ID Date Author Target Materialdown Target Oven W.O# Source Status Subject
  282   Monday, March 14, 2016, 19:22 Aurelia LaxdalTa41790-1LP-SISIn progressTa#47 LP-SIS (with new center block) conditioning

Anders Mjos wrote:

Laura Lambert wrote:

Aurelia Laxdal wrote:

Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).

 Monday, March 14, 2016, 09:20

One thermocouple was not welded on correctly and is not working. 

Cooling evap2 back down, to remove target and re-weld thermocouple.

Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.


 

 Monday, March 14, 2016, 13:12: Stopped turbo pump

 After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.

  283   Friday, March 18, 2016, 17:13 Aurelia LaxdalTa41790-1LP-SISIn progressTa#47 LP-SIS (with new center block) conditioning

Aurelia Laxdal wrote:

Anders Mjos wrote:

Laura Lambert wrote:

Aurelia Laxdal wrote:

Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).

 Monday, March 14, 2016, 09:20

One thermocouple was not welded on correctly and is not working. 

Cooling evap2 back down, to remove target and re-weld thermocouple.

Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.


 

 Monday, March 14, 2016, 13:12: Stopped turbo pump

 After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.

 Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.

  284   Monday, March 21, 2016, 18:57 Aurelia LaxdalTa41790-1LP-SISIn progressTa#47 LP-SIS (with new center block) conditioning

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

Laura Lambert wrote:

Aurelia Laxdal wrote:

Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).

 Monday, March 14, 2016, 09:20

One thermocouple was not welded on correctly and is not working. 

Cooling evap2 back down, to remove target and re-weld thermocouple.

Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.


 

 Monday, March 14, 2016, 13:12: Stopped turbo pump

 After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.

 Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.

Today, lowered the TGHT from 620A (at 1894 deg C) to 300A.  TBHT is still at 230A.

  285   Tuesday, March 22, 2016, 11:31 Aurelia LaxdalTa41790-1LP-SISIn progressTa#47 LP-SIS (with new center block) conditioning

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

Laura Lambert wrote:

Aurelia Laxdal wrote:

Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).

 Monday, March 14, 2016, 09:20

One thermocouple was not welded on correctly and is not working. 

Cooling evap2 back down, to remove target and re-weld thermocouple.

Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.


 

 Monday, March 14, 2016, 13:12: Stopped turbo pump

 After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.

 Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.

Today, lowered the TGHT from 620A (at 1894 deg C) to 300A.  TBHT is still at 230A.

 Cooling down the target.

 

  286   Thursday, March 24, 2016, 11:32 John WongTa41790-1LP-SISDoneTa#47 LP-SIS (with new center block) conditioning

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

Laura Lambert wrote:

Aurelia Laxdal wrote:

Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).

 Monday, March 14, 2016, 09:20

One thermocouple was not welded on correctly and is not working. 

Cooling evap2 back down, to remove target and re-weld thermocouple.

Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.


 

 Monday, March 14, 2016, 13:12: Stopped turbo pump

 After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.

 Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.

Today, lowered the TGHT from 620A (at 1894 deg C) to 300A.  TBHT is still at 230A.

 Cooling down the target.

 

Thursday, March 24, 2016, 11:29 

Target was removed from the Evaporator.  

The thermocouples broke off.  

Need to insert Re foil prior to installing


 

 

  290   Tuesday, April 19, 2016, 09:28 Anders MjosTa41790-1LP-SISDoneTa#47 LP-SIS (with new center block) conditioning

John Wong wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

Laura Lambert wrote:

Aurelia Laxdal wrote:

Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).

 Monday, March 14, 2016, 09:20

One thermocouple was not welded on correctly and is not working. 

Cooling evap2 back down, to remove target and re-weld thermocouple.

Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.


 

 Monday, March 14, 2016, 13:12: Stopped turbo pump

 After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.

 Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.

Today, lowered the TGHT from 620A (at 1894 deg C) to 300A.  TBHT is still at 230A.

 Cooling down the target.

 

Thursday, March 24, 2016, 11:29 

Target was removed from the Evaporator.  

The thermocouples broke off.  

Need to insert Re foil prior to installing


 

 

 Tuesday, April 19, 2016, 09:28: Uploaded thermoucouple data.

