Entry  Thursday, August 17, 2017, 14:38, Isaac Earle, North Hot-Cell, Development, , , 4/6 NHC roof blocks installed 7x

 Roof blocks IRH1641, IRH1642, IRH1643, and IRH1644 have been fully assembled, labeled, and installed as per drawing IRH1652.  Fabrication of TCS shield block (IRH1646) and NHC module port block (IRH1645) is still in progress.

 IMG_0381.jpg

 

IMG_0369.jpg

 

IMG_0368.jpg

 

IMG_0364.jpg

 

IMG_0362.jpg

 

IMG_0340.jpg

Entry  Friday, August 25, 2017, 16:33, Anders Mjos, Conditioning Station, Repair, , , Testing HV after cooling line repair 2017-08-25_HV_Water_Line_Test.xlsx

 The BIAS voltage was brought up to 70 kV today and held there for 1h. No sparking observed.

Entry  Tuesday, August 29, 2017, 08:59, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 HS line leak checks 

TM4 HS line leak checks are done, at SHC and TCS. SHC: Helium spray. TCS: Helium  pressurize 70psi.  LD base LR 0.0 X E-9 atm.cc/sec.  No leak has been found on both leak checks. 

Entry  Tuesday, August 29, 2017, 09:01, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 has been connnected at TCS. 

TM4 has been connected at TCS. TCS water system has been started for TM4. TM4 and TCS vacuum pumping down is good so far.

Entry  Tuesday, September 05, 2017, 06:33, David Wang, Conditioning Station, Standard Operation, TM4, , Turned off TCS water system and vacuum system. 

Argon vent and disconnect TM4 at TCS.

Entry  Friday, September 08, 2017, 14:08, David Wang, Conditioning Station, Repair, TM3, , TCS and TM3  

TM3 is located at TCS and it is pumping down now. TCS water system has been started.  All TCS water lines for TM3 module internal cooling are bypassed and looped at TCS top ground plate. Water only supply to TCS high  current conductors.

Entry  Wednesday, September 13, 2017, 10:05, David Wang, Conditioning Station, Repair, TM3, , Switch off TCS water system and vacuums 

Preparing vent the TCS/TM3. We will remove TM3 service tray cover plate  after venting.

Entry  Wednesday, September 13, 2017, 16:05, David Wang, Conditioning Station, Repair, TM3, , remove Tm3 service tray cover plate 

TM3 service tray cover plate has been removed. It is bagged and placed to TH b2 level south wall beside the silo.

Entry  Wednesday, September 13, 2017, 16:13, David Wang, Conditioning Station, Repair, TM3, , TCS turbo pumps are started.  

TCS and TM3 all vacuum pumps are started. Everything is fine.

Entry  Tuesday, September 19, 2017, 10:40, chad fisher, South Hot-Cell, Maintenance, , , South East Manipulator Maintenence 

Entered hot cell to preform replacement of slave tong cable. Existing cable shows no signs of wear so it has been re-installed. A spare tong cable has been loaded into a spare tong while in the hot cell in preparation for next time this cable needs to be replaced.

Entry  Wednesday, September 20, 2017, 13:38, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Insulator replacement 20170920_132813.jpg20170920_132820.jpg20170920_133244.jpg

Broken insulators ITD0053 and ITD0054 have been uninstalled from TM2.

Entry  Thursday, September 21, 2017, 12:07, chad fisher, South Hot-Cell, Repair, TM2, , Insulator Replacement 

Insulators ITD0053 and 54 have been replaced. All fasteners torqued to 56 in lbs.

 

Entry  Thursday, September 21, 2017, 16:26, Anders Mjos, South Hot-Cell, Standard Operation, TM2, , Inspection of Source Tray TM2_Source_Tray_EE_Insulator.pdf

Chad and Anders inspected the Source Tray today using the camera in the hot cell. A dark spot was observed on one of the four insulators separating the Extraction Electrode from the Ground Electrode. This could potentially influence the high leakage current. Some discolored areas were also observed in the Service Tray, but these was present when the module was built. See attachment for details.

Entry  Friday, September 22, 2017, 12:13, David Wang, South Hot-Cell, Maintenance, TM2, , TM2 service cap inside inspection. TM2_serica_cap_inspection_002.JPGTM2_serica_cap_inspection_003.JPGTM2_serica_cap_inspection_004.JPGTM2_serica_cap_inspection_005.JPGTM2_serica_cap_inspection_008.JPG

Two side panels on TM2 service cap were removed for TM2 service cap inside inspection. A piece of cable tie was found inside cap closing to service tray entrance area. All blue nylon insulators are inspected. They look good. The broken cable tie is moved out of service cap.

 Panels are installed back after the inspection.

See attachments

Entry  Friday, September 22, 2017, 14:15, chad fisher, South Hot-Cell, Repair, TM2, , TM2 containment box off 20170922_140546.jpg20170922_140927.jpg

TM2 containment box has been removed. Found a piece of capton tape or tubing under table (see picture).

Entry  Thursday, September 28, 2017, 10:50, David Wang, Conditioning Station, Standard Operation, TM2, , Helium pressure test on TM2 window and HS water lines at TCS. 

  I did helium pressure test on TM2 containment box window and HS line at TCS. @ 70psi helium  for 3 minutes, HS:2.2XE-7 atm.cc/sec., Window:1.2XE-7 atm.cc/sec. There is no change on HS. But LR on window is bigger than before that was in E -9atm.cc/sec range.  

Entry  Thursday, September 28, 2017, 15:34, Anders Mjos, Conditioning Station, Development, TM2, , Changes to MP3 startup 

 Due to problems with the regulating valve WPV1, the VFD (Variable Frequency Drive) for the pump has been programmed to do a slow (2 min) ramp up. WPV1 has been bypassed and left fully opened. Work was done by Dave Morris

Entry  Thursday, October 05, 2017, 11:04, Anders Mjos, ITW, Maintenance, , , Installation of new valve for module move ventilation 

David installed the new ball valve and connections for the SAS project module move ventilation. SASP0482. Drawing reference ISK5029B.

Entry  Friday, October 06, 2017, 11:12, Isaac Earle, North Hot-Cell, Development, , , NHC module port shield block and TCS vessel shield block installed IMG_0472.jpgIMG_0476.jpgIMG_0479.jpgIMG_0481.jpgIMG_0486.jpg

 The NHC module port shield block (IRH1645) and the TCS vessel shield block (IRH1646) were installed yesterday in the target hall according to assembly drawing IRH1652.  No issues were encountered during installation.  Vacuum was pulled on the TCS and a leak check was performed on the shield: no leaks found.

 

IMG_0472.jpg

 

IMG_0476.jpg

 

IMG_0479.jpg

 

IMG_0481.jpg

 

IMG_0486.jpg

Entry  Friday, October 06, 2017, 11:21, Isaac Earle, North Hot-Cell, Development, , , ISAC-1 active sump drain pipe modified IMG_0513.jpgIMG_0516.jpgIMG_0517.jpg

The 4" PVC drain line in the ISAC-1 active sump was modified so that the drain pipe terminates below the low level water line of the automatic pump-out system.  This will prevent backflow of sump gasses into the SHC, NHC, or TCS space if the air pressure in any of those rooms are lower than the sump air pressure.  The details of the modification were specified by Mechanical Services Group, and the work was done by Paul Jensen.  This system is defined in drawing IAM19183.

 

IMG_0513.jpg

 

IMG_0516.jpg

 

IMG_0517.jpg