  1868   Friday, February 15, 2019, 12:05 David WangITEMaintenanceTM4 ITE annual vacuum leak check. Helium pressure test on all water lines:
70psi , 3 minutes. HS has a quick response
to 9Xe-9atm.cc/sec for 20 seconds. No response
  
  1867   Thursday, February 14, 2019, 14:02 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move TM#2 has been moved from the conditioning
station to the south hot cell.
  
  1866   Thursday, February 14, 2019, 07:13 David WangConditioning StationStandard OperationTM2 TCS vacuum pumps have been stopped.Preparation on TM2 move from TCS to SHC.   
  1865   Monday, February 11, 2019, 10:26 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel moved to Target Hall  On February 8th the SMP shield
box (IRH1675) and the vacuum vessel (IRH1806)
were both raised from a horizontal to vertical
 6x 
  1864   Thursday, January 31, 2019, 14:16 Isaac EarleNorth Hot-CellDevelopment  NHC grounding approval Franco Mammarella was consulted regarding
electrical grounding of the NHC design (RS103
of Document-131915).  After discussing
 NHC_grounding.pdf 
  1863   Monday, January 28, 2019, 10:41 David WangConditioning StationRepairTM2 TM2 water lines helium pressure test at TCSleak detector base LR: 0.0Xe-9atm.cc/sec.
helium 70 psi. test time : 3 minutes for
each circuit.The results in atm.cc/sec are
  
  1862   Thursday, January 24, 2019, 10:34 David WangITWMaintenance  Changed 24VDC plugs of TP solenoid valves in ITW3 damaged 24VDC plugs of TP solenoid valves
are replaced. Inspected other plugs. All
of them are in good condition now. 
  
  1861   Tuesday, January 22, 2019, 09:56 David WangITWMaintenanceTM2 ITW water system maintenance.ITW water system maintenance is done. All
working paddle wheels and coils are replaced.
ITW water system polyurethane tubes are replaced
  
  1860   Monday, January 21, 2019, 16:27 Isaac EarleNorth Hot-CellDevelopment  NHC in-cell camera wired to right side monitor The NHC right side monitor has been
wired to display the signal from the in-cell
camera.  This was tested using a snake
 20190121_154407.jpg 
  1859   Friday, January 18, 2019, 10:26 Isaac EarleNorth Hot-CellDevelopment  NHC sealing improvements and repeat of RH test for LED lightsThe following NHC development work was
completed under WP I2019-01-09-4:

    Location of RH feature
  
  1858   Monday, January 14, 2019, 07:07 David WangConditioning StationMaintenanceTM2 Restarted TCS vacuum system .No issue.   
  1857   Friday, January 11, 2019, 13:59 Isaac EarleSafe Module ParkingDevelopment  SMP motor selection decisionSMP drivetrain design work is currently
underway.  Alejandro has selected a
suitable 1200:1 reducer which will give a
  
  1856   Friday, January 11, 2019, 13:17 David WangConditioning StationStandard OperationTM2 TCS and TM2 vacuum system are switched off for this Sunday power outage. I will restart all pumps Monday morning.  
  
  1855   Friday, January 11, 2019, 11:26 Travis CaveSpent Target VaultStandard Operation UC#25Spent Target Move The spent target in the south hot
cell has been moved to the spent target vault.
It was placed in pail 204 and placed in spot
 Target_Index_2019-01-11.pdf 
  1854   Thursday, January 10, 2019, 10:45 David WangConditioning StationStandard OperationTM2 TM2 is under vacum at TCS.TCS: TP1, TP2 and TP1S are started.    
  1853   Thursday, January 10, 2019, 09:26 Travis CaveConditioning StationStandard OperationTM2no targetModule move TM#2 has been moved from the south
hot cell to the conditioning station.
  
  1852   Wednesday, January 09, 2019, 13:29 David WangITWRepair  ITH:MP1ITH: MP1 has been replaced due to its poor
performance.  Its motor and power cable
are taken out and reused on new pump. Vacuum
  
  1851   Wednesday, January 09, 2019, 13:08 Travis CaveSouth Hot-CellStandard OperationTM2UC#25Electrical Check Electrical check of the target module
with the UC#25 attached after the beam run.
 Electrical_Chk_TM#2_UC#25_post_beam_Jan-09-2019.pdf 
  1850   Wednesday, January 09, 2019, 10:47 Travis CaveSouth Hot-CellStandard OperationTM2UC#25Module move TM#4 with UC#25 has been moved from
ITW to the south hot cell.
  
  1849   Wednesday, January 09, 2019, 06:26 David WangConditioning StationStandard Operation  TCS vacuum pumps have been stopped.The tCS will be vented soon for TM2 move
later this week.
  