Attachment 1: 2016-03-11_Evaporator_2.4ch
°C	Date Time	T1 - C	T2 - C	T3 - C	T4 - C	
1	2016/03/11 14:25:25	21.1	24.7	 	 	
2	2016/03/11 14:25:55	25.0	24.8	 	 	
3	2016/03/11 14:26:25	21.6	- - -	 	 	
4	2016/03/11 14:26:55	21.0	- - -	 	 	
5	2016/03/11 14:27:25	21.3	- - -	 	 	
6	2016/03/11 14:27:55	21.1	- - -	 	 	
7	2016/03/11 14:28:25	21.1	- - -	 	 	
8	2016/03/11 14:28:55	21.0	- - -	 	 	
9	2016/03/11 14:29:25	21.1	- - -	 	 	
10	2016/03/11 14:29:55	21.1	- - -	 	 	
11	2016/03/11 14:30:25	21.1	- - -	 	 	
12	2016/03/11 14:30:55	21.1	- - -	 	 	
13	2016/03/11 14:31:25	21.1	- - -	 	 	
14	2016/03/11 14:31:55	21.1	- - -	 	 	
15	2016/03/11 14:32:25	21.1	- - -	 	 	
16	2016/03/11 14:32:55	21.1	- - -	 	 	
17	2016/03/11 14:33:25	20.0	- - -	 	 	
18	2016/03/11 14:33:55	20.2	- - -	 	 	
19	2016/03/11 14:34:25	20.8	- - -	 	 	
20	2016/03/11 14:34:55	20.8	- - -	 	 	
21	2016/03/11 14:35:25	21.1	- - -	 	 	
22	2016/03/11 14:35:55	19.7	- - -	 	 	
23	2016/03/11 14:36:25	20.8	- - -	 	 	
24	2016/03/11 14:36:55	20.7	- - -	 	 	
25	2016/03/11 14:37:25	21.3	- - -	 	 	
26	2016/03/11 14:37:55	21.1	- - -	 	 	
27	2016/03/11 14:38:25	21.2	- - -	 	 	
28	2016/03/11 14:38:55	20.2	- - -	 	 	
29	2016/03/11 14:39:25	20.7	- - -	 	 	
30	2016/03/11 14:39:55	20.8	- - -	 	 	
31	2016/03/11 14:40:25	21.3	- - -	 	 	
32	2016/03/11 14:40:55	19.7	- - -	 	 	
33	2016/03/11 14:41:25	20.8	- - -	 	 	
34	2016/03/11 14:41:55	20.8	- - -	 	 	
35	2016/03/11 14:42:25	20.8	- - -	 	 	
36	2016/03/11 14:42:55	20.8	- - -	 	 	
37	2016/03/11 14:43:25	20.8	- - -	 	 	
38	2016/03/11 14:43:55	20.8	- - -	 	 	
39	2016/03/11 14:44:25	20.8	- - -	 	 	
40	2016/03/11 14:44:55	20.2	- - -	 	 	
41	2016/03/11 14:45:25	20.8	- - -	 	 	
42	2016/03/11 14:45:55	21.3	- - -	 	 	
43	2016/03/11 14:46:25	20.8	- - -	 	 	
44	2016/03/11 14:46:55	20.4	- - -	 	 	
45	2016/03/11 14:47:25	20.8	- - -	 	 	
46	2016/03/11 14:47:55	20.8	- - -	 	 	
47	2016/03/11 14:48:25	20.8	- - -	 	 	
48	2016/03/11 14:48:55	20.3	- - -	 	 	
49	2016/03/11 14:49:25	20.4	- - -	 	 	
50	2016/03/11 14:49:55	19.9	- - -	 	 	
51	2016/03/11 14:50:25	20.4	- - -	 	 	
52	2016/03/11 14:50:55	20.8	- - -	 	 	
53	2016/03/11 14:51:25	20.5	- - -	 	 	
54	2016/03/11 14:51:55	20.4	- - -	 	 	
55	2016/03/11 14:52:25	20.5	- - -	 	 	
56	2016/03/11 14:52:55	20.4	- - -	 	 	
57	2016/03/11 14:53:25	20.8	- - -	 	 	
58	2016/03/11 14:53:55	20.8	- - -	 	 	
59	2016/03/11 14:54:25	20.3	- - -	 	 	
60	2016/03/11 14:54:55	19.8	- - -	 	 	
61	2016/03/11 14:55:25	20.3	- - -	 	 	
62	2016/03/11 14:55:55	20.4	- - -	 	 	
63	2016/03/11 14:56:25	21.3	- - -	 	 	
64	2016/03/11 14:56:55	21.3	- - -	 	 	
65	2016/03/11 14:57:25	20.5	- - -	 	 	
66	2016/03/11 14:57:55	21.3	- - -	 	 	
67	2016/03/11 14:58:25	21.3	- - -	 	 	
68	2016/03/11 14:58:55	20.4	- - -	 	 	
69	2016/03/11 14:59:25	20.0	- - -	 	 	
70	2016/03/11 14:59:55	20.4	- - -	 	 	
71	2016/03/11 15:00:25	19.8	- - -	 	 	
72	2016/03/11 15:00:55	19.8	- - -	 	 	
73	2016/03/11 15:01:25	19.8	- - -	 	 	
74	2016/03/11 15:01:55	20.4	- - -	 	 	
75	2016/03/11 15:02:25	20.4	- - -	 	 	
76	2016/03/11 15:02:55	20.3	- - -	 	 	
77	2016/03/11 15:03:25	21.2	- - -	 	 	
78	2016/03/11 15:03:55	20.0	- - -	 	 	
79	2016/03/11 15:04:25	21.0	- - -	 	 	
80	2016/03/11 15:04:55	20.5	- - -	 	 	
81	2016/03/11 15:05:25	20.0	- - -	 	 	
82	2016/03/11 15:05:55	20.5	- - -	 	 	
83	2016/03/11 15:06:25	20.5	- - -	 	 	
84	2016/03/11 15:06:55	21.4	- - -	 	 	
85	2016/03/11 15:07:25	21.4	- - -	 	 	
86	2016/03/11 15:07:55	20.5	- - -	 	 	
87	2016/03/11 15:08:25	20.5	- - -	 	 	
88	2016/03/11 15:08:55	20.5	- - -	 	 	
89	2016/03/11 15:09:25	21.4	- - -	 	 	
90	2016/03/11 15:09:55	20.5	- - -	 	 	
91	2016/03/11 15:10:25	21.0	- - -	 	 	
92	2016/03/11 15:10:55	21.0	- - -	 	 	
93	2016/03/11 15:11:25	20.0	- - -	 	 	
94	2016/03/11 15:11:55	21.0	- - -	 	 	
95	2016/03/11 15:12:25	21.0	- - -	 	 	
96	2016/03/11 15:12:55	20.5	- - -	 	 	
97	2016/03/11 15:13:25	21.0	- - -	 	 	
98	2016/03/11 15:13:55	20.5	- - -	 	 	
99	2016/03/11 15:14:25	20.5	- - -	 	 	
100	2016/03/11 15:14:55	20.5	- - -	 	 	
101	2016/03/11 15:15:25	20.0	- - -	 	 	
