1569
|
Tuesday, June 27, 2017, 14:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 vacuum has been connected at TCS | Turbo -pumps are started . The vacuum looks
good so far. |
|
1574
|
Thursday, June 29, 2017, 11:55 |
David Wang | Conditioning Station | Repair | | | TCS HV cable and feed through installation | John Chow and I installed new TCS HV cable
and feed through with their mounting panel
back to TCS Faraday cage this Tuesday. ECO-4269 |
|
1577
|
Wednesday, July 05, 2017, 15:36 |
Isaac Earle | North Hot-Cell | Development | | | NHC and SHC nuclear ventilation flow sensors installed | Installation of new flow sensors
and transmitters for the NHC and SHC duct
lines was completed in the target hall today. |
 |
1578
|
Thursday, July 06, 2017, 14:23 |
Isaac Earle | North Hot-Cell | Repair | | | Slave side Z motion tape snapped on NHC right side manipulator | The NHC right side manipulator was evaluated
today to check if operation was normal through
all ranges of motion. The manipulator |
|
1579
|
Monday, July 10, 2017, 09:09 |
Dan McDonald | North Hot-Cell | Repair | | | manipulator cart repair | A hydraulic leak was found on the
manipulator install and repair cart,
upon further investigation the cause was |
|
1580
|
Monday, July 10, 2017, 10:19 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Turned off TCS water system | Prepare for TM4 move tomorrow morning. |
|
1582
|
Wednesday, July 12, 2017, 11:05 |
Anders Mjos | Conditioning Station | Maintenance | | | Testing of new high voltage cable | The target hall has been locked-out as
per Document-70039.
Forced IG1, IG1S and IG2 to switch |
|
1586
|
Tuesday, July 18, 2017, 15:04 |
Travis Cave | Crane | Maintenance | | | Failure of the ISAC TH Crane Rotate. | Earlier in the day it was noted that
the rotate function of the crane had creased
operation. After David has finished the block |
|
1590
|
Wednesday, August 02, 2017, 15:09 |
David Wang | ITW | Standard Operation | TM2 | | TM2 was disconnencted in ITW yesterday. | Tm2 was disconnected in ITW yesterday.
ITW EL cable crimp ring was broken. John
Chow replaced this ring this afternoon. |
|
1591
|
Wednesday, August 02, 2017, 15:13 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on HS line. | HS line is leak checked at SHC this afternoon
by helium spay. Leak detector base
LR 0.0 XE-9atm.cc/sec. Base pressure 0.0Xe-4 |
|
1592
|
Wednesday, August 02, 2017, 15:41 |
Keith C Ng | Assembly/Bench Test | Development | | | spare source tray build | After re zeroing alignment telescope to
master jig and adjusted parts into place:
|
 |
1594
|
Thursday, August 03, 2017, 17:08 |
Anders Mjos | Conditioning Station | Repair | TM2 | | Power bump | Thursday, August 03, 2017, 17:08:
Restarting vacuum and water system |
|
1596
|
Wednesday, August 09, 2017, 16:39 |
Isaac Earle | North Hot-Cell | Development | | | NHC drain line into sump identified | The NHC drain line was tested by
pouring approximately 10 gallons of water
through the drain grate at the base of the |
|
1599
|
Tuesday, August 15, 2017, 12:10 |
Isaac Earle | North Hot-Cell | Development | | | ISAC Active Sump low water level measured | The ISAC active sump in the Active Service
Room (#002 on B2 level) was pumped out yesterday
using the standard procedure (Section 5.5.2 |
|
1600
|
Thursday, August 17, 2017, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | 4/6 NHC roof blocks installed | Roof blocks IRH1641, IRH1642, IRH1643,
and IRH1644 have been fully assembled, labeled,
and installed as per drawing IRH1652. Fabrication |
7x |
1601
|
Friday, August 25, 2017, 16:33 |
Anders Mjos | Conditioning Station | Repair | | | Testing HV after cooling line repair | The BIAS voltage was brought up to
70 kV today and held there for 1h. No sparking
observed. |
|
1606
|
Tuesday, August 29, 2017, 08:59 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 HS line leak checks | TM4 HS line leak checks are done, at SHC
and TCS. SHC: Helium spray. TCS: Helium
pressurize 70psi. LD base LR 0.0 X |
|
1607
|
Tuesday, August 29, 2017, 09:01 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 has been connnected at TCS. | TM4 has been connected at TCS. TCS water
system has been started for TM4. TM4 and
TCS vacuum pumping down is good so far. |
|
1609
|
Tuesday, September 05, 2017, 06:33 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Turned off TCS water system and vacuum system. | Argon vent and disconnect TM4 at TCS. |
|
1612
|
Friday, September 08, 2017, 14:08 |
David Wang | Conditioning Station | Repair | TM3 | | TCS and TM3 | TM3 is located at TCS and it is pumping
down now. TCS water system has been started.
All TCS water lines for TM3 module internal |
|