  217   Wednesday, November 21, 2012, 09:36 Travis CaveSpent Target VaultStandard Operation  Spent target move

On Nov 20th the 5 targets in mini storage have been moved to the F-308s, those F-308s have since been moved to the hot cell ante room. They will sit there until Monday.

  223   Wednesday, December 05, 2012, 15:53 Anders MjosSouth Hot-CellStandard Operation UCx#5Target inspection - target tube broken

The target was inspected today.

It was found that the target tube had broken on both sides of the centre block in the region that contain target material. The Ta-foil heat shield was removed from the let side tube to allow inspection.

Photos can be found on DocuShare:
https://documents.triumf.ca/docushare/dsweb/View/Collection-9357

  224   Thursday, December 06, 2012, 08:57 Travis CaveSpent Target VaultStandard Operation UCx#5Spent target move

UCx #5 has been moved from the south hot cell to the storage vault. It is in Pail 102, in spot 2A of the vault and had a field of 32.6mSv/hr upon extraction from the south hot cell. See attached PDF for vault details.

Attachment 1: Vault_Storage_December_6_2012.pdf
Vault_Storage_December_6_2012.pdf Vault_Storage_December_6_2012.pdf Vault_Storage_December_6_2012.pdf Vault_Storage_December_6_2012.pdf
  229   Thursday, January 10, 2013, 10:40 David WangITWMaintenance  Replaced all high active water system magnetic pedal wheels in ITW and ITE.

I replaced all high active water system magnetic pedal wheels in ITW and ITE. This is a preventive maintenance job we planned for this winter shut down.

  232   Tuesday, January 15, 2013, 14:37 Travis CaveSpent Target VaultStandard Operation TiC#3Spent target move

TiC #3 was moved from the south hot cell in to the vault storage today, it was placed in slot 4B and was in pail #104, it had a reading of 98.7mSv/hr upon removal from the south hot cell. See attached PDF for vault details.

Attachment 1: Vault_Storage_January_15_2013.pdf
Vault_Storage_January_15_2013.pdf Vault_Storage_January_15_2013.pdf Vault_Storage_January_15_2013.pdf Vault_Storage_January_15_2013.pdf
  233   Thursday, January 17, 2013, 10:06 chad fisherSouth Hot-CellStandard Operation  SiC Test Target for TM4/CS

I have inserted the test target for TM4 and the CS into the hot cell.

I had some concerns about the condition of the target which I have discussed with Pierre and he has cleared. Pictures are attached.

Attachment 1: IMG_0909[1].JPG
IMG_0909[1].JPG
Attachment 2: IMG_0910[1].JPG
IMG_0910[1].JPG
Attachment 3: IMG_0911[1].JPG
IMG_0911[1].JPG
Attachment 4: IMG_0912[1].JPG
IMG_0912[1].JPG
Attachment 5: IMG_0913[1].JPG
IMG_0913[1].JPG
Attachment 6: IMG_0914[1].JPG
IMG_0914[1].JPG
Attachment 7: IMG_0915[1].JPG
IMG_0915[1].JPG
Attachment 8: IMG_0916[1].JPG
IMG_0916[1].JPG
Attachment 9: IMG_0917[1].JPG
IMG_0917[1].JPG
Attachment 10: IMG_0918[1].JPG
IMG_0918[1].JPG
Attachment 11: IMG_0919[1].JPG
IMG_0919[1].JPG
Attachment 12: IMG_0920[1].JPG
IMG_0920[1].JPG
Attachment 13: IMG_0921[1].JPG
IMG_0921[1].JPG
Attachment 14: IMG_0922[1].JPG
IMG_0922[1].JPG
Attachment 15: IMG_0923[1].JPG
IMG_0923[1].JPG
Attachment 16: IMG_0924[1].JPG
IMG_0924[1].JPG
  241   Monday, January 28, 2013, 12:26 Travis CaveConditioning StationDevelopment  Switches connected

the switches and the solenoid are all wire up to 24VDC, when you open either of the little doors the solenoid switches this is also true if there is a power loss. currently the solenoid is powered.

  243   Friday, February 08, 2013, 11:42 Grant MinorITEMaintenance  TAPC 477 resolved - ISAC elec. room gas cylinder

See attached TAPC 477 documentation.

Attachment 1: TAPC-477_resolved_8Feb2013.pdf
TAPC-477_resolved_8Feb2013.pdf TAPC-477_resolved_8Feb2013.pdf TAPC-477_resolved_8Feb2013.pdf
  244   Thursday, February 14, 2013, 09:31 David WangITWRepair  ITH MP1 is replaced.

