  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015I attach new Target Hall schedules here
for 2015 fall and winter runs (beam schedule
129). The TH excel sheet schedule for beam
 Target_Hall_shedule_129_Sep_to_Dec.xlsxTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1066   Thursday, September 10, 2015, 08:59 chad fisherSouth Hot-CellRepair  Manipulator Mait. and field check Sept. 4Hot cell was entered for preventative mait.
on left manip. field measurements around
the cell were taken in prep. for window removal
  
  1075   Tuesday, September 22, 2015, 13:15 David WangSouth Hot-CellStandard Operation Ta#46Leak check on TM4 HS water line with new Ta#46 target. at SHCChad and I leak checked the HS line at
SHC. No leak. Leak rate 0.0xE-9atm.cc/sec.
  
  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015weekly update see attachment  Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1083   Friday, September 25, 2015, 08:21 Travis CaveSouth Hot-CellStandard Operation UC#13Spent Target moveThe spent UC#13 target has been moved from
the south hot cell to the ISAC spent target
vault. It was placed pail #128 and in tray
 Vault_Storage_September_24_2015.pdf 
  1089   Thursday, October 01, 2015, 09:18 Travis CaveSpent Target VaultStandard Operation  Targets transfered to mini storage.In preparation for shipping of the spent
targets five have been moved to the mini
storage. The following target were moved
  
  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance will be performed Tuesday October
6th
Tuesday, October 06, 2015: Maintenance
  
  1097   Tuesday, October 13, 2015, 10:53 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Weekly update schedule. TM3 evaluation
schedule in Nov is added.  
update the schedule after  the
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1108   Tuesday, October 20, 2015, 12:49 Dan McDonaldITWStandard Operation SiC#32Tm2 hook up In ITWLower and disconnect TM2 from crane in
ITW, proceed with hooking up TM2 as per checklist
with Anders. Double check flow meters and
  
  1109   Tuesday, October 20, 2015, 13:52 chad fisherSouth Hot-CellMaintenance  TM4 Febiad coil line disposalThe febiad coil line removed from TM4 has
been cut into pieces small enough to be disposed
of in a 5 gal pal. The line was cut with
 20151020_133045.jpg20151020_134303.jpg 
  1110   Wednesday, October 21, 2015, 09:49 chad fisherSouth Hot-CellRepair  Manipulator handle repairRebuild handle of manipulator serial 7986
(currently in the east position) and replaced
broken snap ring 5555-18h on west side of
  
  1112   Friday, October 23, 2015, 07:41 Dan McDonaldSpent Target VaultMaintenance  F-308'sSix F-308's where received from Nordion
#6,#15,#13,#16 all contained contamination.
Loose contamination was removed with some
  
  1113   Friday, October 23, 2015, 11:30 chad fisherSouth Hot-CellStandard Operation ZrC#7ZrC#7 Spent Move and Febiad CoilZrC#7 was transfered to a spent target
disposal pail today and removed from the
hot cell. The "hot" end of the
  
  1114   Friday, October 23, 2015, 11:40 Travis CaveSpent Target VaultStandard Operation ZrC #7Spent target movedThe spent ZrC#7 target has been moved from
the south hot cell to the spent target vault.
The target was placed in pail #129 and then
 Vault_Storage_October_23_2015.pdf 
  1115   Thursday, October 29, 2015, 13:59 Travis CaveSpent Target VaultStandard Operation  Filling F-308sFive F-308s have been filled with the spent
targets. The F-308s have been moved to the
hall way between the north and south hot
  
  1124   Monday, November 16, 2015, 08:04 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Update TH schedule according to changes.
See attachment 1,2 .
update TH schedule weekly. See attachments
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1126   Monday, November 16, 2015, 10:33 Anders MjosConditioning StationStandard Operation FEBIAD Test TargetHV conditioning by ISAC operatorsISAC operators attempted HV conditioning
over the weekend.
https://web.accel.triumf.ca/isac_elog/Elog_show_result.pl?inid=218447&style=entry
  
  1129   Tuesday, November 24, 2015, 13:54 chad fisherSouth Hot-CellRepair  Cell DeconDecon/removal of large solid waste was
performed on Wednesday November 18th."Hot"
activated items included containment box
  
  1130   Tuesday, November 24, 2015, 14:00 chad fisherSouth Hot-CellRepair  Compressible waste sorting.Residual fields from the remaining compressible
waste were still too high (as far as I'm
concerned) so I have unpacked all compressible
 20151124_101547.jpg 
  1131   Tuesday, November 24, 2015, 14:02 chad fisherSouth Hot-CellRepair  Left Manip repairelectronics package on left manip died
completely yesterday (it has been going for
a while).
  