Monday, December 05, 2016, 10:04, Aurelia Laxdal, Conditioning Station, Repair, TM3, , TM3 vacuum system have been connected at TCS.
|
David Wang wrote:
All water circuits are by passed on the top of TM3. Water pumps and vacuum turbo- pumps are started. |
Monday, December 05, 2016, 10:10, David Wang, ITW, Standard Operation, TM2, , Five shielding blocks have been transferred from ITE to ITW.
|
The ITW is configured to take proton beam. |
Friday, December 09, 2016, 14:58, Isaac Earle, North Hot-Cell, Development, , , NHC service area floor and top of roof block painted
|
The concrete floor in the North Hot Cell service area and the top of the NHC roof block in the target hall have been painted with Macropoxy 646
oil based epoxy paint, colour Flint Grey. Two coats were used for the NHC roof, and one for the service area floor.
|
Friday, December 09, 2016, 18:05, Aurelia Laxdal, Conditioning Station, Repair, TM3, , TM3 vacuum system have been connected at TCS.
|
Aurelia Laxdal wrote:
|
Wednesday, January 04, 2017, 14:27, David Wang, Conditioning Station, Standard Operation, , , started TCS vacuum pump
|
TCS TP1S has been started.
2017-01-23 afternoon: Stopped TP1S. We will use TCS to take TM2 tomorrow afternoon. |
Thursday, January 12, 2017, 14:24, David Wang, ITW, Standard Operation, TM2, , ITW primary and secondary vacuum vessel winter shut down leak check.
|
TM2 is located in ITW for this leak check. Leak detector is installed between ITW BV2s as before. LD base leak rate 0.0XE-9atm.cc/sec, base pressure
0.0XE-4 Torr. First , I leak checked dump module top flange seal which a small leak was found in last year winter shut down. This time,all ITW turbo-pumps
cooling fans are switched off during the check. Lots helium are sprayed around the dump module top flange this time. I did not see any response on LD. |
Monday, January 16, 2017, 09:32, David Wang, ITW, Standard Operation, TM2, , Helium pressure test on TM2 water llines at ITW
|
TM2 helium pressure test result at ITW. 70 psi helium 3 minutes on each circuit. LD base LR0.0XE-9atm.cc/sec BP 0.0XE-4torr. ITW IG1 1.22Xe-7
torr, ITW IG1S 1.31XE-7torr, ITW PNG4 2.66XE-6Torr(ITW TP4 off).
|
Tuesday, January 17, 2017, 13:45, Isaac Earle, North Hot-Cell, Development, , , NHC ducting installed
|
The new ducting section connecting the existing duct termination in the TCS space to the NHC partition wall has been installed by Smith Sheet Metal
contractors. The installation drawing is IRH1618. There was not enough clearance between the duct pipe and the TCS vessel to butt weld the
new ductwork as originally intended. Instead a flange was welded to the existing pipe and also to the new section and the two were bolted together. |
Wednesday, January 18, 2017, 09:55, David Wang, ITE, Standard Operation, TM4, , ITE and TM4 2017 winter shut down leak check.
|
ITE and TM4 2017 winter shut down leak check are finished. All ITE primary, secondary vacuum vessel and TM4 water lines are good. No any leak has been
found. |
Wednesday, January 18, 2017, 11:53, Isaac Earle, North Hot-Cell, Development, , , NHC partition wall installation complete
|
The final panels of the partition wall were installed today as per drawing IRH1609. Sealing, finishing, and painting of the NHC walls and
floor can now commence.
|
Thursday, January 19, 2017, 10:15, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for 2017 winter shut down
|
Updated target hall schedule for 2017 winter shut down. See attachments 1,2
Update schedule after Febiad beam schedule changed to ITE. See attachments 3,4 |
Tuesday, January 24, 2017, 15:24, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 electrical check and leack check.
|
I did electrical check before and after Fefiad target installation on TM2. The RU (coil) Is till short to 60KV as before. Other result are good. After
Febiad target is installed, Tm2 HS line is leak checked. On leak detector, base leak rate pumping down is much slow than before. The base pressure
still could be pumped down to 0.0XE-4 torr. After a long time wait, Chad and I leak checked at 2.2XE-8 atm.cc/sec base leak rate. Chad sprayed lots |
Tuesday, January 24, 2017, 15:29, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been moved to TCS .
|
I connected TCS vacuum system to TM2. The station is under roughing now. All turbo pumps will be started soon. |
Tuesday, January 24, 2017, 15:32, David Wang, ITW, Standard Operation, TM2, , TM2 was moved from ITW to SHC this morning.
|
The move is smooth. Yasmine and Travis did the move. |
Friday, January 27, 2017, 08:50, chad fisher, South Hot-Cell, Standard Operation, , , UCx#18 and Ta#50 autopsy and spent target move
|
On Thursday, January 26th UCx#18 and Ta#50 were inspected and packaged into spent target pails, move to storage vault. |
Friday, January 27, 2017, 10:52, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been moved from TCS to ITE
|
The move is successful. |
Wednesday, February 01, 2017, 12:23, David Wang, ITE, Standard Operation, TM2, , TM2 has been connected in ITE.
|
TM2 has been connected in ITE. The SST window water lines in ITE can not be connected properly to TM2. The water line connector on TM2 window is 90 degree
CCW installed in direction comparing to TM4.This caused the problem. Solution: Two piece of flexible lines and extra male QC adapters have been used to
fix this issue. HV cover and HV fence in ITE work with TM2. Other connections are good as well. |
Friday, February 03, 2017, 11:49, David Wang, Conditioning Station, Standard Operation, , , Update 2017 winter shutdown TH schedule.
|
Update 2017 winter shut down target hall schedule. See attachments |
Tuesday, February 07, 2017, 10:34, David Wang, ITW, Maintenance, , , ITW clean up
|
ITW has been cleaned up today. All station are vacuum cleaned. I wiped all HV cover and HV area including conductors and insulators. The black
foams which are used to wrap around TP back up line are degrading now. I removed most of these foams. Also, Some obsolete water lines are moved
our of station. All waste are bagged . they will be surveyed and stored(or disposed) according to radio-active level. |
Tuesday, February 07, 2017, 15:57, Isaac Earle, North Hot-Cell, Development, , , Ventilation Ducting Gasket Installed
|
Lead gasket IRH1633 was installed today according to assembly drawing IRH1618 Rev B. |
|