  1028   Friday, July 31, 2015, 09:47 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015Weekly update of Target Hall schedule after
so many jobs have been finished in this week. 
See attachment 1, 2
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp 
  1027   Thursday, July 30, 2015, 14:05 Travis CaveSpent Target VaultStandard Operation SiC#31Spent target movedSiC#31 has been moved to the spent target
vault. It is in pail #127 and placed in spot
3C of the vault is was 489mSv/hr when removed
 Vault_Storage_July_30_2015.pdf 
  1026   Wednesday, July 29, 2015, 10:14 David WangITEStandard OperationTM4 TM4 has been connected in ITEDan and I connected TM4 in ITE. We checked
all water signals on ITE cooling circuits.
Everything is good.
  
  1025   Wednesday, July 29, 2015, 08:59 Travis CaveITEStandard OperationTM4UC#13Module movedTM#4 with UC#13 has been moved from the
conditioning station to the east target station.
  
  1024   Wednesday, July 29, 2015, 06:24 David WangConditioning StationStandard OperationTM4UCx 13Stopped the CS and TM4 pumps and vent with argon.Dan and I stopped the CS and TM4 pumps.
We are venting the CS with argon for UCX13
target.
  
  1023   Tuesday, July 28, 2015, 14:40 chad fisherSouth Hot-CellStandard OperationTM4SiC#31 UCx#13SiC#31 removed UCx#13 installedSiC#31 has been removed from TM4 and UCx#13
installed. UCx#13 connection to the 9 pin
connector was VERY VERY tight to the tube
 20150727_115314.jpg 
  1022   Tuesday, July 28, 2015, 14:36 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 AutopsyExtraction electrode was removed from SiC#31
and target inspected.
Pictures of findings can be found
  
  1021   Tuesday, July 28, 2015, 14:31 Travis CaveConditioning StationStandard OperationTM4UC#13Electrical CheckTM#4 with UC#13 electrical check at the
conditioning station under vacuum. See attached
PDF.
 TM4UC13IGLISelecchkCS.PDF 
  1020   Tuesday, July 28, 2015, 10:17 David WangITERepair  ITE TP4 has been replacedTony and I replaced the ITE TP4 turbo pump
today. The pumping time on controller has
been reset to 0. The replaced broken 
  
  1019   Tuesday, July 28, 2015, 10:12 David WangConditioning StationStandard OperationTM4UCx 13Helium pressure test on TM4 HS line at CSI did the helium pressure test on TM4 HS
line at CS. Applied 70 psi helium  2
minutes. base leak rate0.0x E-9 atm.cc/sec. 
  
  1018   Monday, July 27, 2015, 17:03 David WangConditioning StationStandard OperationTM4UCx 13UCx13 and TM4 under vacuum at CS.I connected the CS  vacuum system 
to TM4. The CS and TM4 turbo pumps are started.
Everything is good so far. The HS line will
  
  1017   Monday, July 27, 2015, 15:46 David WangSouth Hot-CellStandard Operation  The yellow steel plug is put on SHC in THThe yellow steel plug is put on SHC in
TH. The spent target is inside the SHC.The
field around the SHC area in TH is so high
  
  1016   Monday, July 27, 2015, 15:34 David WangITEStandard OperationTM4 Leak check on TM4 HS water line with new UCX target. at SHCChad and I leak checked the HS line at
SHC after UCX target installation. On first
round helium spray, one of VCR fitting has
  
  1015   Monday, July 27, 2015, 14:37 Travis CaveSouth Hot-CellStandard OperationTM4UC#13Module movedTM#4 has been moved from the east target
station (morning with SiC#31), and moved
to the conditioning station from the south
  
  1014   Monday, July 27, 2015, 13:38 Travis CaveSouth Hot-CellStandard OperationTM4UC#13Electrical CheckElectrical check of TM#4 with UC#13 at
the south hot cell. See PDF for details.
 TM4UC13IGLISelecchkSHC.PDF 
  1013   Monday, July 27, 2015, 12:12 Travis CaveSouth Hot-CellStandard OperationTM4SiC#31Electrical CheckElectrical check of TM#4 post beam with
target (SiC#31) on and module without target
on. There is a short between the target and
 TM4_elecchk_notgt.PDFTM4SiC31postbeamelecchk_.PDF 
  1012   Friday, July 24, 2015, 14:41 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule movedTM#2 has been moved from the south hot
cell to north east silo.
  
  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.Dan and I moved 5 shielding blocks from
ITE to block storage area. The move is smooth.
  
  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015Update Target Hall schedule after the changing
on TM2 process. See attachment 1,2
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp 
  1009   Wednesday, July 22, 2015, 12:13 chad fisherSouth Hot-CellRepairTM2 TM2 Short FindingsPin X was unplugged, short remained, however
any slight pressure on the block towards
the source tray makes the short go away.
 TM2_Short_July_22.jpg 