  2633   Friday, July 05, 2024, 12:50 David WangSouth Hot-CellStandard OperationTM4TiC#7TM4 and TiC#7 target electrical check and HS leak check at SHC after target installation .TM4 and TiC#7 target electrical check and
HS leak check at SHC after target installation
have been done.  all results are good.
  
  2632   Thursday, July 04, 2024, 13:23 David WangSouth Hot-CellStandard OperationTM4UCx#45electrical check on TM4 UCx#45 target at SHC after operation. electrical check  on TM4 UCx#45 target
at SHC after operation is done.  
see attachment.
 Tm4_UCx_46_at_SHC_after_operatiom.pdf 
  2631   Thursday, July 04, 2024, 11:45 Frank SongITWStandard OperationTM4UCx#45module disconnectionTM4 with spent target UCx#45 was disconnected
in ITW and moved to SHC.
 TM4 move from ITW to SHC is
 TM4_with_Spent_Target_UCx#45_disconnection_in_ITW_2024-07-04.pdf 
  2630   Thursday, July 04, 2024, 01:20 Carla BabcockITEDevelopmentTM3SiC#46TM3 conditioning with protonsInitial Summary:
TM3 sparking behaviour in ITE has
been very disruptive both with and without
  
  2629   Wednesday, July 03, 2024, 14:01 David WangConditioning StationStandard OperationTM2 Tm2 has been moved from TCS to SW silo.Tm2 has been moved from TCS to SW silo.
the move is smooth.
  
  2628   Tuesday, July 02, 2024, 11:38 Frank SongITE/ITW/Storage AreaStandard Operation  shielding blocks transfer 5 shielding blocks have been moved
from ITW to ITE, MAA area has been secured.
  
  2627   Thursday, June 27, 2024, 09:49 David WangNorth Hot-CellStandard Operation Nb#10Nb#10target has been remotely transferred from NHC to SHC. Nb#10target has been remotely  transferred
from NHC to SHC.  
  
  2626   Wednesday, June 26, 2024, 13:49 David WangConditioning StationStandard OperationTM2 Tm2 has been moved from SW silo to TCS.Tm2 has been successfully moved from SW
silo to TCS. 
  
  2625   Tuesday, June 25, 2024, 12:49 Frank SongITEStandard OperationTM3SiC#46Module Connection TM3 with new target SiC#46 was connected
in ITE.
 TM3_with_SiC#46_connection_in_ITE_2024-06-25.pdf 
  2624   Tuesday, June 25, 2024, 11:59 David WangITEStandard OperationTM3SiC #46Tm3 has been moved from TCS to ITE.Tm3 has been moved from TCS to ITE. the
move is smooth.
  
  2623   Tuesday, June 25, 2024, 11:59 David WangITEStandard OperationTM3SiC #46Tm3 has been moved from TCS to ITE.Tm3 has been moved from TCS to ITE. the
move is smooth. 
  
  2622   Monday, June 24, 2024, 14:37 Carla BabcockSouth Hot-CellDevelopmentTM3UCx#44Inspection of TM3 and UCx#44 after no-protons runTM3 and UCx#44 ran in ITE but issues with
the cyclotron prevented proton beam delivery.
Nonetheless, the target was heated and provided
 MicrosoftTeams-image_(61).pngMicrosoftTeams-image_(62).pngMicrosoftTeams-image_(60).pngMicrosoftTeams-image_(63).png 
  2621   Wednesday, June 19, 2024, 14:16 David WangSouth Hot-CellStandard OperationTM3SiC #46Tm3 electrical check with SiC#46 target at SHCTm3 electrical check with SiC#46 target 
and HS line helium spray check at SHC. were
done. everything is good. see attachment.
 TM3_with_SiC_46#_target_electrical_check_at_SHC.pdf 
  2620   Wednesday, June 19, 2024, 14:11 David WangSouth Hot-CellStandard OperationTM3 TM3 has been moved from SHC to TCS.TM3 has been moved  from SHC to TCS.The
move is smooth. 
  
  2619   Wednesday, June 19, 2024, 08:10 David WangWaste Package/ShipDevelopment   5 gallon spent target pail, spent target lifting long pole and hook assembly load test 5 gallon spent target pail, lifting
long pole and hook assembly load test was
done by Rupan, Keyur ,and David.  Load
  
  2618   Tuesday, June 18, 2024, 15:16 Adam NewsomeCraneMaintenance  Pail Handling Tool - Annual InspectionThe pail handling tool which is used to
move 5 gallon pails around  the target hall
was inspected by A. Newsome.  The main tool
 PXL_20240618_213742257.jpgPXL_20240618_213455575.jpgPXL_20240618_213626154.jpg 
  2617   Tuesday, June 18, 2024, 15:04 Adam NewsomeSpent Target VaultMaintenance   Annual Inspection of Main and Mini Storage Vaults The annual inspection of the main storage
vault will be skipped this year since extensive
inspection and testing was performed during
 PXL_20240618_213819000.jpgPXL_20240618_213905146.jpg 
  2616   Tuesday, June 18, 2024, 11:59 David WangSouth Hot-CellStandard OperationTM3 Tm3 electrical check without target.Tm3 electrical check without target is
done. Everything is good including 2 x 5
pin connectors( all OL at 250 V to 60 KV
 TM3_without_target_2024_june_18.pdf 
  2615   Monday, June 17, 2024, 17:24 Carla BabcockITEDevelopmentTM3UCx#44Status of gas system prototype in ITEA new gas system for FEBIAD operation was
installed in ITE to enable us to use a calibrated
leak which is attached to the target heat
 schematic_pumpinggaslines_detailed.png 
  2614   Monday, June 17, 2024, 07:36 David WangITERepair  IG1S elbow oring seal and a blabk off cap oring seal beside the elbow were replaced on ITE entrance module top..IG1S elbow o ring seal and a blank off
cap o-ring seal beside the elbow were replaced
on ITE entrance module top last Friday. IG1s
  