ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
2761
|
Thursday, January 30, 2025, 07:17 |
David Wang | Crane | Standard Operation | | | inspection of target hall crane below hook attachment pins and plates ITA6550-01. |
Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01 yesterday. He certified the use of these pins and plates for year 2025. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08. After inspection, The inspection tag was issued. Tom has an inspection record on this job. |
2760
|
Thursday, January 30, 2025, 07:13 |
David Wang | Crane | Standard Operation | | | inspection of target module lifting frames ITA0494-1997-01 and ITA1994-1997-02 |
Tom Gauss inspected two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 yesterday. He certified the use of these two frames for 2025. Inspection tags have been issued and attached to frames. He has inspection record on them.
|
2759
|
Thursday, January 30, 2025, 07:07 |
David Wang | Crane | Standard Operation | | | target hall crane annual inspection. |
Tom Kauss finished TH crane annual inspection yesterday. The crane woks fine. Tom has this inspection record in his file. The crane inspection tag has been issued for 2025. |
2758
|
Wednesday, January 29, 2025, 11:39 |
chad fisher | North Hot-Cell | Repair | | | Model N Remote Arm #9342 Tong Cable |
Model N remote arm serial #9342 tong cable has been un-jammed from between pulley 3D (see picture) and casting (this is an ongoing issue with #9342 and 9352) and cable restrung and exercised to check motion. Tong system is now functional but exhibits excessive slack. Next step will be to check tension of the elevation/twist cables and adjust the pulley block if required (this pulley block houses both the elevation twist cable pulleys and the tong cable pulley 3D which is the site of the persistent cable hop)...I suspect adjusting the tension here will at least slightly improve the slack. In addition I will also investigate repositioning the tong drum screws (the procedure used to adjust the tong opening). |
Attachment 1: Model_N_Pulley_3D.JPG
|
|
2757
|
Wednesday, January 29, 2025, 11:10 |
chad fisher | South Hot-Cell | Standard Operation | | | Pre-entry field Check |
Fields in the hot cell were checked using a pole monitor. Field approximately in the area someone would stand to repair manip. is 3.8 mSv/h
Hot item found! Bag with extraction electrode and high current fasteners from an online target. |
Attachment 1: Image_(1).jpg
|
|
2756
|
Wednesday, January 29, 2025, 09:06 |
David Wang | ITE/ITW | Standard Operation | | | ITE and ITW water system paddle wheels and coils on flow sensors have been replaced |
ITE and ITW water system paddle wheels and coils on all flow sensors in pits have been replaced. It's a SAS job. |
2755
|
Tuesday, January 28, 2025, 11:47 |
David Wang | Conditioning Station | Standard Operation | TM3 | No target | Tm3 has been moved from TCS to silo. |
Tm3 has been moved from TCS to silo. The move is successful. |
2754
|
Monday, January 27, 2025, 08:27 |
om David Wang | South Hot-Cell | Maintenance | | parasite target | Transfer parasite target from SHC to NHC. |
A parasite target has been transferred from SHC to NHC. It is a job to reduce SHC field for coming SHC entry job. The transfer is successful. |
2753
|
Wednesday, January 22, 2025, 10:29 |
Frank Song | Faraday Cage | Maintenance | | | Annual clean up for ITE/ITW Faraday cages |
David and I cleaned both cages in ISAC1 electric room, all done. |
2752
|
Tuesday, January 21, 2025, 10:46 |
David Wang | ITE/ITW | Standard Operation | | | ITW/ITE pit general annual cleaning up. |
ITW/ITE pit general annual cleaning up were done. all concrete floor and TM equipment surface are vacuum cleaned. HV cage inside and blue nylon insulators were wiped by paper. |
2751
|
Monday, January 20, 2025, 11:33 |
Adam Newsome | Waste Package/Ship | Standard Operation | | | F-308 flask loading - six flasks loaded |
Today (2025-01-20), six flasks were loaded in preparation for shipment with the following targets: C#4, TiC#5, Ta#64,Ta#62, Nb#10, SiC#44
Some of the pails (256, 273, 279, 277) required replacement of the wire rope cable with new style, 30 ft length, as requested by CNL. A lifting label was also applied to these pails. Some of the pails (295, 298) already had the appropriate cable and lifter label.
