ID Date Author Category Typedown Subject Text Attachments
  112   Tuesday, March 13, 2018, 15:36 Keith C NgM9Standard Operationm9 alignment workSet up shielding canyon for M9 laser tracker
job.
 dms.jpg 
  117   Tuesday, March 27, 2018, 15:08 Keith C NgM9Standard Operationt2 m9 port blank off1.
Blank off installed 11:40      with Dan McDonald,
east spring ear looks 'deeper" than
 20180327_t2m9_P1030978.JPG20180327_t2m9_P1030979.JPG 
  122   Tuesday, September 24, 2019, 14:37 Keith C NgPrimary BeamlinesStandard Operationlead pig radiation surveySurveyed contents of storage flask located
at TNF. The lid was lifted off roughly 12"
up and a pole monitor was swept over the
  
  130   Friday, May 06, 2022, 11:27 Keith C NgPrimary BeamlinesStandard Operation4V CM1 RH joint install 2022 Apr 28 to 29:
Installed a new remote handling 4"
indium joint for new beamline 4 north section.
 2022_4v_cm1_rh_joint_install.pdf 
  1   Thursday, June 30, 2011, 16:58 John WongPrimary BeamlinesRepairblah blah blahdfdfdfdfdf   
  2   Tuesday, February 14, 2012, 16:29 Keith C NgM20Repairm20 q1 q2 repairWarm cell reconfigured for water leak repair
at coil termination. Radiation surveys done.
M20 Q1 ready for  removal of insulators.
 P1010986.JPG 
  3   Thursday, February 16, 2012, 08:08 Keith C NgM20Repairm20 q1 q2 repairInsulators # 6,7,8 removed from Q1 headers
late afternoon by C Ballard. Ready for removal
and re-brazing of #7 joint some time today.
 P1020003.JPGP1020001.JPG 
  4   Thursday, February 16, 2012, 16:22 Keith C NgM20Repairm20 q1 q2 repairOld #7 coil fitting removed, replaced and
re-brazed today by M Good. Insulators ready
to go back on to magnet coils to be pressure
 IMG_2545.JPGP1020013.JPGP1020028.JPG 
  5   Friday, February 17, 2012, 15:35 Keith C NgM20Repairm20 q1 q2 repairReinstalled ceramic insulators #6 7 8 to
Q1 magnet by C Ballard. #6 and 8 went on
with no issues. The copper tubing on insulator
 P1020033.JPGP1020037.JPGP1020038.JPGP1020035.JPGP1020031.JPG 
  6   Thursday, March 01, 2012, 16:01 Keith C NgPrimary BeamlinesRepair2C Rad Hard Valve Replacement4" indium flanges at the 2C rad hard
valve were cleaned of the remaining indium
by C. Ballard. Both upstream and down stream
  
  7   Thursday, May 24, 2012, 18:59 Grant MinorM20RepairM20 front-end leak vacuum check T2/Q1/Q2/Scraper

Normal
0




false
false
false
 6x 
  8   Thursday, October 11, 2012, 16:40 Keith C NgM9Repairm9 t2 joint repairToday:
Bridge setup complete; Noticed 12
x 3 x 3 block when placed on top of several
 20121011_RH1_01_0357.JPG20121011_RH1_02_0367.JPG20121011_RH1_02_0362.JPG20121011_RH1_02_0363.JPG 
  9   Friday, October 12, 2012, 15:12 Keith C NgM9RepairM9 T2 Joint Repair cont.Joint repair continues.
 
Leak Check:
 20121012_RH2_01_0002.JPG20121012_RH2_01_0004.JPG 
  10   Monday, October 15, 2012, 17:03 Keith C NgM9RepairM9 T2 joint repair cont.Today:
- Removed pins and removed indium
through ring. Joint fully open at 14.5 to
  
  11   Tuesday, October 16, 2012, 19:47 Grant MinorM9RepairInspection of failed double-indium thru-ring TB22148See inspection notes attached for failed
M9T2 double-indium thru-ring TB22148, inspected
on Oct 15th 2012.
 TB22148_thru_ring_inspT2_15oct2012.pdfTB22148_thru_ring_inspQ1_15oct2012.pdf 
  12   Tuesday, October 16, 2012, 19:50 Grant MinorM9RepairM9T2 Joint Repair - Status Update 16 Oct 2012See attached.  M9T2_Joint_Repair_-_Status_Update_16_Oct_2012.pdf 
  13   Thursday, October 18, 2012, 08:26 Keith C NgM9RepairM9 T2 joint repair cont.Yesterday:
Installed indium blank off at M9
T2 joint and pumped down at 15:20 to 15:45
  
  14   Thursday, October 18, 2012, 16:28 Keith C NgM9RepairM9 T2 joint repair cont.Today:
Completed leak check of M9 T2 area:
joint(s) are He leak tight. Remote He lines
 T2_Remote_Leak_Check.PDF20121018_m9q2_waterleak.jpg 
  15   Friday, October 19, 2012, 16:48 Keith C NgM9RepairM9 T2 Joint Repair cont.Today:
Cleaned up work site and removed
extraneous poles and tooling. Radioactive
 20121019_RH1_01_0081.JPG20121019_RH1_01_0082.JPG20121019_RH2_02_0004.JPG 
  17   Monday, October 22, 2012, 15:48 Keith C NgM9RepairM9 T2 clean up and shield restorationToday;
Restoring shielding at M9 T2 area
and cleaning up RH setup.
 20121022_RH1_02_0092.JPG20121022_RH1_02_0081.JPG20121022_RH1_02_0082.JPG 