  RH-Cyclotron, Page 10 of 10  Not logged in ELOG logo
ID Date Author Category Type Subject Text Attachments
  13   Wednesday, February 13, 2013, 08:55 maicodallavalleService BridgeRepairService Bridge/Carrier Hydraulic JacksOn Monday February 4TH  the Service
Bridge was being lifted into  the Cyclotron
with the Carrier. It was noticed that one
 Hydraulic_Jack_RC-254.pdf 
  12   Wednesday, February 06, 2013, 18:07 Grant MinorElevation JackMaintenanceLid-down yoke gap measurements from 1994Attached is a scan of a handwritten record
from 1994 showing yoke-to-upper-structure
gap measurements from 1994, both L and R
 Elevation_Yoke_Measurements_1994.pdf 
  11   Wednesday, February 06, 2013, 17:50 Grant MinorElevation JackMaintenanceService records compiled by G. MinorAttached is a compiled record showing the
years of service of the jacks, upper bearing,
and gear reducers, prepared by Grant Minor
 Cyclotron_Elevation_Maintenance_Rotation_Record_17Dec2012.pdf 
  10   Wednesday, February 06, 2013, 17:42 Grant MinorElevation JackMaintenanceIn-situ jack power screw lubrication inspection - Stations 9, 10, 11, and 6Due to concerns raised regarding the state
of the lubrication of the power screws at
Station 9, the lubrication was visually inspected
 16x 
  9   Monday, February 04, 2013, 13:52 Grant MinorService BridgeRepairHydraulic cylinder failure on service bridgeThe hydraulic cylinder on the West side
of the service bridge (used to raise the
bridge for insertion into the Cyclotron)
 6x 
  8   Wednesday, January 30, 2013, 14:44 Grant MinorElevation JackStandard OperationFurther lid-up notes from Dan LouieDan Louie's e-mail comments from 30 Jan
2013 are attached.
- Grant
 Dan_Louie_Lid-Up_e-mail_30Jan2013.pdf 
  7   Tuesday, January 29, 2013, 18:49 Grant MinorElevation JackStandard OperationLid-up complete - summary notesLid-up was first attempted yesterday (Jan
28th) by Dan Louie, Arthur Leung, and Maico
Dalla Valle.  They experienced problems
 Jacks_Station_6_and_4_Procedure_Jan_12_2012_122.jpg 
  6   Thursday, October 25, 2012, 13:58 maicodallavalleService BridgeMaintenanceOrbit DriveIt was observed during the last time the
Cyclotron service bridge was used the orbit
drive chain had a lot of slack. The drive
  
  5   Tuesday, September 25, 2012, 08:57 maicodallavalleElevation JackMaintenance2012 Service Maintance of #4 Station Jacking System Shut down work for 2012.Replaced serviced
Jacking Station #6. Tapered alignment pins
were damaged. They were skimmed and checked
  
  4   Friday, February 17, 2012, 15:07 Don JacksonTrolleyRepairVideo Trolley Failed in Cyclotron TankAll control to the video trolley was lost
during remote photographing of components
in the cyclotron. The control system and
 Stuck_Video_Trolley_Feb_17_2012_005.jpgStuck_Video_Trolley_Feb_17_2012_001.jpg 
  3   Tuesday, February 14, 2012, 15:40 Grant MinorTrolleyStandard Operation2C Removal - all 4 QDLs were actuated remotely this year!Today Remote Handling staff (Maico Dalla
Valle, Travis Cave) used the Remote Handling
2C probe removal trolley to remove the probe
 2C_probe_Feb_14_2012_labelled.JPG2C_probe_solenoid_5_Feb_14_2012_labelled.JPG 
  2   Tuesday, February 07, 2012, 18:09 Grant MinorService BridgeRepairService Bridge Center Post Bearing Maintenance and Orbit Counter (2011/2012)Repair
of Orbit Limit Switch Plastic Belt
During
 Stripped_Orbit_Limit_Belt_Sept_23_2011.JPGBridge_Belt_Repair_Fall_2011.JPGOrbit_Counter_Wheel_Just_Before_Skip_Point.JPGD7900_detail_Feb_7_2012.JPGCyclotron_Orbit_Counter_Wheel_emails_Mar-Sep_2011.pdf 
  1   Monday, June 27, 2011, 10:38 John WongGeneralRoutineTesting RH elog    