102	2016/03/11 15:15:55	21.0	- - -	 	 	
103	2016/03/11 15:16:25	21.0	- - -	 	 	
104	2016/03/11 15:16:55	19.9	- - -	 	 	
105	2016/03/11 15:17:25	21.0	- - -	 	 	
106	2016/03/11 15:17:55	21.4	- - -	 	 	
107	2016/03/11 15:18:25	20.8	- - -	 	 	
108	2016/03/11 15:18:55	20.5	- - -	 	 	
109	2016/03/11 15:19:25	21.0	- - -	 	 	
110	2016/03/11 15:19:55	20.0	- - -	 	 	
111	2016/03/11 15:20:25	19.9	- - -	 	 	
112	2016/03/11 15:20:55	21.4	- - -	 	 	
113	2016/03/11 15:21:25	20.8	- - -	 	 	
114	2016/03/11 15:21:55	20.8	- - -	 	 	
115	2016/03/11 15:22:25	20.8	- - -	 	 	
116	2016/03/11 15:22:55	20.3	- - -	 	 	
117	2016/03/11 15:23:25	21.3	- - -	 	 	
118	2016/03/11 15:23:55	20.8	- - -	 	 	
119	2016/03/11 15:24:25	20.8	- - -	 	 	
120	2016/03/11 15:24:55	20.4	- - -	 	 	
121	2016/03/11 15:25:25	21.0	- - -	 	 	
122	2016/03/11 15:25:55	20.5	- - -	 	 	
123	2016/03/11 15:26:25	20.4	- - -	 	 	
124	2016/03/11 15:26:55	20.8	- - -	 	 	
125	2016/03/11 15:27:25	21.3	- - -	 	 	
126	2016/03/11 15:27:55	21.3	- - -	 	 	
127	2016/03/11 15:28:25	20.8	- - -	 	 	
128	2016/03/11 15:28:55	21.3	- - -	 	 	
129	2016/03/11 15:29:25	21.3	- - -	 	 	
130	2016/03/11 15:29:55	20.7	- - -	 	 	
131	2016/03/11 15:30:25	21.3	- - -	 	 	
132	2016/03/11 15:30:55	21.3	- - -	 	 	
133	2016/03/11 15:31:25	20.8	- - -	 	 	
134	2016/03/11 15:31:55	20.7	- - -	 	 	
135	2016/03/11 15:32:25	21.3	- - -	 	 	
136	2016/03/11 15:32:55	21.3	- - -	 	 	
137	2016/03/11 15:33:25	20.8	- - -	 	 	
138	2016/03/11 15:33:55	20.8	- - -	 	 	
139	2016/03/11 15:34:25	20.8	- - -	 	 	
140	2016/03/11 15:34:55	19.9	- - -	 	 	
141	2016/03/11 15:35:25	21.3	- - -	 	 	
142	2016/03/11 15:35:55	20.8	- - -	 	 	
143	2016/03/11 15:36:25	20.8	- - -	 	 	
144	2016/03/11 15:36:55	21.3	- - -	 	 	
145	2016/03/11 15:37:25	20.4	- - -	 	 	
146	2016/03/11 15:37:55	20.2	- - -	 	 	
147	2016/03/11 15:38:25	21.3	- - -	 	 	
148	2016/03/11 15:38:55	20.7	- - -	 	 	
149	2016/03/11 15:39:25	20.8	- - -	 	 	
150	2016/03/11 15:39:55	20.8	- - -	 	 	
151	2016/03/11 15:40:25	20.7	- - -	 	 	
152	2016/03/11 15:40:55	20.3	- - -	 	 	
153	2016/03/11 15:41:25	20.8	- - -	 	 	
154	2016/03/11 15:41:55	19.8	- - -	 	 	
155	2016/03/11 15:42:25	19.7	- - -	 	 	
156	2016/03/11 15:42:55	21.2	- - -	 	 	
157	2016/03/11 15:43:25	20.7	- - -	 	 	
158	2016/03/11 15:43:55	20.2	- - -	 	 	
159	2016/03/11 15:44:25	20.8	- - -	 	 	
160	2016/03/11 15:44:55	20.7	- - -	 	 	
161	2016/03/11 15:45:25	20.8	- - -	 	 	
162	2016/03/11 15:45:55	21.3	- - -	 	 	
163	2016/03/11 15:46:25	20.8	- - -	 	 	
164	2016/03/11 15:46:55	20.2	- - -	 	 	
165	2016/03/11 15:47:25	21.3	- - -	 	 	
166	2016/03/11 15:47:55	20.8	- - -	 	 	
167	2016/03/11 15:48:25	21.3	- - -	 	 	
168	2016/03/11 15:48:55	21.3	- - -	 	 	
169	2016/03/11 15:49:25	21.3	- - -	 	 	
170	2016/03/11 15:49:55	20.8	- - -	 	 	
171	2016/03/11 15:50:25	19.8	- - -	 	 	
172	2016/03/11 15:50:55	20.8	- - -	 	 	
173	2016/03/11 15:51:25	21.3	- - -	 	 	
174	2016/03/11 15:51:55	19.7	- - -	 	 	
175	2016/03/11 15:52:25	20.8	- - -	 	 	
176	2016/03/11 15:52:55	20.8	- - -	 	 	
177	2016/03/11 15:53:25	20.4	- - -	 	 	
178	2016/03/11 15:53:55	20.8	- - -	 	 	
179	2016/03/11 15:54:25	21.3	- - -	 	 	
180	2016/03/11 15:54:55	21.3	- - -	 	 	
181	2016/03/11 15:55:25	20.8	- - -	 	 	
182	2016/03/11 15:55:55	20.8	- - -	 	 	
183	2016/03/11 15:56:25	20.4	- - -	 	 	
184	2016/03/11 15:56:55	19.8	- - -	 	 	
185	2016/03/11 15:57:25	21.3	- - -	 	 	
186	2016/03/11 15:57:55	21.3	- - -	 	 	
187	2016/03/11 15:58:25	21.3	- - -	 	 	
188	2016/03/11 15:58:55	20.4	- - -	 	 	
189	2016/03/11 15:59:25	21.3	- - -	 	 	
190	2016/03/11 15:59:55	20.8	- - -	 	 	
191	2016/03/11 16:00:25	20.8	- - -	 	 	
192	2016/03/11 16:00:55	19.7	- - -	 	 	
193	2016/03/11 16:01:25	20.3	- - -	 	 	
194	2016/03/11 16:01:55	21.3	- - -	 	 	
195	2016/03/11 16:02:25	20.8	- - -	 	 	
196	2016/03/11 16:02:55	21.3	- - -	 	 	
197	2016/03/11 16:03:25	21.3	- - -	 	 	
198	2016/03/11 16:03:55	20.8	- - -	 	 	
199	2016/03/11 16:04:25	20.2	- - -	 	 	
200	2016/03/11 16:04:55	21.3	- - -	 	 	
201	2016/03/11 16:05:25	20.2	- - -	 	 	
202	2016/03/11 16:05:55	20.2	- - -	 	 	
