ID Date Author Category Type Moduledown Target/Number Subject
  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filter

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.

The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.

  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Update Target Hall schedule after the changing on TM2 process. See attachment 1,2

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.

Dan and I moved 5 shielding blocks from ITE to block storage area. The move is smooth.

  1017   Monday, July 27, 2015, 15:46 David WangSouth Hot-CellStandard Operation  The yellow steel plug is put on SHC in TH

The yellow steel plug is put on SHC in TH. The spent target is inside the SHC.The field around the SHC area in TH is so high that we have put it on. It will be moved out on this Thursday just before the spent target move. 

  1020   Tuesday, July 28, 2015, 10:17 David WangITERepair  ITE TP4 has been replaced

Tony and I replaced the ITE TP4 turbo pump today. The pumping time on controller has been reset to 0. The replaced broken  pump is bagged and stored at west end of TH.

  1027   Thursday, July 30, 2015, 14:05 Travis CaveSpent Target VaultStandard Operation SiC#31Spent target moved

SiC#31 has been moved to the spent target vault. It is in pail #127 and placed in spot 3C of the vault is was 489mSv/hr when removed from the south hot cell. See attached pdf for vault status

Attachment 1: Vault_Storage_July_30_2015.pdf
Vault_Storage_July_30_2015.pdf Vault_Storage_July_30_2015.pdf Vault_Storage_July_30_2015.pdf Vault_Storage_July_30_2015.pdf
  1028   Friday, July 31, 2015, 09:47 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Weekly update of Target Hall schedule after so many jobs have been finished in this week.  See attachment 1, 2

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1029   Thursday, August 06, 2015, 10:26 Travis CaveSpent Target VaultStandard Operation  Spent Target Measurments and Assays

All targets but one ( SiC#31 went in last week) have been measured or assayed. See attached PDF for the details.

Attachment 1: Vault_Storage_August_6_2015.pdf
Vault_Storage_August_6_2015.pdf Vault_Storage_August_6_2015.pdf Vault_Storage_August_6_2015.pdf Vault_Storage_August_6_2015.pdf
  1031   Friday, August 07, 2015, 10:01 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 19 2015

Weekly update target hall schedule and activities. See attachment 1,2

Update and extend Target Hall schedule to Sep 08.  See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
  1048   Wednesday, August 26, 2015, 09:54 Anders MjosConditioning StationMaintenance  Topped up water in TCS:TK2

 Filled to 24.9 in

  1061   Tuesday, September 01, 2015, 16:55 Anders MjosConditioning StationMaintenance  TBHT power supply remvoed

 The power supply is needed as a spare for the failed TGHT p/s in ITW

  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.

Weekly update of Target Hall Schedule.See Attachments 3,4

Attachment 1: Target_Hall_shedule_129_Sep_to_Dec.xlsx
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 5: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1066   Thursday, September 10, 2015, 08:59 chad fisherSouth Hot-CellRepair  Manipulator Mait. and field check Sept. 4

Hot cell was entered for preventative mait. on left manip. field measurements around the cell were taken in prep. for window removal in January and left/south light bulb changed.

Hottest item in the cell was the conductor block end of the TM4 febiad coil line. It was 70 mSv/H on contact and seemed to be the major source of field in the hot cell. The waterblock end of this line did not apper to be hot.

  1075   Tuesday, September 22, 2015, 13:15 David WangSouth Hot-CellStandard Operation Ta#46Leak check on TM4 HS water line with new Ta#46 target. at SHC

Chad and I leak checked the HS line at SHC. No leak. Leak rate 0.0xE-9atm.cc/sec.

  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

weekly update see attachment

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1083   Friday, September 25, 2015, 08:21 Travis CaveSouth Hot-CellStandard Operation UC#13Spent Target move

The spent UC#13 target has been moved from the south hot cell to the ISAC spent target vault. It was placed pail #128 and in tray spot 1A. It was 21.5mSv/hr upon removal from the hot cell. See attached PDF for details.

Attachment 1: Vault_Storage_September_24_2015.pdf
Vault_Storage_September_24_2015.pdf Vault_Storage_September_24_2015.pdf Vault_Storage_September_24_2015.pdf Vault_Storage_September_24_2015.pdf
  1089   Thursday, October 01, 2015, 09:18 Travis CaveSpent Target VaultStandard Operation  Targets transfered to mini storage.

In preparation for shipping of the spent targets five have been moved to the mini storage. The following target were moved to the mini storage, SiC#26, Ta#36, UC#9,10,11.

  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance

 will be performed Tuesday October 6th

Tuesday, October 06, 2015: Maintenance re-schedlued for Wednesday October 7th

  1097   Tuesday, October 13, 2015, 10:53 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update schedule. TM3 evaluation schedule in Nov is added.  

update the schedule after  the cancellation of TM2 from SHC to CS trip.see attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp