ID Date Author Category Type Module Target/Number Subject
  2761   Thursday, January 30, 2025, 07:17 David WangCraneStandard Operation  inspection of target hall crane below hook attachment pins and plates ITA6550-01.

Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01 yesterday. He certified the use of these pins and plates for year 2025. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08.  After inspection, The inspection tag  was issued. Tom has an inspection record on this job.

  2760   Thursday, January 30, 2025, 07:13 David WangCraneStandard Operation  inspection of target module lifting frames ITA0494-1997-01 and ITA1994-1997-02

Tom Gauss inspected  two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 yesterday. He certified the use of these two frames for 2025. Inspection tags have been issued and attached to frames. He has inspection record on them. 

 
  2759   Thursday, January 30, 2025, 07:07 David WangCraneStandard Operation  target hall crane annual inspection.

Tom Kauss finished TH crane annual inspection yesterday. The crane woks fine. Tom has this inspection record in his file. The crane inspection tag has been issued for 2025.

  2758   Wednesday, January 29, 2025, 11:39 chad fisherNorth Hot-CellRepair  Model N Remote Arm #9342 Tong Cable

Model N remote arm serial #9342 tong cable has been un-jammed from between pulley 3D (see picture) and casting (this is an ongoing issue with #9342 and 9352) and cable restrung and exercised to check motion. Tong system is now functional but exhibits excessive slack. Next step will be to check tension of the elevation/twist cables and adjust the pulley block if required (this pulley block houses both the elevation twist cable pulleys and the tong cable pulley 3D which is the site of the persistent cable hop)...I suspect adjusting the tension here will at least slightly improve the slack. In addition I will also investigate repositioning the tong drum screws (the procedure used to adjust the tong opening).

Attachment 1: Model_N_Pulley_3D.JPG
Model_N_Pulley_3D.JPG
  2757   Wednesday, January 29, 2025, 11:10 chad fisherSouth Hot-CellStandard Operation  Pre-entry field Check

Fields in the hot cell were checked using a pole monitor. Field approximately in the area someone would stand to repair manip. is 3.8 mSv/h

Hot item found! Bag with extraction electrode and high current fasteners from an online target.

Attachment 1: Image_(1).jpg
Image_(1).jpg
  2756   Wednesday, January 29, 2025, 09:06 David WangITE/ITWStandard Operation  ITE and ITW water system paddle wheels and coils on flow sensors have been replaced

ITE and ITW water system paddle wheels and coils on all flow sensors in pits have been replaced. It's a SAS job.

  2755   Tuesday, January 28, 2025, 11:47 David WangConditioning StationStandard OperationTM3No targetTm3 has been moved from TCS to silo.

Tm3 has been moved  from TCS to silo. The move is successful.

  2754   Monday, January 27, 2025, 08:27 om David WangSouth Hot-CellMaintenance parasite targetTransfer parasite target from SHC to NHC.

A parasite target has been transferred from SHC to NHC. It is a job to reduce SHC field for coming SHC entry job. The transfer is successful.

  2753   Wednesday, January 22, 2025, 10:29 Frank SongFaraday CageMaintenance  Annual clean up for ITE/ITW Faraday cages

 David and I cleaned both cages in ISAC1 electric room, all done.

  2752   Tuesday, January 21, 2025, 10:46 David WangITE/ITWStandard Operation  ITW/ITE pit general annual cleaning up.

ITW/ITE pit general annual cleaning up were done. all concrete floor and TM equipment surface are vacuum  cleaned. HV cage inside and blue nylon insulators were wiped by paper.

  2751   Monday, January 20, 2025, 11:33 Adam NewsomeWaste Package/ShipStandard Operation   F-308 flask loading - six flasks loaded

Today (2025-01-20), six flasks were loaded in preparation for shipment with the following targets: C#4, TiC#5, Ta#64,Ta#62, Nb#10, SiC#44

Some of the pails (256, 273, 279, 277) required replacement of the wire rope cable with new style, 30 ft length, as requested by CNL. A lifting label was also applied to these pails. Some of the pails (295, 298) already had the appropriate cable and lifter label.

 

At the time of writing this log:

  • The second crimped lifting loop has not yet been applied to each pail.
  • The locks have not yet been applied to the flasks.

 

The mini-storage vault is now EMPTY. The mini-storage vault has been swiped and checked for contamination.