203	2016/03/11 16:06:25	20.3	- - -	 	 	
204	2016/03/11 16:06:55	20.2	- - -	 	 	
205	2016/03/11 16:07:25	19.7	- - -	 	 	
206	2016/03/11 16:07:55	21.3	- - -	 	 	
207	2016/03/11 16:08:25	19.7	- - -	 	 	
208	2016/03/11 16:08:55	21.3	- - -	 	 	
209	2016/03/11 16:09:25	20.8	- - -	 	 	
210	2016/03/11 16:09:55	20.8	- - -	 	 	
211	2016/03/11 16:10:25	20.8	- - -	 	 	
212	2016/03/11 16:10:55	21.3	- - -	 	 	
213	2016/03/11 16:11:25	21.3	- - -	 	 	
214	2016/03/11 16:11:55	21.3	- - -	 	 	
215	2016/03/11 16:12:25	20.8	- - -	 	 	
216	2016/03/11 16:12:55	20.8	- - -	 	 	
217	2016/03/11 16:13:25	20.1	- - -	 	 	
218	2016/03/11 16:13:55	20.2	- - -	 	 	
219	2016/03/11 16:14:25	21.3	- - -	 	 	
220	2016/03/11 16:14:55	21.3	- - -	 	 	
221	2016/03/11 16:15:25	20.8	- - -	 	 	
222	2016/03/11 16:15:55	20.8	- - -	 	 	
223	2016/03/11 16:16:25	20.3	- - -	 	 	
224	2016/03/11 16:16:55	21.1	- - -	 	 	
225	2016/03/11 16:17:25	20.8	- - -	 	 	
226	2016/03/11 16:17:55	20.3	- - -	 	 	
227	2016/03/11 16:18:25	20.3	- - -	 	 	
228	2016/03/11 16:18:55	20.6	- - -	 	 	
229	2016/03/11 16:19:25	19.8	- - -	 	 	
230	2016/03/11 16:19:55	20.2	- - -	 	 	
231	2016/03/11 16:20:25	20.8	- - -	 	 	
232	2016/03/11 16:20:55	20.6	- - -	 	 	
233	2016/03/11 16:21:25	21.3	- - -	 	 	
234	2016/03/11 16:21:55	20.6	- - -	 	 	
235	2016/03/11 16:22:25	20.8	- - -	 	 	
236	2016/03/11 16:22:55	20.8	- - -	 	 	
237	2016/03/11 16:23:25	21.1	- - -	 	 	
238	2016/03/11 16:23:55	20.8	- - -	 	 	
239	2016/03/11 16:24:25	20.4	- - -	 	 	
240	2016/03/11 16:24:55	20.2	- - -	 	 	
241	2016/03/11 16:25:25	21.3	- - -	 	 	
242	2016/03/11 16:25:55	20.8	- - -	 	 	
243	2016/03/11 16:26:25	20.4	- - -	 	 	
244	2016/03/11 16:26:55	20.8	- - -	 	 	
245	2016/03/11 16:27:25	19.8	- - -	 	 	
246	2016/03/11 16:27:55	19.9	- - -	 	 	
247	2016/03/11 16:28:25	20.2	- - -	 	 	
248	2016/03/11 16:28:55	20.8	- - -	 	 	
249	2016/03/11 16:29:25	20.8	- - -	 	 	
250	2016/03/11 16:29:55	21.3	- - -	 	 	
251	2016/03/11 16:30:25	21.1	- - -	 	 	
252	2016/03/11 16:30:55	20.8	- - -	 	 	
253	2016/03/11 16:31:25	21.3	- - -	 	 	
254	2016/03/11 16:31:55	21.3	- - -	 	 	
255	2016/03/11 16:32:25	21.3	- - -	 	 	
256	2016/03/11 16:32:55	20.8	- - -	 	 	
257	2016/03/11 16:33:25	21.1	- - -	 	 	
258	2016/03/11 16:33:55	20.8	- - -	 	 	
259	2016/03/11 16:34:25	20.3	- - -	 	 	
260	2016/03/11 16:34:55	21.2	- - -	 	 	
261	2016/03/11 16:35:25	20.8	- - -	 	 	
262	2016/03/11 16:35:55	20.8	- - -	 	 	
263	2016/03/11 16:36:25	20.8	- - -	 	 	
264	2016/03/11 16:36:55	21.3	- - -	 	 	
265	2016/03/11 16:37:25	21.3	- - -	 	 	
266	2016/03/11 16:37:55	21.3	- - -	 	 	
267	2016/03/11 16:38:25	21.3	- - -	 	 	
268	2016/03/11 16:38:55	19.8	- - -	 	 	
269	2016/03/11 16:39:25	20.2	- - -	 	 	
270	2016/03/11 16:39:55	20.8	- - -	 	 	
271	2016/03/11 16:40:25	20.8	- - -	 	 	
272	2016/03/11 16:40:55	20.8	- - -	 	 	
273	2016/03/11 16:41:25	20.8	- - -	 	 	
274	2016/03/11 16:41:55	20.8	- - -	 	 	
275	2016/03/11 16:42:25	21.3	- - -	 	 	
276	2016/03/11 16:42:55	21.3	- - -	 	 	
277	2016/03/11 16:43:25	20.7	- - -	 	 	
278	2016/03/11 16:43:55	20.2	- - -	 	 	
279	2016/03/11 16:44:25	20.3	- - -	 	 	
280	2016/03/11 16:44:55	20.4	- - -	 	 	
281	2016/03/11 16:45:25	20.2	- - -	 	 	
282	2016/03/11 16:45:55	20.2	- - -	 	 	
283	2016/03/11 16:46:25	21.3	- - -	 	 	
284	2016/03/11 16:46:55	20.8	- - -	 	 	
285	2016/03/11 16:47:25	20.8	- - -	 	 	
286	2016/03/11 16:47:55	20.8	- - -	 	 	
287	2016/03/11 16:48:25	20.7	- - -	 	 	
288	2016/03/11 16:48:55	20.8	- - -	 	 	
289	2016/03/11 16:49:25	19.9	- - -	 	 	
290	2016/03/11 16:49:55	20.2	- - -	 	 	
291	2016/03/11 16:50:25	21.3	- - -	 	 	
292	2016/03/11 16:50:55	21.3	- - -	 	 	
293	2016/03/11 16:51:25	20.5	- - -	 	 	
294	2016/03/11 16:51:55	21.3	- - -	 	 	
295	2016/03/11 16:52:25	21.3	- - -	 	 	
296	2016/03/11 16:52:55	21.3	- - -	 	 	
297	2016/03/11 16:53:25	20.8	- - -	 	 	
298	2016/03/11 16:53:55	20.5	- - -	 	 	
299	2016/03/11 16:54:25	20.5	- - -	 	 	
... 53646 more lines ...
Attachment 2: 2016-03-11_Evaporator_2.xlsx
  310   Tuesday, July 26, 2016, 16:53 Laura LambertTa41369-6HP-SISDoneConditioning Ta#49

