Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 103 of 141  Not logged in ELOG logo
ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  523   Thursday, October 24, 2013, 11:31 Travis CaveSpent Target VaultStandard Operation UC#7Spent target moveUC #7 has been moved from the south hot
cell to the spent target vault, it was placed
in pail #110 and put in slot 8B of the vault,
 Vault_Storage_October_24_2013.pdf 
  541   Tuesday, November 12, 2013, 14:33 Bevan MossConditioning StationRepair  Cooling manifold returned The cooling manifold for the conditioning
station high power water cooled lines has
been returned. The cooling package can once
  
  547   Monday, November 18, 2013, 16:44 Bevan MossConditioning StationStandard Operation  Testing of cooling package I have tested all of the compressors
for TCS. All are operational and cycled as
they should. 
  
  549   Tuesday, November 19, 2013, 14:24 David WangITERepair  ITE TP3Hi
all, The old  ITE  TP3 pump is
moved out and the new pump is  in
  
  555   Friday, November 22, 2013, 10:29 Travis CaveSpent Target VaultStandard Operation NiO#2Spent target moveNiO#2 has been moved from the south hot
cell into spent target storage. It was placed
in pail 111 in slot 3C of the storage vault.
 Vault_Storage_November_22_2013.pdf 
  557   Tuesday, November 26, 2013, 14:10 Travis CaveCraneMaintenance  Thermal relay replacedThe bad thermal motor protection relay
for the crane has been replaced with a new
unit. Crane was tested in pendant(local)
  
  564   Tuesday, December 03, 2013, 10:35 Travis CaveITWStandard Operation  fields above and in the target station with blocks offThe blocks have been removed from the west
target station. The fields at the top of
the target pit at the railing at waist level
  
  576   Monday, December 09, 2013, 13:15 Travis CaveSpent Target VaultStandard Operation Ta#41Spent target moveThe spent Ta#41 target has been moved from
the south hot cell to the spent target storage
vault. It is an unnumbered pail (should be
 Vault_Storage_December_9_2013.pdf 
  579   Thursday, January 09, 2014, 11:07 chad fisherSouth Hot-CellMaintenance  Field LevelI have managed to reduce the field at the
broken manipulator from 12 mSv/h to 400 uSv/h.
  
  580   Thursday, January 16, 2014, 10:36 chad fisherSouth Hot-CellRepair  East Manipulator RepairThe repair/cable replacement on the east
manipulator is now complete.
Yesterday's initail cable replacement
 Manip_repair_20140114.jpgManip_repair_20140115.jpg 
  583   Monday, January 20, 2014, 13:40 maicodallavalleSpent Target VaultMaintenance F-308Empty F-308sFour empty F-308s just arrived back at
Triumf. I moved them  from shipping
to the Remote Handling Shop for service and
  
  586   Wednesday, January 22, 2014, 10:51 David WangITERepair  Removed 4 shielding blocks located on top of preseperator in THTravis and I removed 4 shielding blocks
located on top of pre-seperator  in
TH. This is a job for ITE harp 9 re-installation
  
  587   Wednesday, January 22, 2014, 15:00 Travis CaveSpent Target VaultStandard Operation UC#8Spent target moveUC#8 has been moved from the south hot
cell to the vault storage. It was placed
in pail 113 and placed in slot 8A of the
 Vault_Storage_January_22_2014.pdf 
  588   Wednesday, January 22, 2014, 15:20 Anders MjosSouth Hot-CellStandard Operation UC#8Target Inspection - post beamThe Target Assembly was inspected with
Chad, Jens Henning and Anders today.

    The Target Container was
  
  590   Monday, February 03, 2014, 14:45 Travis CaveSpent Target VaultStandard Operation  Spent targets to mini storage and the F-308s to the Target HallTargets NiO#1(101), Nb#5(85), TaC#1(92),
and ZrC#5(81) have been moved from the storage
vault and placed in the mini storage. The
 Vault_Storage_February_3_2014.pdfMini_Vault_Storage_February_3_2014.pdf 
  594   Wednesday, February 05, 2014, 14:12 Travis CaveSpent Target VaultStandard Operation  Targets moved from mini storage to F-308sAll targets in the mini storage (4) have
been moved from there and placed into the
F-308s and those have been moved to the mech
  
  618   Tuesday, March 11, 2014, 10:47 Travis CaveITERepair  entrance module moveITE entrance module has been moved from
the east station to the south east silo.
  
  620   Wednesday, March 12, 2014, 16:33 Keith C NgITERepair  2A3 window removal and replacementprep'ed area for work:
- removed shield plug from window
clamp area
 20140312_2a3window_RHB_6676.JPG20140312_2a3window_RHB_6682.JPG2a_bp_sw1_white_powder_under_w11.PDF2a_bp_sw2_white_powder_under_w11.PDF2a_bp_sw3_rust_w11.PDF 
  622   Thursday, March 13, 2014, 16:23 Keith C NgITERepair  2a3 window - inspectionVideo inspected 2a3 window joint this morning.
Screenshots from video showing debris
forming around aluminum cradle and brown/red
 Fullscreen_capture_03132014_41458_PM.bmp.jpgFullscreen_capture_03132014_41527_PM.bmp.jpg 
  623   Monday, March 17, 2014, 15:39 Keith C NgITERepair  2a3 window - prep and cleanCleaned top of the ITE vacuum flange and
top of window clamp. Attempted to clean the
bellows/beam pipe through the wall, mostly
  
ELOG V2.9.2-2455