Edi and I replaced the broken ITH MP1 in target hall with a new pump. The old pump was leak on oil. There were no oil had been left in the old pump by checking the sight glass.Thats the reason of  the pump  failure.The tray which the old pump sat on was full of leaking oil ( highly contaminated ). The old pump was bagged in 3 thick plastic bags ,and the tray was cleaned before the new pump was installed. The working area had been cleaned up and surveyed couple of times after the job. Everything is good. The new pump had been tested after the installation. It works fine.

  252   Wednesday, March 06, 2013, 10:09 Travis CaveITWMaintenance  module move

ITW EX1 has been moved from the west target station to the south hot cell for the seal replacement on the west station.

  253   Wednesday, March 06, 2013, 12:50 Travis CaveSouth Hot-CellMaintenance  module move

ITW EX1 have been moved back to the west target station from the south hot cell.

  254   Wednesday, March 06, 2013, 14:12 David WangITWRepair  ITW EXIT1 tank to module o-ring replacement
 ITW EXIT1 o-ring replacement is fininshed today. The ITW EXIT 1 is back to ITW. The old o-ring lost most its elastic property and changed to stiff sqaure shape inside the slot.The flange surface around the o-ring slot was dirty. I cleaned the o-ring surface completely before putting the new o-ring . Everything should be fine now. There will be a leak check late on this new installed o-ring.
  259   Wednesday, March 13, 2013, 14:30 Bevan MossConditioning StationDevelopment  Faraday Cup

 Dave Morris and I investigated the Faraday Cup today. It was found to be plumed in the wrong direction (fails in). This is not an issue for the conditioning station as there is nothing down stream from the cup. Dave will change the controls to reflect this.

  318   Wednesday, April 24, 2013, 09:00 Bevan MossConditioning StationDevelopment  New user testing

 Controls has created a new user group that can operate the conditioning station but cannot use any of the bypasses or forces. The cooling package will be used to test this new profile. The main loop bypass has been opened to allow this testing to happen without the risk of over pressure.

  320   Wednesday, April 24, 2013, 10:36 maicodallavalleSpent Target VaultMaintenance  F-308

The F-308's have been serviced and are ready to be filled. All inspection records are stored  in docushare.

https://documents.triumf.ca/docushare/dsweb/View/Collection-1085
  334   Thursday, May 09, 2013, 10:13 chad fisherSouth Hot-CellDevelopment  Mock-up Progress

The source tray for the mock-up has been setup for waterline bending and soldering/brazing.

Thanks to Travis for finding the photos for the TM3 rebuild that took place in the anteroom in 09' and Maico and Dan for the support in ironing the issues with the source tray side soldering issues.

 

Attachment 1: IMG_1056[1].JPG
IMG_1056[1].JPG
Attachment 2: IMG_1057[1].JPG
IMG_1057[1].JPG
Attachment 3: IMG_1058[1].JPG
IMG_1058[1].JPG
  345   Wednesday, May 15, 2013, 10:20 Bevan MossConditioning StationRepair  Roof top chiller failed

I have been getting a fault on the roof top chiller for the 2 tandem 7.5 ton chillers. I have checked and we have water flow and the temperatures are nowhere near freezing. I believe they are over heating as the fans on that side are not coming on. The blades are free to turn by hand but the VFD controller keeps saying off. I have tried turning it on and off and that also did nothing. I have contacted ESC for further advice.

  346   Wednesday, May 15, 2013, 10:25 Bevan MossConditioning StationRepair  ONICON flow meter

 Scott Adair from Riada sales came to site to complete diagnostics on the ONICON flow meter. He could not determine the problem and believes that there was a short in the head. He has taken the flow meter for what should be warranty repair. The flow meter is for diagnostics only, the conditioning station can still operate without it.

 

 

  347   Wednesday, May 15, 2013, 16:21 Bevan MossConditioning StationRepair  BIAS Current readings off by a factor of 5

 A special thanks to Kazuya, Jane and Ray who jumped on this issue right away! The limit of the BIAS PS was set as 20000uA when in reality it is 4000uA. The issue has now been corrected. Please remember to divide the current by 5 for any elogs older than this one.

  351   Friday, May 17, 2013, 10:04 chad fisherSouth Hot-CellRepair  Manipulator Repair

Manipulator has been sucessfully repaired. Recieved 0.19 mSv. Took Approx. 10-20 minutes