ID Date Author Category Type Module Target/Numberdown Subject
  1540   Wednesday, May 17, 2017, 08:35 David WangConditioning StationStandard OperationTM4 TCS turbo pumps was started yesterday

Anders started TCS turbo-pumps yesterday. The TCS and TM4 pumping down is good so far. I started TCS water pumps this morning for TCS water flow check.

2017-05-17 morning:  Stopped the water pumps. The field around the TM4 is high because of spent target in SHC. The water flow measurement will be delayed to this Friday.

  1541   Thursday, May 18, 2017, 10:08 David WangConditioning StationStandard OperationTM4 TM4 TP1 at TCS

TM4 TP1 was found making some noise during operation this morning. The current draw was check then. It was 1.8 A which is higher than 1.0A normal range. The pump body temperature was higher by hand feeling. But,1.0 hour later when checking again, everything on the pump goes back to normal. It is still fine so far. I will watch on this pump closely.

 2017-05-19,morning.  The TM4 TP1 stopped running last night.  I tried to start it this morning. But, It can't pass 6KRMP even. I think we have to replace it.    E- fault will be issued as well.   

  1544   Friday, May 19, 2017, 12:25 David WangConditioning StationStandard OperationTM4 TCS and TM4 water flow measurement.

 

 

  TCS(LPM) Freq(HZ) TCS+TM4(LPM) Freq(HZ)
Ta 5.5 106 3.7 68
Tu 5.6 107 4.3 79
Coil(RU only) 5.8 112 4.6 92
HS 7.0 13 6.6 12
MSP 6.4 21 5.8 21
EE 5.6 112 3.8 77
Window 4.5 81 4.3 78

 

  1545   Friday, May 19, 2017, 13:49 David WangConditioning StationRepairTM4 TM4 TP1 at TCS

TM4 TP1 is replaced. TCS and TM4 was argon vented before the job.The job took about 30minutes.  I started the all turbo pumps after job. All pumps work fine. The TCS vacuum is good.     

  1547   Tuesday, May 23, 2017, 13:30 David WangITEStandard OperationTM4 TM4 has been connected in ITE

Yasmine and I connected TM4 in ITE . All turbo pumps are started.

  1548   Tuesday, May 23, 2017, 14:10 David WangITEStandard Operation  ITE water interlock check is done.

We do this check once a year now. Rene found a target oven reset issue during the check . He will consult with Friedhelm. The interlock check is good.

  1549   Wednesday, May 24, 2017, 08:11 David WangITWStandard OperationTM2 TH schedule 132 update weekly

See attachments.

  1551   Wednesday, June 07, 2017, 13:33 David WangConditioning StationStandard OperationTM2 TM2 SiC#36 leakc check and electrical check.

The results  are good. See attachment.

  1552   Wednesday, June 07, 2017, 13:34 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

I started all turbo pumps.

  1553   Thursday, June 08, 2017, 07:37 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 water llines at TCS.
  The helium pressure test on HS line is done at TCS this morning. I got the same result as last time when we helium pressure it it with first target in April. The leak  rate on this line is 1.8 XE-7atm.cc/sec. So, we know this leak is mostly on the line, but not on the VCR joints connecting the target.  See attachment for last time(April) checking e-log. The leak could be from water block which is same as other lines. I do not think this leak rate will affect the operation.

The attachment can not be opened for some reasons. Please check TM2 leak check  2017-03-13 e- log for last time test result and comment.

  1554   Thursday, June 08, 2017, 08:35 David WangConditioning StationDevelopmentTM2 TM2 gas line reconfiguration on the module top.

Reconfigured TM2 gas line on the module top. It matches with the febiad gas line we are using on service tray now. Facing the module, both of them should be that right side line of two SST lines on feed-through. The gas line on TM2 was leak checked with a blind cap installed on service tray side and LD connected on module top this Tuesday. It is leak free with helium spray on the top of module and service tray.

  1555   Friday, June 09, 2017, 11:21 chad fisherNorth Hot-CellMaintenance  Model 'N' Slave Removal Through Roof

Isaac and Chad disengaged the slave end of the manipulator and performed a slave removal through the slave removal roof hatch. This is part of investigation into a 'Z' motion tape that is "rubbing" on its drum on the master side of the manipulator during manual 'Z' retraction of 'Z' extension.

