Entry  Wednesday, September 02, 2015, 09:26, David Wang, ITE, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_shedule_129_Sep_to_Dec.xlsxTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp

I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.

Weekly update of Target Hall Schedule.See Attachments 3,4

Entry  Thursday, September 10, 2015, 08:59, chad fisher, South Hot-Cell, Repair, , , Manipulator Mait. and field check Sept. 4 

Hot cell was entered for preventative mait. on left manip. field measurements around the cell were taken in prep. for window removal in January and left/south light bulb changed.

Hottest item in the cell was the conductor block end of the TM4 febiad coil line. It was 70 mSv/H on contact and seemed to be the major source of field in the hot cell. The waterblock end of this line did not apper to be hot.

Entry  Tuesday, September 22, 2015, 13:15, David Wang, South Hot-Cell, Standard Operation, , Ta#46, Leak check on TM4 HS water line with new Ta#46 target. at SHC 

Chad and I leak checked the HS line at SHC. No leak. Leak rate 0.0xE-9atm.cc/sec.

Entry  Friday, September 25, 2015, 07:56, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp

weekly update see attachment

Entry  Friday, September 25, 2015, 08:21, Travis Cave, South Hot-Cell, Standard Operation, , UC#13, Spent Target move Vault_Storage_September_24_2015.pdf

The spent UC#13 target has been moved from the south hot cell to the ISAC spent target vault. It was placed pail #128 and in tray spot 1A. It was 21.5mSv/hr upon removal from the hot cell. See attached PDF for details.

Entry  Thursday, October 01, 2015, 09:18, Travis Cave, Spent Target Vault, Standard Operation, , , Targets transfered to mini storage. 

In preparation for shipping of the spent targets five have been moved to the mini storage. The following target were moved to the mini storage, SiC#26, Ta#36, UC#9,10,11.

Entry  Monday, October 05, 2015, 10:19, Anders Mjos, Conditioning Station, Maintenance, , , Chiller maintenance 

 will be performed Tuesday October 6th

Tuesday, October 06, 2015: Maintenance re-schedlued for Wednesday October 7th

Entry  Tuesday, October 13, 2015, 10:53, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp

Weekly update schedule. TM3 evaluation schedule in Nov is added.  

update the schedule after  the cancellation of TM2 from SHC to CS trip.see attachments 3,4

Entry  Tuesday, October 20, 2015, 12:49, Dan McDonald, ITW, Standard Operation, , SiC#32, Tm2 hook up In ITW 

Lower and disconnect TM2 from crane in ITW, proceed with hooking up TM2 as per checklist with Anders. Double check flow meters and coils, reset TP1 and TP2

Entry  Tuesday, October 20, 2015, 13:52, chad fisher, South Hot-Cell, Maintenance, , , TM4 Febiad coil line disposal 20151020_133045.jpg20151020_134303.jpg

The febiad coil line removed from TM4 has been cut into pieces small enough to be disposed of in a 5 gal pal. The line was cut with a Ridgid Model 104 manual pipe cutter (using the manipulators of course).

This pieces constitute the bulk of the field in the hot cell and will be disposed of with the next spent target.

Entry  Wednesday, October 21, 2015, 09:49, chad fisher, South Hot-Cell, Repair, , , Manipulator handle repair 

Rebuild handle of manipulator serial 7986 (currently in the east position) and replaced broken snap ring 5555-18h on west side of the handle underneath motion switch.

Entry  Friday, October 23, 2015, 07:41, Dan McDonald, Spent Target Vault, Maintenance, , , F-308's 

Six F-308's where received from Nordion #6,#15,#13,#16 all contained contamination. Loose contamination was removed with some fixed contamination remaining levels are low enough to allow the transport of spent targets. flasks where serviced as per Nordion Document IS/PP 0009 F308, IS/PP 0981 F308. Flasks are now located in the north hot cell area.

Entry  Friday, October 23, 2015, 11:30, chad fisher, South Hot-Cell, Standard Operation, , ZrC#7, ZrC#7 Spent Move and Febiad Coil 

ZrC#7 was transfered to a spent target disposal pail today and removed from the hot cell. The "hot" end of the TM4 coil end was also disposed of in the same pail (#129)

Entry  Friday, October 23, 2015, 11:40, Travis Cave, Spent Target Vault, Standard Operation, , ZrC #7, Spent target moved Vault_Storage_October_23_2015.pdf

The spent ZrC#7 target has been moved from the south hot cell to the spent target vault. The target was placed in pail #129 and then placed in slot 3B of the vault, it was 157mSv/hr upon removal from the south hot cell.

Entry  Thursday, October 29, 2015, 13:59, Travis Cave, Spent Target Vault, Standard Operation, , , Filling F-308s 

Five F-308s have been filled with the spent targets. The F-308s have been moved to the hall way between the north and south hot cell areas.

Entry  Monday, November 16, 2015, 08:04, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp

Update TH schedule according to changes. See attachment 1,2 .

update TH schedule weekly. See attachments 3,4

Entry  Monday, November 16, 2015, 10:33, Anders Mjos, Conditioning Station, Standard Operation, , FEBIAD Test Target, HV conditioning by ISAC operators 

ISAC operators attempted HV conditioning over the weekend.

https://web.accel.triumf.ca/isac_elog/Elog_show_result.pl?inid=218447&style=entry

 

Entry  Tuesday, November 24, 2015, 13:54, chad fisher, South Hot-Cell, Repair, , , Cell Decon 

Decon/removal of large solid waste was performed on Wednesday November 18th."Hot" activated items included containment box cover from TM2, Febiad coil line remnants from TM4 (the hottest ends were previously cut off and disposed of), some target conductor bolts, steerer plugs from TM2, target material remn.

Drum containing these solid items is 2.5mSv/hr at 1/2m.

Drum is stored in the north hot cell temp.

Compressible waste will require another drum.

Swipes were taken of the window... 170k counts per minute of cont.

Entry  Tuesday, November 24, 2015, 14:00, chad fisher, South Hot-Cell, Repair, , , Compressible waste sorting. 20151124_101547.jpg

Residual fields from the remaining compressible waste were still too high (as far as I'm concerned) so I have unpacked all compressible waste looking for a "hot" item that has snuck into these items.

I have a hand full of small bolts (possible target components), a hand full of target material/dust (including an entire target disc), and some cloths that had clearly been used to wipe the table (they are black with target dust).

These items will be disposed of with the next spent target.

Entry  Tuesday, November 24, 2015, 14:02, chad fisher, South Hot-Cell, Repair, , , Left Manip repair 

electronics package on left manip died completely yesterday (it has been going for a while).

Disconnected entire package and replaced with package from "spare" manipulator.

everything is back up and working.