 Tuesday, July 26, 2016, 16:50

loaded into evap2

pumped down, HS water valves opened, no leaks detected.

tapped up manually to 35A

vacuum stable = 3.8e-6 Torr

Initiating auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively.

Final setpoints at 230A for the TBHT and 600A for the TGHT.

Final desired temperature = 1800C


 Wednesday, July 27, 2016, 09:20

IGP1 = 6.3e-7 Torr, vacuum stable.

TGHT = 232A, 2.7V

TBHT = 131A, 1.76V

Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.


 Wednesday, July 27, 2016, 15:46

TGHT = 600A, 8.87V

TBHT = 230A, 3.7V

IGP1 = 1.37e-6 Torr

OMEGA = 1640C

Increased max TGHT voltage to 12V

Tapped up manually to OMEGA = 1810C

TGHT = 675A, 10.21V

IGP1 = 2.2e-6 Torr

Will remain at max setpoints for the rest of the week and cool down over weekend.


 Thursday, July 28, 2016, 08:34

TGHT = 675A, 10.41V

OMEGA = 1833C

Tapped down to 660A, 10.09V

OMEGA = 1805C


 Friday, July 29, 2016, 13:57

OMEGA = 1814C

TGHT = 660A, 10.16V

TBHT = 230A, 3.72V

IGP1 = 3.43e-7 Torr

evap2 has remained at max setpoints for ~42hrs

conditioning complete.

Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


 Tuesday, August 02, 2016, 13:39

vented in air and removed from evap2 this morning.

target looks good!


 

  328   Friday, October 07, 2016, 16:42 Laura LambertTa41790-5LP-SISIn progressConditioning Ta#50

Friday, October 07, 2016, 16:40

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass 47.6889g [Incl foils + Ta wire on 6 packs]

Note: Target consists of 350 single discs and 6x20 packs of Ta discs

3x Ta Heat shields.

No endcaps inserted, no Rh foil inserted.

Chamber currently pumping down.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 300A at 2.0A/min.

Final desired temperature = 1900C


 Tuesday, October 11, 2016, 10:02
 
HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 2e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

 Wednesday, October 12, 2016, 16:15

Tapped up to 1900C? [see attached link for data concerning temperature readings]

TGHT = 450A, 7.16V

TBHT = 230A, 4.1V

OMEGA = 1748C

IGP1 = 6.1e-7 Torr


 

Attachment 1: Ta#50_no_endcaps_3xh.s..xlsx
  329   Wednesday, October 12, 2016, 21:18 John WongTa41790-5LP-SISIn progressConditioning Ta#50

Laura Lambert wrote:

Friday, October 07, 2016, 16:40

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass g [Incl foils + Ta wire on 6 packs]

Note: Target consists of 350 single discs and 6x20 packs of Ta discs

3x Ta Heat shields.

No endcaps inserted, no Rh foil inserted.

Chamber currently pumping down.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 300A at 2.0A/min.

Final desired temperature = 1900C


 Tuesday, October 11, 2016, 10:02
 
HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 2e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

 Wednesday, October 12, 2016, 16:15

Tapped up to 1900C? [see attached link for data concerning temperature readings]

TGHT = 450A, 7.16V

TBHT = 230A, 4.1V

OMEGA = 1748C

IGP1 = 6.1e-7 Torr


 

 Wednesday, October 12, 2016, 21:14

Current status before cooling down:

TGHT at 450A/7.32V; TBHT at 230A/4.10V; OMEGA at 1747C

Vacuum at 4.05 e-7 Torr.

Initiate auto-rampping at 2A/min for TGHT and 1A/min for TBHT


 

  330   Thursday, October 13, 2016, 17:32 Laura LambertTa41790-5LP-SISDoneConditioning Ta#50

John Wong wrote:

Laura Lambert wrote:

Friday, October 07, 2016, 16:40

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass g [Incl foils + Ta wire on 6 packs]

Note: Target consists of 350 single discs and 6x20 packs of Ta discs

3x Ta Heat shields.

