Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 106 of 138  Not logged in ELOG logo
  ID Date Author Category Type Module Target/Number Subject Text Attachments
  661   Thursday, May 15, 2014, 14:38 David WangITERepairTM3TM3Bias short on ITEAnders and I opened the HV cover in ITE
and did  a visual check inside ITE HV 
cover and top of TM3.Bill was with us and
  
  660   Wednesday, May 14, 2014, 19:01 Grant MinorITEMaintenanceTM3 HV short inspection at ITEFriedhelm Ames commented to me that there
appears to be a short between High Voltage
and Ground at TM3 at ITE.
  
  659   Wednesday, May 07, 2014, 10:15 David WangITERepairTM3 ITE TM3, entrance module and BL2A3 window flange seals leak check..ITE TM3, entrance module, and 2A3 window
flange seals have been leak checked this
morning after 2 new seals replacement.The
  
  658   Wednesday, May 07, 2014, 10:08 David WangITERepairTM3 ITE entrance module flange seal had been replaced.ITE entrance module flange seal had been
replaced yesterday.The flange and the seal
groove were cleaned with Acetone before the
 7x 
  657   Tuesday, May 06, 2014, 14:05 Travis CaveITEStandard Operation  module moveThe entrance module was out a new seal
went in and then the entrance module went
back, and then TM#3 went back. So all modules
  
  656   Monday, May 05, 2014, 13:11 David WangITERepairTM3  ITE Entrance module has been disconnected.ITE entrance module has been disconnected
and the lifting yoke is installed for module
move. See attached pictures.
 011.JPG025.JPG033.JPG035.JPG032.JPG 
  655   Monday, May 05, 2014, 13:05 David WangITERepairTM3 ITE target module flange seal has been replaced.ITE target module flange seal has been
replaced.The flan surface and the o-ring
groove have been cleaned with Acetone before
 004.JPG008.JPG008.JPG007.JPG 
  654   Monday, May 05, 2014, 10:40 Travis CaveITEStandard OperationTM3TiC#4module moveTM#3 with TiC#4 has been moved from the
east station to the south west silo.
  
  653   Wednesday, April 30, 2014, 12:03 Travis CaveSpent Target VaultStandard Operation 2A3 windowWindow now in vaultThe 2A3 window now has a lid, and lift
yolk on it and it has been installed in the
spent target vault in spot 2A. The lid is
 Vault_Storage_April_30_2014.pdf 
  652   Wednesday, April 16, 2014, 17:08 Keith C NgITERepair  2a3 window - He leak checkHelium leak checked 2a3 window after installing
using remote line: 
- There was a leak found between
  
  651   Wednesday, April 16, 2014, 10:16 Anders MjosITWDevelopmentTM3Ta#42Flow meters installed on Heat Shield and Coil water return 

    
  
  650   Tuesday, April 15, 2014, 08:53 Travis CaveITEStandard OperationTM3TiC#4module moveTM#3 with TiC#4 has been moved from the
conditioning station to the east target station.
  
  649   Monday, April 14, 2014, 13:58 David WangITERepair  Reconnected ITE entrance moduleI reconnected the entrance module back
to the ITE station. All diagnostic cables,
turbo- pump, air lines, water lines on ITE
  
  648   Monday, April 14, 2014, 11:57 Travis CaveITEStandard Operation  entrance module moveThe East Entrance module has been moved
from the south west silo to the east target
station. The move went well.
  
  647   Friday, April 11, 2014, 18:17 Keith C NgITERepair  2a3 window - installToday:
1) Installed new cradle and shortened
beam pipe section in wall penetration.
  
  646   Friday, April 11, 2014, 11:35 David WangConditioning StationStandard OperationTM3 Helium pressure test on TM3 HS water line with new Ta target. at CSThe helium pressure test on TM3 HS water
line with new Ta target is finished at CS.
The circuit is leak tight.. No any response
 6x 
  645   Thursday, April 10, 2014, 14:03 Bevan MossConditioning StationStandard OperationTM3TiC#4HV conditioning The TiC#4 target that is on TM3 was
conditioned to 25kV today with the EINZEL
lens at 12.5kV. There was one spark shortly
 10042014_Tm3_TiC#4_HV_conditioning.JPG10042014_TM3_TiC#4_HV_conditioning.txt 
  644   Wednesday, April 09, 2014, 11:10 David WangSouth Hot-CellStandard OperationTM3 TM3 heat shield circuit leack check at SHCThis Monday morning, Chad and I leak checked
heat shielding circuit on TM3 with new target
installed. The base LR on LD :0.0xE-9 atm.cc/sec,
  
  643   Tuesday, April 08, 2014, 09:05 Travis CaveSouth Hot-CellStandard OperationTM3TiC#4module moveTM#3 with TiC#4 has been moved from the
south hot cell to the conditioning station.
  
  642   Monday, April 07, 2014, 14:13 chad fisherSouth Hot-CellStandard OperationTM3TiC#4TiC#4 installationTiC#4 has been installed onto TM3   
ELOG V2.9.2-2455