ID Date Author Category Typedown Subject Text Attachments
  3   Tuesday, February 14, 2012, 15:40 Grant MinorTrolleyStandard Operation2C Removal - all 4 QDLs were actuated remotely this year!Today Remote Handling staff (Maico Dalla
Valle, Travis Cave) used the Remote Handling
2C probe removal trolley to remove the probe
 2C_probe_Feb_14_2012_labelled.JPG2C_probe_solenoid_5_Feb_14_2012_labelled.JPG 
  7   Tuesday, January 29, 2013, 18:49 Grant MinorElevation JackStandard OperationLid-up complete - summary notesLid-up was first attempted yesterday (Jan
28th) by Dan Louie, Arthur Leung, and Maico
Dalla Valle.  They experienced problems
 Jacks_Station_6_and_4_Procedure_Jan_12_2012_122.jpg 
  8   Wednesday, January 30, 2013, 14:44 Grant MinorElevation JackStandard OperationFurther lid-up notes from Dan LouieDan Louie's e-mail comments from 30 Jan
2013 are attached.
- Grant
 Dan_Louie_Lid-Up_e-mail_30Jan2013.pdf 
  14   Wednesday, February 27, 2013, 12:08 Travis CaveCyclotronStandard OperationInstallation of 2C2C has been installed located on all QDLs
and all the numbers, continuity check done
and passed. Bridge has been removed from
  
  15   Tuesday, March 05, 2013, 14:11 Travis CaveCyclotronStandard OperationSetup and the Installation of the HE 1 probe.Setup of the HE 1 probe is difficult has
we have no mockup of it to properly setup
cameras and equipment for it. This is problem
  
  19   Friday, March 15, 2013, 08:39 Don JacksonCyclotronStandard OperationPre Lid Down In Tank Video SurveyIn tank survey completed.  A few items
of interest were found.  Ladders need
to moved manually outboard to #5 resonators
 Pre_Lid_Down_Survey_2013.pdf 
  20   Friday, March 15, 2013, 15:18 Grant MinorCyclotronStandard OperationLid Down Successful - Mechanical Counter ReadingsPrior to the lid-down operation today,
the Cyclotron was lowered by 0.75" and
then raised again to confirm that the upper
  
  22   Tuesday, March 19, 2013, 19:17 Grant MinorElevation JackStandard OperationRe-indexing of all jack station "zero" yoke elevationsThe dimension between the yokes and the
Cyclotron upper structure primary beams was
set to .25" nominal at all jack stations
 Jacks_Station_6_and_4_Procedure_Jan_12_2012_122.jpg 
  26   Friday, January 17, 2014, 07:53 Travis CaveTrolleys servicedStandard OperationTrolley checksAll trolleys work electrically and control
wise. One encoder was found non functioning
on the upper resonator trolley for the vertical
  
  27   Monday, January 20, 2014, 12:00 Grant MinorElevation JackStandard OperationIndexing Check of Cyclotron Jack StationsMaico Dalla Valle and Grant Minor, supported
by Dan Louie and Arthur Leung, entered the
Cyclotron Vault on January 15th, 2014 to
  
  28   Thursday, January 23, 2014, 18:47 Grant MinorElevation JackStandard OperationCyclotron Lid-Up Report - 22 Jan 2014Yesterday Grant Minor (me), Maico Dalla
Valle, Dan Louie, and Arthur Leung worked
with Operations to perform the Cyclotron
 6x 
  29   Friday, January 24, 2014, 14:10 Travis CaveCyclotronStandard OperationCopper blockersThe copper blockers have been removed from
the cyclotron and placed into the coffins.
  
  30   Monday, January 27, 2014, 14:42 Travis CaveShieldingStandard Operationshields and radiation survey The cyclotron radiation survey was aborted
due to the orbit not working recording the
numbers correctly. One shield has been in
 Meeting_Orbital_Counter_Problem_Jan_2014.pdf 
  31   Tuesday, January 28, 2014, 14:59 Travis CaveShieldingStandard Operationshields 200's, 400's, 500's, 600's, and a pallet
of 700's have been installed
  
  32   Wednesday, January 29, 2014, 15:08 Bevan MossCyclotronStandard OperationShielding and Port Hole Covers The Shielding and the Port Hole Covers
have all been installed. No issues with the
installation have caused any problems. This
  
  33   Thursday, January 30, 2014, 13:47 Travis CaveCyclotronStandard OperationshieldsAll shields, pothole covers, and ladders
have been installed into the cyclotron.
  
  34   Friday, January 31, 2014, 10:07 Travis CaveCyclotronStandard Operation2C removal2C has been successfully removed from the
cyclotron and is now currently sitting in
the B2 level of the RH building. A tank access
  
  35   Friday, February 07, 2014, 10:50 Travis CaveCyclotronStandard Operation2C install2C has been installed into the cyclotron.   
  36   Friday, February 21, 2014, 11:05 Bevan MossCyclotronStandard OperationOld Monitor Box Removed, New installed One of the beam spill monitor boxes
was removed and placed into a lead coffin.
The fields around the coffin prior to the
 7x 
  37   Friday, February 21, 2014, 15:58 Bevan MossCyclotronStandard OperationOld Monitor Box Removed, New installedDuring the electrical test the was no contact.
 To help investigate further the Montitor
box was removed from the Cyclotron. It was
  