The target index spreadsheet has been updated (attached).

Attachment 1: Target_Index_2025-01-20.xlsm
  2750   Thursday, January 16, 2025, 14:21 David WangConditioning StationStandard OperationTM3No targetTM3 electrical check at TCS under good vacuum

A complete TM3 electrical check at TCS under good vacuum has been done. Pin 14 to 60KV only has 8K ohm on ohmmeter check , and it's about 2Kohm @250V Megga. It's low in resistivity. The pin 14 is for thermocouples only so no big concern.  The rest things are good. See attachments.

Attachment 1: TM3_electrical_check_@TCS_page_1.pdf
TM3_electrical_check_@TCS_page_1.pdf
Attachment 2: TM3_electrical_check_@TCS_page_2.pdf
TM3_electrical_check_@TCS_page_2.pdf
  2749   Thursday, January 16, 2025, 10:03 Travis CaveSpent Target VaultStandard Operation UC#47Spent Target Move

 The spent UC#47 was moved from the south hot cell to the spent target vault placed in pail #302 in spot 1C of the vault, it was 24.5mSv/hr when removed from the south hot cell. See attached for vault details.

Attachment 1: Target_Index_2025-01-16.pdf
Target_Index_2025-01-16.pdf
  2748   Tuesday, January 14, 2025, 10:00 David WangSouth Hot-CellStandard OperationTM3UCx#47after operation electrical check, Tm3 UCx 47

TM3 UCx#47 after operation electrical check  is done at SHC. The result is normal. See attachment.

Attachment 1: TM3_UCX_47_after_operation_electrical_check.pdf
TM3_UCX_47_after_operation_electrical_check.pdf
  2747   Monday, January 13, 2025, 10:36 Frank SongITEStandard OperationTM3UCx#47module disconnection

 TM3 with spent target UCx#47 was disconnected in ITE and will be moved to SHC.

Attachment 1: TM3_with_spent_target_UCx#47_disconnection_in_ITE_2025-01-13.pdf
TM3_with_spent_target_UCx#47_disconnection_in_ITE_2025-01-13.pdf TM3_with_spent_target_UCx#47_disconnection_in_ITE_2025-01-13.pdf TM3_with_spent_target_UCx#47_disconnection_in_ITE_2025-01-13.pdf
  2746   Monday, January 13, 2025, 10:02 Travis CaveSpent Target VaultStandard Operation UC#46Spent Target Move
UC#46 was placed in pail# 301 in spot 1B and was 26.3mSv/hr when removed from the SHC. See attached PDF for vault 
details.
Attachment 1: Target_Index_2025-01-13.pdf
Target_Index_2025-01-13.pdf
  2745   Thursday, January 09, 2025, 11:46 David WangSafe Module ParkingStandard OperationTM4No targetSMP is under vacuum for TM4 storage during shut down.

 SMP:MP1 is started with SMP BV1 is opened. SMP is under vacuum for TM4 storage during shut down.

  2744   Thursday, January 09, 2025, 11:08 David WangFacilitiesMaintenance  ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings

ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readings and investigation in pit. A fault 17644 has been issued. this pump will be replaced in March when general fielding in vacuum pit is reasonable for the job.

  2743   Wednesday, January 08, 2025, 07:37 chad fisherSouth Hot-CellStandard OperationTM4UCx#46UCx#46 removal

UCx#46 removed from TM4 and placed into a pail back-filled with argon. Nothing visually unusual; no issues.

Attachment 1: TM4_UCx46_07012024.jpeg
TM4_UCx46_07012024.jpeg
Attachment 2: TM4_UCx46_2_07012024.jpeg
TM4_UCx46_2_07012024.jpeg
  2742   Tuesday, January 07, 2025, 12:05 David WangITEStandard OperationTM3UCx #47ITE primary and secondary vacuum vessel leak check for 2025 shut down

ITE primary and secondary vacuum vessel leak check for 2025 shut down have been done. No leak.  The TM3 waterlines helium pressure test will be done at TCS when module is there.

TM3 water lines helium pressure test  are done. 70 psi helium 3 minutes to each line( except HS which has no target on it ) . leak detector base leak rate :0.0Xe-9 atm.cc/sec. No leak on all tested water lines.Helium were purged out after test. and 60 psi nitrogen were filled in lines for storage. 