1568
|
Tuesday, June 27, 2017, 10:26 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#52 | Leak check on TM4 HS line at SHC | LD base LR:0.0Xe-9 atm.cc/sec. No leak
has been found during the check. The
HS line will be helium pressurized at TCS |
|
1567
|
Tuesday, June 27, 2017, 09:14 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | Ta#52 | Module move | TM#4 with Ta#52 has been moved from
south hot cell to the conditioning station. |
|
1566
|
Monday, June 26, 2017, 11:47 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | Ta#52 | UC#20 Removed Ta#52 installed | UC#20 has been removed from TM4 and put
in a bucket back-filled with argon. Ta#52
has been installed onto TM4 with new fasteners. |
|
1565
|
Monday, June 26, 2017, 11:42 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#20 | Module move | TM#4 with UC#20 has been moved from
the east target station to the south hot
cell. Also the shield plug was remotely installed |
|
1564
|
Friday, June 23, 2017, 17:28 |
Isaac Earle | North Hot-Cell | Development | | | NHC module flange and cameras installed | The North Hot Cell module support
flange (IRH1152D) was installed on June 21,
2017 using 1/8" rubber sheet as a sealing |
|
1563
|
Friday, June 23, 2017, 12:08 |
David Wang | Crane | Repair | | | TH crane inspection and probem fixing by Gordon crane | Gordon crane technician Peter came in today
and checked TH crane. Maico and I were there
with him. What he found is that brake gap |
|
1562
|
Thursday, June 22, 2017, 11:10 |
chad fisher | South Hot-Cell | Maintenance | | | In cell airline | The in cell airline has preemptively been
replaced. The hose was, as far as I know
the original. |
|
1561
|
Monday, June 19, 2017, 07:29 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Update TH MS project schedule. | Update TH MS project schedule. See attachment
1,2. |
|
1560
|
Thursday, June 15, 2017, 11:29 |
Isaac Earle | North Hot-Cell | Development | | | NHC inlet ducting installed | The North Hot Cell inlet ducting assembly
was installed today in the target hall at
the north end of the NHC roof block. A |
|
1559
|
Tuesday, June 13, 2017, 13:41 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been connected in ITW. | Yasmine and I connected TM2 in ITW today.
the control page is set to febiad mode. Both
gas line in ITW are opened for febiad run. |
|
1558
|
Tuesday, June 13, 2017, 11:10 |
Grant Minor | Crane | Maintenance | | | ISAC THall Crane 100% / 125% Load Test Documentation - 2011 | The ISAC Target Hall Crane was load tested
and re-certified in January 2011 prior to
doing a near-capacity lift for the North |
|
1557
|
Tuesday, June 13, 2017, 09:57 |
Travis Cave | ITW | Standard Operation | TM2 | SiC#36 | module moved | TM#2 with SiC#36 has been moved from the
conditioning station to the west target station. |
|
1556
|
Monday, June 12, 2017, 13:51 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent Target move | The spent Ta#51 target has been moved from
the south hot cell to the spent target vault.
It was placed in pail#149 and put in spot |
|
1555
|
Friday, June 09, 2017, 11:21 |
chad fisher | North Hot-Cell | Maintenance | | | Model 'N' Slave Removal Through Roof | Isaac and Chad disengaged the slave end
of the manipulator and performed a slave
removal through the slave removal roof hatch. |
|
1554
|
Thursday, June 08, 2017, 08:35 |
David Wang | Conditioning Station | Development | TM2 | | TM2 gas line reconfiguration on the module top. | Reconfigured TM2 gas line on the module
top. It matches with the febiad gas line
we are using on service tray now. Facing |
|
1553
|
Thursday, June 08, 2017, 07:37 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 water llines at TCS. |
The helium pressure test on HS line is done |
|
1552
|
Wednesday, June 07, 2017, 13:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | I started all turbo pumps. |
|
1551
|
Wednesday, June 07, 2017, 13:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 SiC#36 leakc check and electrical check. | The results are good. See attachment. |
|
1550
|
Tuesday, June 06, 2017, 13:42 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | SiC#36 | Ta#51 removed SiC#36 installed | This afternoon Ta#51 was removed from TM2
and SiC#36 installed.
All new fasteners used. High current |
|
1549
|
Wednesday, May 24, 2017, 08:11 |
David Wang | ITW | Standard Operation | TM2 | | TH schedule 132 update weekly | See attachments. |
|