This also was the first test of the concept of removing the manipulator slave through the manipulator hatch that was built into the roof.

The lifting bail on the slave end of the manipulator was not centered to the hatch as per design but this did not compromise the procedure at all and the procedure otherwise followed the design intent.

Pictures can be located on Docushare  http://documants.triumf.ca/docushare/dsweb/View/Collection-20157

 

 

  1556   Monday, June 12, 2017, 13:51 Travis CaveSpent Target VaultStandard Operation  Spent Target move

The spent Ta#51 target has been moved from the south hot cell to the spent target vault. It was placed in pail#149 and put in spot 8B of the vault.

  1558   Tuesday, June 13, 2017, 11:10 Grant MinorCraneMaintenance  ISAC THall Crane 100% / 125% Load Test Documentation - 2011

The ISAC Target Hall Crane was load tested and re-certified in January 2011 prior to doing a near-capacity lift for the North Hot Cell roof structure (IRH1112E).

Photos and documentation from Norelco is attached.

- Grant

  1559   Tuesday, June 13, 2017, 13:41 David WangITWStandard OperationTM2 TM2 has been connected in ITW.

Yasmine and I connected TM2 in ITW today. the control page is set to febiad mode. Both gas line in ITW are opened for febiad run. All connections are double checked. Module connection checklist is finished.  All turbo pumps are started now. Everything is good so far. The TM2 is ready for conditioning when the ITW vacuum is good enough.

  1560   Thursday, June 15, 2017, 11:29 Isaac EarleNorth Hot-CellDevelopment  NHC inlet ducting installed

The North Hot Cell inlet ducting assembly was installed today in the target hall at the north end of the NHC roof block.  A small section of the perforated aluminum sheet on the TCS cage had to be trimmed for the assembly to fit (see IMG_0214).  At each end of the assembly it was fastened to the roof structure using a 1/4"-20 tapped hole in the steel roof, and a 1/4"-20 anchor in the north wall of the target hall.  The base flange of the assembly was sealed to the roof structure and TH wall using Sikaflex 1A polyurethane sealant on all sides.

 

IMG_0217.jpg

 

IMG_0218.jpg

 

IMG_0219.jpg

 

IMG_0214.jpg

  1561   Monday, June 19, 2017, 07:29 David WangConditioning StationStandard OperationTM2 Update TH MS project schedule.

Update TH MS project schedule. See attachment 1,2.

  1562   Thursday, June 22, 2017, 11:10 chad fisherSouth Hot-CellMaintenance  In cell airline

The in cell airline has preemptively been replaced. The hose was, as far as I know the original.

  1563   Friday, June 23, 2017, 12:08 David WangCraneRepair  TH crane inspection and probem fixing by Gordon crane

Gordon crane technician Peter came in today and checked TH crane. Maico and I were there with him. What he found is that brake gap on both side of main hoist decreased after months of using.  The solution is to lock the automatic self adjustment system so the gap will be fixed there. Each year during annual inspection, they will adjust the gap manually. After he locked both side of device, I tested the crane up and down couple of times. The brakes work fine. 

  1564   Friday, June 23, 2017, 17:28 Isaac EarleNorth Hot-CellDevelopment  NHC module flange and cameras installed

 The North Hot Cell module support flange (IRH1152D) was installed on June 21, 2017 using 1/8" rubber sheet as a sealing gasket.  The rubber was glued at the seams with Loctite 495 instant adhesive.  Cameras with all required wiring and connectors were installed on the mounting bars (IGN0325D) and then aligned to provide the same view as at other module installation locations in the target hall.  A cable with 5 video signals, and a camera power cable was routed from the south wall in the target hall (where video line connections are), to the panduit on the north wall.  An additional section of cable will be installed to link to the flange cameras after cable covers are installed on the floor.

 

IMG_0231.jpg

 

IMG_0234.jpg

 

IMG_0245.jpg

 

IMG_0240.jpg