ID Date Author Category Type Moduledown Target/Number Subject
  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.

Weekly update of Target Hall Schedule.See Attachments 3,4

Attachment 1: Target_Hall_shedule_129_Sep_to_Dec.xlsx
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 5: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1066   Thursday, September 10, 2015, 08:59 chad fisherSouth Hot-CellRepair  Manipulator Mait. and field check Sept. 4

Hot cell was entered for preventative mait. on left manip. field measurements around the cell were taken in prep. for window removal in January and left/south light bulb changed.

Hottest item in the cell was the conductor block end of the TM4 febiad coil line. It was 70 mSv/H on contact and seemed to be the major source of field in the hot cell. The waterblock end of this line did not apper to be hot.

  1075   Tuesday, September 22, 2015, 13:15 David WangSouth Hot-CellStandard Operation Ta#46Leak check on TM4 HS water line with new Ta#46 target. at SHC

Chad and I leak checked the HS line at SHC. No leak. Leak rate 0.0xE-9atm.cc/sec.

  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

weekly update see attachment

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1083   Friday, September 25, 2015, 08:21 Travis CaveSouth Hot-CellStandard Operation UC#13Spent Target move

The spent UC#13 target has been moved from the south hot cell to the ISAC spent target vault. It was placed pail #128 and in tray spot 1A. It was 21.5mSv/hr upon removal from the hot cell. See attached PDF for details.

Attachment 1: Vault_Storage_September_24_2015.pdf
Vault_Storage_September_24_2015.pdf Vault_Storage_September_24_2015.pdf Vault_Storage_September_24_2015.pdf Vault_Storage_September_24_2015.pdf
  1089   Thursday, October 01, 2015, 09:18 Travis CaveSpent Target VaultStandard Operation  Targets transfered to mini storage.

In preparation for shipping of the spent targets five have been moved to the mini storage. The following target were moved to the mini storage, SiC#26, Ta#36, UC#9,10,11.

  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance

 will be performed Tuesday October 6th

Tuesday, October 06, 2015: Maintenance re-schedlued for Wednesday October 7th

  1097   Tuesday, October 13, 2015, 10:53 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update schedule. TM3 evaluation schedule in Nov is added.  

update the schedule after  the cancellation of TM2 from SHC to CS trip.see attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1108   Tuesday, October 20, 2015, 12:49 Dan McDonaldITWStandard Operation SiC#32Tm2 hook up In ITW

Lower and disconnect TM2 from crane in ITW, proceed with hooking up TM2 as per checklist with Anders. Double check flow meters and coils, reset TP1 and TP2

  1109   Tuesday, October 20, 2015, 13:52 chad fisherSouth Hot-CellMaintenance  TM4 Febiad coil line disposal

The febiad coil line removed from TM4 has been cut into pieces small enough to be disposed of in a 5 gal pal. The line was cut with a Ridgid Model 104 manual pipe cutter (using the manipulators of course).

This pieces constitute the bulk of the field in the hot cell and will be disposed of with the next spent target.

Attachment 1: 20151020_133045.jpg
20151020_133045.jpg
Attachment 2: 20151020_134303.jpg
20151020_134303.jpg
  1110   Wednesday, October 21, 2015, 09:49 chad fisherSouth Hot-CellRepair  Manipulator handle repair

Rebuild handle of manipulator serial 7986 (currently in the east position) and replaced broken snap ring 5555-18h on west side of the handle underneath motion switch.

  1112   Friday, October 23, 2015, 07:41 Dan McDonaldSpent Target VaultMaintenance  F-308's

Six F-308's where received from Nordion #6,#15,#13,#16 all contained contamination. Loose contamination was removed with some fixed contamination remaining levels are low enough to allow the transport of spent targets. flasks where serviced as per Nordion Document IS/PP 0009 F308, IS/PP 0981 F308. Flasks are now located in the north hot cell area.

  1113   Friday, October 23, 2015, 11:30 chad fisherSouth Hot-CellStandard Operation ZrC#7ZrC#7 Spent Move and Febiad Coil

ZrC#7 was transfered to a spent target disposal pail today and removed from the hot cell. The "hot" end of the TM4 coil end was also disposed of in the same pail (#129)

  1114   Friday, October 23, 2015, 11:40 Travis CaveSpent Target VaultStandard Operation ZrC #7Spent target moved

The spent ZrC#7 target has been moved from the south hot cell to the spent target vault. The target was placed in pail #129 and then placed in slot 3B of the vault, it was 157mSv/hr upon removal from the south hot cell.

Attachment 1: Vault_Storage_October_23_2015.pdf
Vault_Storage_October_23_2015.pdf Vault_Storage_October_23_2015.pdf Vault_Storage_October_23_2015.pdf Vault_Storage_October_23_2015.pdf
  1115   Thursday, October 29, 2015, 13:59 Travis CaveSpent Target VaultStandard Operation  Filling F-308s

Five F-308s have been filled with the spent targets. The F-308s have been moved to the hall way between the north and south hot cell areas.

  1124   Monday, November 16, 2015, 08:04 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Update TH schedule according to changes. See attachment 1,2 .

update TH schedule weekly. See attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1126   Monday, November 16, 2015, 10:33 Anders MjosConditioning StationStandard Operation FEBIAD Test TargetHV conditioning by ISAC operators

ISAC operators attempted HV conditioning over the weekend.

https://web.accel.triumf.ca/isac_elog/Elog_show_result.pl?inid=218447&style=entry

 

  1129   Tuesday, November 24, 2015, 13:54 chad fisherSouth Hot-CellRepair  Cell Decon

Decon/removal of large solid waste was performed on Wednesday November 18th."Hot" activated items included containment box cover from TM2, Febiad coil line remnants from TM4 (the hottest ends were previously cut off and disposed of), some target conductor bolts, steerer plugs from TM2, target material remn.

Drum containing these solid items is 2.5mSv/hr at 1/2m.

Drum is stored in the north hot cell temp.

Compressible waste will require another drum.

Swipes were taken of the window... 170k counts per minute of cont.

  1130   Tuesday, November 24, 2015, 14:00 chad fisherSouth Hot-CellRepair  Compressible waste sorting.

Residual fields from the remaining compressible waste were still too high (as far as I'm concerned) so I have unpacked all compressible waste looking for a "hot" item that has snuck into these items.

I have a hand full of small bolts (possible target components), a hand full of target material/dust (including an entire target disc), and some cloths that had clearly been used to wipe the table (they are black with target dust).

These items will be disposed of with the next spent target.

Attachment 1: 20151124_101547.jpg
20151124_101547.jpg
  1131   Tuesday, November 24, 2015, 14:02 chad fisherSouth Hot-CellRepair  Left Manip repair

electronics package on left manip died completely yesterday (it has been going for a while).

Disconnected entire package and replaced with package from "spare" manipulator.

everything is back up and working.