ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1268   Monday, June 27, 2016, 13:45 David WangITEStandard Operation  5 Shielding blocks have been transferred from ITW to ITE.ITE is configured to take proton beam.   
  1269   Tuesday, June 28, 2016, 14:42 Travis CaveSpent Target VaultStandard Operation ManySpent target assay.The spent target assay were finally started
or re-started today. Four targets were done
today.
 Vault_Storage_June_30_2016.pdfMini_Vault_Storage_June_30_2015.pdf 
  1270   Thursday, June 30, 2016, 13:33 Dan McDonaldSpent Target VaultMaintenance  F308'sThe five spent target F308  flasks
where gone through in accordance with Nordion
guidelines, the sixth spare is remains in
  
  1272   Wednesday, July 06, 2016, 07:06 David WangConditioning StationStandard Operation  venting TCS with argon.I switched off the vacuum pumps and vented
TCS with argon. The TCS will be ready to
accept TM2 this afternoon.
  
  1279   Friday, July 08, 2016, 16:56 Anders MjosConditioning StationRepair  VFD21 OL1 fault on ChillerPlant Services group (Tony) will contact
a service tech on Monday.
Water system will be switched off
  
  1280   Monday, July 11, 2016, 10:59 Travis CaveSpent Target VaultStandard Operation Ta#48Spent Target moveThe spent Ta#48 was moved from the south
hot cell to the spent target vault. I was
placed in pail 139 and is in spot 6C in the
 Vault_Storage_July_11_2016.pdf 
  1283   Tuesday, July 12, 2016, 12:42 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Update schedule weekly.Attachment 1,2  Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 
  1286   Thursday, July 14, 2016, 13:25 Anders MjosConditioning StationRepair  VFD21 OL1 fault on Chiller

    

       
            
  
  1292   Tuesday, July 26, 2016, 11:22 chad fisherSouth Hot-CellMaintenance  Soth Hot Cell Waste Storage Vault TunnelThe two 45 gal (m) drums of waste removed
from the south hot cell in December 2015
and January 2016 were transferred from the
  
  1294   Friday, July 29, 2016, 14:27 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Measurements & Cleanup The North
Hot Cell was accessed today via the Ante
  
  1300   Wednesday, August 03, 2016, 09:15 chad fisherSouth Hot-CellRepair  ManipulatorEast manipulator on the south hot cell
is showing signs of eminent wrist/tong cable
failure. Some slight slippage was noted yesterday
  
  1303   Wednesday, August 03, 2016, 09:56 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Update schedule weekly. See attachments
1,2
 Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1305   Thursday, August 04, 2016, 08:56 Travis CaveSpent Target VaultStandard Operation UC#16Spent Target moveThe spent UC #16 have been moved from the
south hot cell to the storage vault see attached
PDF for details.
 Vault_Storage_August_3_2016.pdf 
  1306   Friday, August 05, 2016, 13:50 chad fisherSouth Hot-CellMaintenance  Anteroom clean outSome items have been removed from the anteroom
in preparation for painting. Items have been
placed on plastic in the south hot cell service
  
  1307   Friday, August 05, 2016, 14:13 Isaac EarleNorth Hot-CellDevelopment  Preparations for NHC Ventilation TestA hole was drilled in the NHC exhaust duct
in the east end of the target hall above
the hatch to the Ante Room.  This will
  
  1308   Monday, August 08, 2016, 11:24 chad fisherSouth Hot-CellMaintenance  Anteroom Clean-up - WaveguideThe wave guide from TM3 has been surveyed,
swiped and removed from the anteroom and
transported to rad waste for disposal. The
  
  1311   Tuesday, August 09, 2016, 11:36 Anders MjosConditioning StationMaintenance  RGA and CG1S moved The locations (ports) for the RGA
and CG1S was swapped today by Anders and
Isaac to provide clearance for the North
 Old.JPGNew.JPG 
  1314   Wednesday, August 10, 2016, 12:18 chad fisherSouth Hot-CellMaintenance  Anteroom clearingBlack "radio active" materials
cabinet has been emptied, items bagged and
removed from the anteroom. Cabinet itself
  
  1315   Wednesday, August 10, 2016, 14:38 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Ventilation Test ResultsTesting was performed on August 9th on
the ISAC nuclear ventilation system to determine
if the existing ventilation system can achieve
  
  1317   Friday, August 12, 2016, 09:58 chad fisherSouth Hot-CellMaintenance  Manipulator MaitenanceDisassembled the master side of the right
manipulator this morning to check the wrist
cable. The cable on the master side shows
  