ID Date Author Categorydown Type Subject Text Attachments
  25   Thursday, January 16, 2014, 08:46 maicodallavalleTrolleys servicedMaintenancePre Cyclotron work servicing and checkingThis is a list of all the trolleys and
other equipment witch were checked and serviced
prior to work in the Cyclotron.
  
  26   Friday, January 17, 2014, 07:53 Travis CaveTrolleys servicedStandard OperationTrolley checksAll trolleys work electrically and control
wise. One encoder was found non functioning
on the upper resonator trolley for the vertical
  
  56   Tuesday, February 17, 2015, 07:10 Dan McDonaldTrolleys servicedMaintenancePre shut down trolley serviceRoutine maintenance as per Mike Gallop's
written procedure took place in December
with the only non routine service being the
  
  129   Friday, February 26, 2021, 08:29 Adam NewsomeTrolleys servicedMaintenanceFirst Turn Radial Flag (FTRF) Jig - Pneumatic UpgradeOld fittings and broken pneumatic tubing
on the FTRF jig have been replaced with new
push-connect fittings and polyurethane tubing.
 PXL_20210216_202019350.jpg 
  130   Friday, February 26, 2021, 13:00 Adam NewsomeTrolleys servicedMaintenanceLower Resonator Trolley - Radial Drive Failure IssueOn Feb. 24 while practising a training
exercise, the lower resonator trolley unexpectedly
experienced a radial drive failure. The trolley
  
  135   Tuesday, August 31, 2021, 14:28 Adam NewsomeTrolleys servicedDevelopmentUpper Resonator Trolley - Finger Cylinders ReplacedThe two support fingers on the upper resonator
trolley were bent due to excessive loading
during cylinder toggling.
 new_fingers.PNG 
  3   Tuesday, February 14, 2012, 15:40 Grant MinorTrolleyStandard Operation2C Removal - all 4 QDLs were actuated remotely this year!Today Remote Handling staff (Maico Dalla
Valle, Travis Cave) used the Remote Handling
2C probe removal trolley to remove the probe
 2C_probe_Feb_14_2012_labelled.JPG2C_probe_solenoid_5_Feb_14_2012_labelled.JPG 
  4   Friday, February 17, 2012, 15:07 Don JacksonTrolleyRepairVideo Trolley Failed in Cyclotron TankAll control to the video trolley was lost
during remote photographing of components
in the cyclotron. The control system and
 Stuck_Video_Trolley_Feb_17_2012_005.jpgStuck_Video_Trolley_Feb_17_2012_001.jpg 
  69   Tuesday, July 28, 2015, 11:47 Dan McDonaldTrolleyMaintenanceCamera trolley serviceServiced the Camera trolley this morning
as per Mike Gallops service outline.
  
  89   Thursday, June 30, 2016, 13:47 Dan McDonaldTrolleyMaintenanceLift trolleyMaintenance has been performed on the lift
trolley, re sealed the main drive gear box
it was quite dry inside and in need of new
  
  108   Friday, February 02, 2018, 14:14 Don JacksonTrolleyRepairOvercurrent on radial drive motor 
 
  
  109   Monday, February 19, 2018, 12:58 maicodallavalleTrolleyRepairLift Trolley RepairWe had just finished pulling out the ladders
from the cyclotron with the lift trolley.
We started to run the lift trolley into the
  
  113   Wednesday, September 04, 2019, 15:29 Adam NewsomeTrolleyMaintenanceConnector faceplate and tubing upgradeTool Trolley: 
The connector faceplate was replaced
with a new version to allow for more space
  
  119   Wednesday, February 05, 2020, 15:04 Adam NewsomeTrolleyRepairUpper resonator trolley: cylinders for Ex 2C tasks[B]Cylinder 4[/B] on the upper resonator trolley
was not fully functional when removing Ex
2C during 2020 shutdown. It worked occasionally.
  
  121   Saturday, April 04, 2020, 10:03 Dan McDonaldTrolleyDevelopmentAddition of DC motor controller mountsUpper and lower resonator trolleys received
mounting plates and brackets to accommodate
DC motor controls for updated drive motors.
  
  139   Monday, March 21, 2022, 13:14 Adam NewsomeTrolleyRepairVideo Trolley Mk 1 - Radial Limit Switch ReplacementAn issue was observed in which radial motion
on the Video Trolley Mk 1 did not respond
to commands. After troubleshooting, it was
  
  141   Wednesday, May 04, 2022, 12:07 Adam NewsomeTrolleyDevelopmentTool Trolley: Brass air fittings replacement completeAll of the old brass air fittings on the
Tool Trolley have now been swapped over to
push-connect style fittings. As these are
  
  155   Thursday, August 03, 2023, 10:43 Adam NewsomeTrolleyDevelopmentPrevious generation video trolley decommissionedThe "old" video trolley featuring
scissor mechanism and DSLR camera has officially
been decommissioned. Going forward, Video
  
  157   Thursday, September 14, 2023, 13:51 Adam NewsomeTrolleyMaintenanceLift Trolley: upgrades to camera tilt mechanismThe two camera tilt mechanisms on the lift
trolley have been upgraded. Upgrades include:
For the individual camera:
 PXL_20230914_193143524.jpg 
  158   Friday, September 15, 2023, 10:15 Adam NewsomeTrolleyMaintenanceLift Trolley: mirror actuation mechanism repair/upgradeThe mirror actuation mechanism was observed
to be "sticky" during 2023 winter
shutdown - it occasionally did not function
 PXL_20230915_164811247.jpg 