No endcaps inserted, no Rh foil inserted.

Chamber currently pumping down.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 300A at 2.0A/min.

Final desired temperature = 1900C


 Tuesday, October 11, 2016, 10:02
 
HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 2e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

 Wednesday, October 12, 2016, 16:15

Tapped up to 1900C? [see attached link for data concerning temperature readings]

TGHT = 450A, 7.16V

TBHT = 230A, 4.1V

OMEGA = 1748C

IGP1 = 6.1e-7 Torr


 

 Wednesday, October 12, 2016, 21:14

Current status before cooling down:

TGHT at 450A/7.32V; TBHT at 230A/4.10V; OMEGA at 1747C

Vacuum at 4.05 e-7 Torr.

Initiate auto-rampping at 2A/min for TGHT and 1A/min for TBHT


 

 Thursday, October 13, 2016, 17:32

vented in air and opened up this morning.

target looks good.

  331   Thursday, October 13, 2016, 18:05 Laura LambertTa41790-5LP-SISIn progressTemperature measurements for Ta#50

Thursday, October 13, 2016, 18:04

Target loaded into evap2

No heat shields.

Both endcaps inserted and expanded.

Rh foil inserted [when inserting, the Ta rod used to expand the Rh foil inside the ionizer tube snapped off inside the container - this piece was able to be shaken out and is no longer inside]

Chamber pumped down.

HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 5e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 300A at 2.0A/min.

Final desired temperature = 1900C


Friday, October 14, 2016, 13:28

TGHT and TBHT had reached 300A/ 230A respectively.

Power bump ~10min ago caused evap2 to trip off.

Tapped back up manually to 35A.

Re-initiating auto ramp now.


 

  332   Saturday, October 15, 2016, 12:42 Aurelia LaxdalTa41790-5LP-SISIn progressTemperature measurements for Ta#50

Laura Lambert wrote:

Thursday, October 13, 2016, 18:04

Target loaded into evap2

No heat shields.

Both endcaps inserted and expanded.

Rh foil inserted [when inserting, the Ta rod used to expand the Rh foil inside the ionizer tube snapped off inside the container - this piece was able to be shaken out and is no longer inside]

Chamber pumped down.

HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 5e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 300A at 2.0A/min.

Final desired temperature = 1900C


Friday, October 14, 2016, 13:28

TGHT and TBHT had reached 300A/ 230A respectively.

Power bump ~10min ago caused evap2 to trip off.

Tapped back up manually to 35A.

Re-initiating auto ramp now.


 

Friday October 14: the target was ramp up to 300A/230A after Laura started it. Then, I cooled down at 6pm before leaving TRIUMF. <br>

Saturday October 15: restated the auto-ramp for Ta#50 in EVAP2. It's currently set to go to 300A/230A.

  333   Sunday, October 16, 2016, 17:55 Aurelia LaxdalTa41790-5LP-SISIn progressTemperature measurements for Ta#50

Aurelia Laxdal wrote:

Laura Lambert wrote:

Thursday, October 13, 2016, 18:04

Target loaded into evap2

No heat shields.

Both endcaps inserted and expanded.

Rh foil inserted [when inserting, the Ta rod used to expand the Rh foil inside the ionizer tube snapped off inside the container - this piece was able to be shaken out and is no longer inside]

Chamber pumped down.

HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 5e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 300A at 2.0A/min.

Final desired temperature = 1900C


Friday, October 14, 2016, 13:28

TGHT and TBHT had reached 300A/ 230A respectively.

Power bump ~10min ago caused evap2 to trip off.

Tapped back up manually to 35A.

Re-initiating auto ramp now.


 

Friday October 14: the target was ramp up to 300A/230A after Laura started it. Then, I cooled down at 6pm before leaving TRIUMF. <br>

Saturday October 15: restated the auto-ramp for Ta#50 in EVAP2. It's currently set to go to 300A/230A.

 Sunday October 16: the target temperature measurements up to 620A/230A were performed today not on October 15 (yesterday, it was cooled down before reaching 300A/230A). Currently the target is cooling down, to be ready tomorrow morning for the Test Stand. 

  334   Tuesday, October 18, 2016, 09:23 Laura LambertTa41790-5LP-SISDoneTemperature measurements for Ta#50

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Laura Lambert wrote:

Thursday, October 13, 2016, 18:04

Target loaded into evap2

No heat shields.

Both endcaps inserted and expanded.

Rh foil inserted [when inserting, the Ta rod used to expand the Rh foil inside the ionizer tube snapped off inside the container - this piece was able to be shaken out and is no longer inside]

Chamber pumped down.

HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 5e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 300A at 2.0A/min.

Final desired temperature = 1900C


Friday, October 14, 2016, 13:28

TGHT and TBHT had reached 300A/ 230A respectively.

Power bump ~10min ago caused evap2 to trip off.

Tapped back up manually to 35A.

Re-initiating auto ramp now.


 

Friday October 14: the target was ramp up to 300A/230A after Laura started it. Then, I cooled down at 6pm before leaving TRIUMF. <br>

Saturday October 15: restated the auto-ramp for Ta#50 in EVAP2. It's currently set to go to 300A/230A.

 Sunday October 16: the target temperature measurements up to 620A/230A were performed today not on October 15 (yesterday, it was cooled down before reaching 300A/230A). Currently the target is cooling down, to be ready tomorrow morning for the Test Stand. 

 Monday, October 17, 2016, 09:21

Vented in air and taken out this morning.

Target looks good!


 

  341   Friday, December 16, 2016, 14:14 Laura LambertTa39530-3LP-FEBIADDoneConditioning Ta FEBIAD target for shutdown tests

 Friday, December 16, 2016, 14:08

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass 45.9091g [Incl foils + Ta wire on 6 packs]

Target consists of 350 single discs and 6x20 packs of Ta discs

Discs in target are arranged as follows: 1pack / 75singles / 1pack / 100singles / 2packs / 100singles / 1pack / 75singles / 1pack

3x Ta Heat shields.

