  RH-Cyclotron, Page 3 of 10  Not logged in ELOG logo
Entry  Tuesday, February 09, 2016, 14:48, Travis Cave, Cyclotron, Standard Operation, shadow shields 

All shadow shields have been installed. Ladders, the pothole covers and the second rad survey will be done tomorrow.

Entry  Wednesday, February 10, 2016, 14:53, Travis Cave, Cyclotron, Standard Operation, shadow shields 

All cyclotron in tank work is completed.

Entry  Thursday, February 25, 2016, 11:41, Travis Cave, Cyclotron, Standard Operation, Ex 2C removal 

Ex 2C has been removed from the cyclotron. A trip into the tank was needed to free the probe, hung up on the usual spot.

Entry  Tuesday, March 01, 2016, 13:27, Travis Cave, Cyclotron, Standard Operation, Ex 2C install 

EX 2C has been installed back into the cyclotron.

Entry  Thursday, April 07, 2016, 11:04, Travis Cave, Cyclotron, Standard Operation, Closed the shield door 

The shield door on the B2 level of the RH building has been closed.

Entry  Tuesday, January 31, 2017, 14:41, Travis Cave, Cyclotron, Standard Operation, Shield installation 

200, 400, 500, 600, and a pallet of 700 series of shield have been installed in the cyclotron.

Entry  Tuesday, January 16, 2018, 13:43, Travis Cave, Cyclotron, Standard Operation, Cyclotron in tank work 

 All cyclotron in tank work has been completed.

Entry  Tuesday, April 03, 2018, 11:57, Travis Cave, Cyclotron, Standard Operation, Blue Shield Door Shut. 

 The Blue Shield Door on the B2 level of the RH building has been closed.

Entry  Wednesday, January 19, 2022, 09:50, Travis Cave, Shielding, Standard Operation, Shield door is now open 

 The shield door is now open on the RH B2 level.

Entry  Wednesday, March 09, 2016, 17:09, Ron Kuramoto, Cyclotron, Development, EX4N new housing installation dspage07994143927104268192.pdfExtr_4N_Final_instalation_-_gimbal-pipe-valve.docxIMG_1886.JPG

The new EX4N housing assembly drawing TEC0071 (unfinished) was installed and connected to the EX4 tank side port flange over a 3 day period from Feb29 – Mar 2, 2016. This was a hands on installation spread amongst 5 people with the total accumulated dose was 2.97 mSv.  See W/P C2016-02-29-5
 

Attached are;

- Rad field survey map.
- Updated installation procedure (rev4) with additional notes/comments during the installation  Revisions in Red.  Competed steps in Green. 
- Photo of the EX4N housing assembly.

Recent photos, are on Dimo's S drive :S\dyosifov\Extraction 4\Photos 2016

Entry  Tuesday, May 14, 2024, 10:53, Riley Sykes, Carrier, Maintenance, Carrier underrail wheels maintenance 

 All 4 Under rail wheels serviced and cleaned. All Timken bearings repacked with grease. No defects in any bearing set. 4 spare Timken 02820 bearings in RH shop.

Entry  Thursday, May 16, 2024, 12:33, Riley Sykes, Service Bridge, Maintenance, Center Post Bearing 

 Center post bearing on service bridge inspected, turned freely by hand and regreased with Molub-Alloy 777-1 ES

Entry  Friday, May 31, 2024, 08:57, Riley Sykes, Carrier, Maintenance, Carrier Drive motor/gear reducer 

 Motor/Gearbox unit removed from carrier and fully inspected and serviced. Oil changed on May 29th using Mobil 600 W Super Cylinder Oil. No signs of wear in internal gears, recommend oil service roughly every 5 years after shutdown.

Entry  Friday, May 31, 2024, 11:28, Riley Sykes, Service Bridge, Maintenance, Outrigger mechanical inspection 

 Both outriggers were inspected and were found to be mechanically sound. No damage to components or hardware visible, will revisit with pre-inspection before shutdown period 2025.

Entry  Friday, May 31, 2024, 12:47, Riley Sykes, Trolleys serviced, Maintenance, Tool Trolley Scheduled Maintenance Tool_Trolley_Drive_Motor.jpg

 60 month service completed. Bearings for drive motor wheels regreased, Reducer repacked with Molub Alloy 777-1 ES, all mechanically sound. Recommended to swap out front right drive wheel in 5 years due to minimal deteoration.

Entry  Monday, June 03, 2024, 14:29, Riley Sykes, Trolleys serviced, Maintenance, Upper Resonator Trolley 

 24 Month, 60 month service completed. Bearings for drive motor wheels regreased and observed to move freely without load. Reducers repacked with Molub Alloy 777-1 ES. Vertical ball screw mechanism inspected and bearing change postponed due to lack of major usage, recommend change within next 5 years or service. All mechanically sound.

Entry  Tuesday, June 04, 2024, 14:29, Riley Sykes, Trolleys serviced, Maintenance, Lower Resonator Trolley 

  12, 24 and 60 month service completed. Bearings for drive motor wheels regreased and observed to move freely without load. Reducers repacked with Molub Alloy 777-1 ES. Vertical ball screw scissor mechanism inspected and all operations observed to be in sound mechanical condition.

Entry  Wednesday, June 12, 2024, 10:35, Riley Sykes, Trolleys serviced, Maintenance, Outriggers 1 and 2 Service 

 1,2 and 5 Year service completed. Vertical ball screws and chains inspected and regreased with Chemours Krytox EG 2000 suitable for vacuum and clean room situations. Mechanically sound, will do a once over before next shutdown period.

Entry  Friday, June 14, 2024, 10:04, Riley Sykes, Service Bridge, Maintenance, Service/ Bridge inspection 

 Yearly, 2 Year and 5 Year service completed. All bearings on support frames turn freely and were regreased with Molub Alloy 777-1 ES. Reducer repacked as well. Reinspect pre shutdown and lubricate orbital drive chain before wiping off excess.

Entry  Monday, June 24, 2024, 12:53, Riley Sykes, Elevation Jack, Maintenance, Highfield Service 

 Highfields 7A,7B post shutdown service complete. Oil change completed, new Mobil 600 W Super Cylinder oil added. Sample collected for RPG of used oil. Both found to be mechanically sound and stored in upper mezzanine. 