good Vacuum limit changed

Changed by Dave Morris. 

New value is 1E-5 T (old value was 7.09E-5 T)

Attachment 1: IG1GoodVacuum.png
IG1GoodVacuum.png
  898   Monday, April 27, 2015, 10:28 David WangConditioning StationStandard OperationTM1UCx12TM4 has been partially disconnected at CS.

TM1 has been partially disconnected at CS for tomorrow move. The CS TP1S is still running and will be stopped and disconnected tomorrow morning.

  901   Tuesday, April 28, 2015, 10:21 David WangConditioning StationStandard OperationTM1UCx12CS and TM1 was vented with Argon gas

Dan and I vented CS and TM1 with Argon gas before it is moved this morning.

  909   Monday, May 04, 2015, 13:32 Anders MjosConditioning StationMaintenance  TK2 expansion tank topped up

Caled cyclotron ops to open P23 and confirmed penthouse valve open.

Filled up TK2 to 21 in water leve.

  913   Monday, May 11, 2015, 10:45 Anders MjosConditioning StationMaintenance  RGA electronics box installed

 The communications chip has been replaced. The electronics box has been grounded (see attached pdf).

Attachment 1: 2015-05_RGA_GND_connection.pdf
2015-05_RGA_GND_connection.pdf 2015-05_RGA_GND_connection.pdf 2015-05_RGA_GND_connection.pdf
ELOG V2.9.2-2455