LP-FEBIAD container with large center block.

No endcaps inserted, no Rh foil inserted.

Chamber currently pumping down.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 350A at 2.0A/min.

Final desired temperature = 1900C


 Friday, December 16, 2016, 14:32

HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 2.1e-6 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

 Monday, December 19, 2016, 11:52

Tapped up manually to ~1900C [see attached excel for details on data collected - interesting temperature fluctuations]

 Will remain at max setpoints for min 4hrs then auto-cool


 Monday, December 19, 2016, 15:20

Target has remained at max setpoints for just over 4hrs

TGHT = 520A, 8.67V

OMEGA = 1820C

IGP1 = 5.2e-7 Torr

Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


 Tuesday, December 20, 2016, 11:52

Vented in air and opened up this morning.

Looks like the windows was coated in evap2, unsure if this was missed and coated before conditioning target or if this is from materials coming out during conditioning process...

Target looks good.

Endcaps inserted but not expanded.


 

Attachment 1: Ta-FEBIAD.xlsx
Attachment 2: Evernote_Camera_Roll_20161220_145947.jpg
Evernote_Camera_Roll_20161220_145947.jpg
  352   Monday, March 13, 2017, 15:34 Anders MjosTa41790-4LP-SISDoneConditioning Ta#51

Target container wrapped in 3x heat shield foils and installed by JW

 Monday, March 13, 2017, 15:33: Opened water for HS. Vacuum stable at IG1 1E-6 T 

Monday, March 13, 2017, 15:48: TGHT / TBHT to 30 / 15 A.

Monday, March 13, 2017, 15:54: Started auto-ramping to TGHT / TBHT 150 / 75 A at 1 / 0.5 A/min. Good/bad vacuum 3 / 4 E-5 Torr


Tuesday, March 14, 2017, 08:23: Continue auto-ramping to TGHT / TBHT 300 / 150 A. Vacuum stable at IG1 2.3E-7 T 

Tuesday, March 14, 2017, 11:18: Continue auto-ramping to TGHT / TBHT 350 / 200 A. Vacuum stable at IG1 3.8E-7 T 


Wednesday, March 15, 2017, 08:31: Continue auto-ramping to TGHT 375. Vacuum stable at IG1 2.5E-7 T. Omega at 1500 C

Wednesday, March 15, 2017, 16:34: Continue auto-ramping to TGHT 500. Vacuum increased to IG1 5.5E-7 T. Omega at 1887 C


Thursday, March 16, 2017, 08:34: Continue auto-ramping to TGHT 520. Vacuum increased to IG1 3.3E-7 T. Omega at 1888 C

Thursday, March 16, 2017, 08:48: TGHT at 521 A 8.99 V. Omega at 1899 C


Friday, March 17, 2017, 08:25: TGHT at 521 A 8.88 V. Omega at 1886 C. Vacuum IG1 2.5E-7 Torr

Ramping down


Wednesday, March 22, 2017, 08:42: Turbo pump stopped

  372   Tuesday, May 30, 2017, 14:40 Laura LambertTa42218-14LP-SISDoneConditioning Ta#52

 Tuesday, May 30, 2017, 14:36

Target consists of 400 discs.

Total packed length 2.9cm [exactly 8.05cm space on both sides]

Total mass 42.8228g [Incl foils + Ta wire on 4 packs]

Target consists of 320 single discs and 4x20 packs of Ta discs

Discs in target are arranged as follows: 80singles / 1pack / 80singles / 2packs / 80singles / 1pack / 80singles

3x Ta Heat shields.

No endcaps inserted, no Rh foil inserted.

Chamber currently pumping down.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 350A at 2.0A/min.

Final desired temperature = 1900C

OMEGA slope = 0.98

Windows cleaned.

Vacuum limit stop at 3.0e-5 Torr, backing off at 4.0e-5 Torr.


 Wednesday, May 31, 2017, 09:47

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

Vacuum stable.

IGP1 = 4.58e-7 Torr

IGP2 = 3.68e-7 Torr

Initiating auto ramp.


 Wednesday, May 31, 2017, 14:07

IGP1 = 1.11e-6 Torr

IGP2 = 1.13e-6 Torr

TGHT = 354A, 5.45V

TBHT =233A, 4.01V

OMEGA = 1565C

Increasing max setpoint to 400A at same ramping rate.


 Wednesday, May 31, 2017, 14:41

IGP1 = 1.19e-6 Torr

IGP2 = 1.24e-6 Torr

TGHT = 401A, 6.37V

OMEGA = 1708C

Increasing max setpoint to 425A at same ramping rate.


Wednesday, May 31, 2017, 15:51

Tapped up to ~1900C

TGHT = 480A, 7.85V

TBHT = 230A, 4.06V

OMEGA = 1912C

IGP1 = 1.85e-6 Torr

IGP2 = 2.06e-6 Torr

Will remain at max setpoints for a couple days before cooling


 Friday, June 02, 2017, 13:19

Remained at max setpoint for 2days

TGHT = 480A, 7.85V

TBHT = 230A, 4.06V

OMEGA = 1885C

IGP1 = 2.15e-7 Torr

IGP2 = 2.07e-7 Torr

Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


 Monday, June 05, 2017, 15:18

Vented in air and taken out this morning.

Target looks good 


 Wednesday, June 07, 2017, 15:41

Endcaps inserted.

Ta heat shield removed.

Rh foil inserted.

Handed off to assembly.


 

  377   Tuesday, June 20, 2017, 16:07 Laura LambertTa42218-6HP-SISDoneConditioning Ta#53

 Tuesday, June 20, 2017, 15:58

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass 50.3105g [Incl foils + Ta wire on 6 packs]

Target consists of 350 single discs and 6x20 packs of Ta discs

Discs in target are arranged as follows: 1pack / 75singles / 1pack / 100singles / 2packs / 100singles / 1pack / 75singles / 1pack

1 long Ta Heat shield.