At the time of writing this log:
- The second crimped lifting loop has not yet been applied to each pail.
- The locks have not yet been applied to the flasks.
The mini-storage vault is now EMPTY. The mini-storage vault has been swiped and checked for contamination.
The target index spreadsheet has been updated (attached). |
Attachment 1: Target_Index_2025-01-20.xlsm
|
2750
|
Thursday, January 16, 2025, 14:21 |
David Wang | Conditioning Station | Standard Operation | TM3 | No target | TM3 electrical check at TCS under good vacuum |
A complete TM3 electrical check at TCS under good vacuum has been done. Pin 14 to 60KV only has 8K ohm on ohmmeter check , and it's about 2Kohm @250V Megga. It's low in resistivity. The pin 14 is for thermocouples only so no big concern. The rest things are good. See attachments. |
Attachment 1: TM3_electrical_check_@TCS_page_1.pdf
|
|
Attachment 2: TM3_electrical_check_@TCS_page_2.pdf
|
|
2749
|
Thursday, January 16, 2025, 10:03 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#47 | Spent Target Move |
The spent UC#47 was moved from the south hot cell to the spent target vault placed in pail #302 in spot 1C of the vault, it was 24.5mSv/hr when removed from the south hot cell. See attached for vault details. |
Attachment 1: Target_Index_2025-01-16.pdf
|
|
2748
|
Tuesday, January 14, 2025, 10:00 |
David Wang | South Hot-Cell | Standard Operation | TM3 | UCx#47 | after operation electrical check, Tm3 UCx 47 |
TM3 UCx#47 after operation electrical check is done at SHC. The result is normal. See attachment. |
Attachment 1: TM3_UCX_47_after_operation_electrical_check.pdf
|
|
2747
|
Monday, January 13, 2025, 10:36 |
Frank Song | ITE | Standard Operation | TM3 | UCx#47 | module disconnection |
TM3 with spent target UCx#47 was disconnected in ITE and will be moved to SHC. |
Attachment 1: TM3_with_spent_target_UCx#47_disconnection_in_ITE_2025-01-13.pdf
|
|
2746
|
Monday, January 13, 2025, 10:02 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#46 | Spent Target Move |
UC#46 was placed in pail# 301 in spot 1B and was 26.3mSv/hr when removed from the SHC. See attached PDF for vault
details. |
Attachment 1: Target_Index_2025-01-13.pdf
|
|
2745
|
Thursday, January 09, 2025, 11:46 |
David Wang | Safe Module Parking | Standard Operation | TM4 | No target | SMP is under vacuum for TM4 storage during shut down. |
SMP:MP1 is started with SMP BV1 is opened. SMP is under vacuum for TM4 storage during shut down. |
2744
|
Thursday, January 09, 2025, 11:08 |
David Wang | Facilities | Maintenance | | | ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings |
ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings and investigation in pit. A fault 17644 has been issued. this pump will be replaced in March when general fielding in vacuum pit is reasonable for the job. |
2743
|
Wednesday, January 08, 2025, 07:37 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UCx#46 | UCx#46 removal |
UCx#46 removed from TM4 and placed into a pail back-filled with argon. Nothing visually unusual; no issues. |
Attachment 1: TM4_UCx46_07012024.jpeg
|
|
Attachment 2: TM4_UCx46_2_07012024.jpeg
|
|
2742
|
Tuesday, January 07, 2025, 12:05 |
David Wang | ITE | Standard Operation | TM3 | UCx #47 | ITE primary and secondary vacuum vessel leak check for 2025 shut down |
ITE primary and secondary vacuum vessel leak check for 2025 shut down have been done. No leak. The TM3 waterlines helium pressure test will be done at TCS when module is there.
TM3 water lines helium pressure test are done. 70 psi helium 3 minutes to each line( except HS which has no target on it ) . leak detector base leak rate :0.0Xe-9 atm.cc/sec. No leak on all tested water lines.Helium were purged out after test. and 60 psi nitrogen were filled in lines for storage. |