1600
|
Thursday, August 17, 2017, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | 4/6 NHC roof blocks installed | Roof blocks IRH1641, IRH1642, IRH1643,
and IRH1644 have been fully assembled, labeled,
and installed as per drawing IRH1652. Fabrication |
7x |
1601
|
Friday, August 25, 2017, 16:33 |
Anders Mjos | Conditioning Station | Repair | | | Testing HV after cooling line repair | The BIAS voltage was brought up to
70 kV today and held there for 1h. No sparking
observed. |
|
1606
|
Tuesday, August 29, 2017, 08:59 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 HS line leak checks | TM4 HS line leak checks are done, at SHC
and TCS. SHC: Helium spray. TCS: Helium
pressurize 70psi. LD base LR 0.0 X |
|
1607
|
Tuesday, August 29, 2017, 09:01 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 has been connnected at TCS. | TM4 has been connected at TCS. TCS water
system has been started for TM4. TM4 and
TCS vacuum pumping down is good so far. |
|
1609
|
Tuesday, September 05, 2017, 06:33 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Turned off TCS water system and vacuum system. | Argon vent and disconnect TM4 at TCS. |
|
1612
|
Friday, September 08, 2017, 14:08 |
David Wang | Conditioning Station | Repair | TM3 | | TCS and TM3 | TM3 is located at TCS and it is pumping
down now. TCS water system has been started.
All TCS water lines for TM3 module internal |
|
1613
|
Wednesday, September 13, 2017, 10:05 |
David Wang | Conditioning Station | Repair | TM3 | | Switch off TCS water system and vacuums | Preparing vent the TCS/TM3. We will remove
TM3 service tray cover plate after
venting. |
|
1614
|
Wednesday, September 13, 2017, 16:05 |
David Wang | Conditioning Station | Repair | TM3 | | remove Tm3 service tray cover plate | TM3 service tray cover plate has been removed.
It is bagged and placed to TH b2 level south
wall beside the silo. |
|
1615
|
Wednesday, September 13, 2017, 16:13 |
David Wang | Conditioning Station | Repair | TM3 | | TCS turbo pumps are started. | TCS and TM3 all vacuum pumps are started.
Everything is fine. |
|
1617
|
Tuesday, September 19, 2017, 10:40 |
chad fisher | South Hot-Cell | Maintenance | | | South East Manipulator Maintenence | Entered hot cell to preform replacement
of slave tong cable. Existing cable shows
no signs of wear so it has been re-installed. |
|
1619
|
Wednesday, September 20, 2017, 13:38 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Insulator replacement | Broken insulators ITD0053 and ITD0054 have
been uninstalled from TM2. |
  |
1621
|
Thursday, September 21, 2017, 12:07 |
chad fisher | South Hot-Cell | Repair | TM2 | | Insulator Replacement | Insulators ITD0053 and 54 have been replaced.
All fasteners torqued to 56 in lbs.
|
|
1622
|
Thursday, September 21, 2017, 16:26 |
Anders Mjos | South Hot-Cell | Standard Operation | TM2 | | Inspection of Source Tray | Chad and Anders inspected the Source Tray
today using the camera in the hot cell. A
dark spot was observed on one of the four |
|
1624
|
Friday, September 22, 2017, 12:13 |
David Wang | South Hot-Cell | Maintenance | TM2 | | TM2 service cap inside inspection. | Two side panels on TM2 service cap were
removed for TM2 service cap inside inspection.
A piece of cable tie was found inside cap |
    |
1625
|
Friday, September 22, 2017, 14:15 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 containment box off | TM2 containment box has been removed. Found
a piece of capton tape or tubing under table
(see picture). |
 |
1629
|
Thursday, September 28, 2017, 10:50 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 window and HS water lines at TCS. | I did helium pressure test on TM2
containment box window and HS line at TCS.
@ 70psi helium for 3 minutes, HS:2.2XE-7 |
|
1631
|
Thursday, September 28, 2017, 15:34 |
Anders Mjos | Conditioning Station | Development | TM2 | | Changes to MP3 startup | Due to problems with the regulating
valve WPV1, the VFD (Variable Frequency Drive)
for the pump has been programmed to do a |
|
1634
|
Thursday, October 05, 2017, 11:04 |
Anders Mjos | ITW | Maintenance | | | Installation of new valve for module move ventilation | David installed the new ball valve and
connections for the SAS project module move
ventilation. SASP0482. Drawing reference |
|
1635
|
Friday, October 06, 2017, 11:12 |
Isaac Earle | North Hot-Cell | Development | | | NHC module port shield block and TCS vessel shield block installed | The NHC module port shield block
(IRH1645) and the TCS vessel shield block
(IRH1646) were installed yesterday in the |
    |
1636
|
Friday, October 06, 2017, 11:21 |
Isaac Earle | North Hot-Cell | Development | | | ISAC-1 active sump drain pipe modified | The 4" PVC drain line in the ISAC-1
active sump was modified so that the drain
pipe terminates below the low level water |
  |