No endcaps inserted, no Rh foil inserted.

Chamber currently pumping down.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 600A at 2.0A/min.

Final desired temperature = 1900C

OMEGA slope = 0.98

Vacuum limit stop at 3.0e-5 Torr, backing off at 4.0e-5 Torr.

*Note: container accidentally engraved with WO#412218-6 when it should be WO#42218-6


Wednesday, June 21, 2017, 10:05 

HS water valves opened, no leaks detected.

Tapped up manually to 40A, vacuum stable.

IGP1 = 5.53e-7 Torr

IGP2 = 4.35e-7 Torr

Initiating auto-ramp.


 Wednesday, June 21, 2017, 14:48

TGHT stopped at 575A due to voltage limit sitting at 9V

Increased max setpoint of voltage to 14V.

Re-started auto-ramp starting at 575A.


Wednesday, June 21, 2017, 15:23  

TGHT = 600A, 8.95V

TBHT = 230A, 3.72V

IGP1 = 1.55e-6 Torr

IGP2 = 1.62e-6 Torr

OMEGA = 1538C

Increasing max setpoint of TGHT to 700A


 Wednesday, June 21, 2017, 16:21

TGHT = 700A, 10.57V

TBHT = 230A, 3.75V

IGP1 = 2.2e-6 Torr

IGP2 = 2.4e-6 Torr

OMEGA = 1730C

Increasing max setpoint of TGHT to 750A


 Friday, June 23, 2017, 15:41

TGHT = 780A, 11.77V

TBHT = 230A, 3.77V

IGP1 = 4.8e-7 Torr

IGP2 = 4.8e-7 Torr

OMEGA = 1890C

Conditioning process complete.

Initiating auto-cool at 2.0A/min for the TGHT and 1.0A/min for the TBHT.


 Monday, June 26, 2017, 10:51

Target vented in air and removed from evap2 today.

Endcaps inserted.

Target looks good!


 

Attachment 1: Ta#53.JPG
Ta#53.JPG
  388   Friday, September 15, 2017, 10:56 Laura LambertTa42218-10HP-SISDoneConditioning Ta#54

 Friday, September 15, 2017, 09:44

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass g [Incl foils + Ta wire on 6 packs]

Target consists of 350 single discs and 6x20 packs of Ta discs

Discs in target are arranged as follows: 1pack / 75singles / 1pack / 100singles / 2packs / 100singles / 1pack / 75singles / 1pack

1 long Ta Heat shield on each side, not incl center block.

No endcaps inserted, no Rh foil inserted.

Loaded into evap2 yesterday.

Chamber pumped down overnight.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 650A at 2.0A/min.

Final desired temperature = 1900C

OMEGA slope = 0.98

HS water valves were already open.

Tapped up manually to 40A, vacuum stable.

IGP1 = 1.1e-6 Torr

IGP2 = 7.8e-7 Torr

Initiating auto-ramp.

Vacuum limit stop at 3.0e-5 Torr, backing off at 4.0e-5 Torr.


 Monday, September 18, 2017, 08:38

TGHT = 647A, 10.04V

TBHT = 233A, 3.51V

IGP1 = 4.65e-7 Torr

IGP2 = 3.78e-7 Torr

OMEGA = 1700C

Increasing max setpoint of TGHT to 750A


 Monday, September 18, 2017, 14:49

TGHT = 760A, 11.96V

TBHT = 233A, 3.54V

IGP1 = 8.9e-7 Torr

IGP2 = 8.6e-7 Torr

OMEGA = 1905C

Conditioning process complete.

Initiating auto-cool at 2.0A/min for the TGHT and 1.0A/min for the TBHT.


 Tuesday, September 19, 2017, 10:38

Target was cooled down in sections so Yasser could take some temperature measurements with his thermocouples.

Vented in air and removed from evap2 this morning.

Target looks good.

Endcaps inserted and expanded.

Inserting Rh foil this afternoon.


 Tuesday, September 26, 2017, 10:53

Tapped up manually to 230A over the course of ~35min.

TBHT striptool = 228A, 0.33V

TBHT direct readout = 230.4A, 0.33V

Vacuum good/ stable.

Minor spike to IGP1 = 1.5e-5 Torr ~5min after reached max setpoint of 230A.

IGP1 striptool = 3e-6 Torr

IGP1 direct readout = 3.79e-6 mBar

Initiating auto-cool at 2.0A/min.


 

Attachment 1: Capture.JPG
Capture.JPG
  404   Tuesday, April 17, 2018, 10:24 Laura LambertTa41177-3LP-SISDoneConditioning Ta#56 back-up target/ Temp measurements for Aurelia

 Tuesday, April 17, 2018, 10:20

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass g [Incl foils + Ta wire on 6 packs]

Target consists of 350 single discs and 6x20 packs of Ta discs

Discs in target are arranged as follows: 1pack / 75singles / 1pack / 100singles / 2packs / 100singles / 1pack / 75singles / 1pack

No Heat shields.

No endcaps inserted, no Rh foil inserted.

Chamber pumped down over night.

HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 6.5e-7 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

TGHT will be ramped up to 300A at 1.0A/min.

Aurelia will take over for temp measurements.

Final desired temperature = 1900C

Vacuum limit stop at 3.0e-5 Torr, backing off at 8.0e-5 Torr.


 Thursday, April 19, 2018, 08:39

First round of temperature measurements complete.

Reached a max current of 600A, ~1700C

Cooled down overnight.

Will remove from evap2, insert endcaps, and load back in for more measurements.


 Thursday, April 19, 2018, 12:35

Vented in air and removed from evap2.

See next elog for follow up temperature measurements.


 

ELOG V2.9.2-2455