Entry  Thursday, July 30, 2015, 17:07, John Wong, , , , Maintenance, Connect NALCW to EVAP1  

 Thursday, July 30, 2015, 17:02

EVAP1 cooling system is now on the NALCW.  The city water has been removed from the system.  

Tested all the cooling system interlocks by shutting off each individual valve, and the main supply valve to the lab -  All Passed!  


 

Entry  Friday, July 31, 2015, 15:10, John Wong, , , , Maintenance, Installed leftside port 

Friday, July 31, 2015, 15:09

The left side port was installed on the evaporator #2.  Leak check was performed and no leak was detected. 


 

Entry  Monday, August 24, 2015, 12:58, John Wong, , , , Maintenance, Replacing turbo pump, IEVAP2TP1 

 Monday, August 24, 2015, 12:54

The turbo pump was found to be faulty.  The pump couldn't get on full speed and eventually timed out.  Vacuum group inspected the pump and it is time for a service.  

A new pump has been installed.  Leak  check was performed and no leaks were detected.  

Pump is now fully operational. 

Back in business…. 


 

Entry  Thursday, November 05, 2015, 16:20, Laura Lambert, , 41077-3, LP-SIS, In progress, Sintering TaC coating on 'temporary endcaps' springs 2015-11-02_16.03.10.jpg'temporary_endcap'_springs_nov.3_2015.jpgIMG_20151105_141239627_HDR.jpgIMG_20151105_141248901_HDR.jpg

 Thursday, November 05, 2015, 16:19

Springs coated with TaC and loaded into container for sintering.

3x Ta heat shield.

EVAP2 currently pumping down.


 Friday, November 06, 2015, 08:39

Opened HS water valves, no leaks detected.

Tapped up manually to 35A.

IGP1 = 5.5e-7 Torr.


 Friday, November 06, 2015, 10:08

IGP1 = 5.8e-7 Torr.

Vacuum stable.

Initiating auto-ramp at 0.2A/min and 0.1A/min with final setpoints of 450A and 230A for the TGHT and TBHT respectively.

See photos attached to view how springs were coated and loaded into container.


 Monday, November 09, 2015, 09:07

TGHT reached 450A, 7.2V ~8pm sat, nov 7th.

OMEGA = 1775C

IGP1 = 3.2e-7 Torr.

Tapping up manually to 1900C.


 

    Reply  Monday, November 09, 2015, 12:56, John Wong, , 41077-3, LP-SIS, In progress, Sintering TaC coating on 'temporary endcaps' springs (Slope changed to 1.04) 

Laura Lambert wrote:

 Thursday, November 05, 2015, 16:19

Springs coated with TaC and loaded into container for sintering.

3x Ta heat shield.

EVAP2 currently pumping down.


 Friday, November 06, 2015, 08:39

Opened HS water valves, no leaks detected.

Tapped up manually to 35A.

IGP1 = 5.5e-7 Torr.


 Friday, November 06, 2015, 10:08

IGP1 = 5.8e-7 Torr.

Vacuum stable.

Initiating auto-ramp at 0.2A/min and 0.1A/min with final setpoints of 450A and 230A for the TGHT and TBHT respectively.

See photos attached to view how springs were coated and loaded into container.


 Monday, November 09, 2015, 09:07

TGHT reached 450A, 7.2V ~8pm sat, nov 7th.

OMEGA = 1775C

IGP1 = 3.2e-7 Torr.

Tapping up manually to 1900C.


 

 Monday, November 09, 2015, 12:30

Checked the temp on the inner surface (not at the spring) of the container was around 2050C at 500A. 

The TaC coated spring is reading at 1900C; that's what the OMEGA is reading with the setting for 2-colors and slope at 0.98.

Lower TGHT to 450A/ 7.12V.

By comparing the data from the previous temp curve (OMEGA slope at 0.98) with no material inside the container,  the voltage and current plot is aligned with the curve.

Changed OMEGA setting slope to 1.04.  Current temp is reading at 1917C at 450A.

For 2-Color setting, the emissivity should be negligible.  That makes me believe that different materials has different slope setting for the temp reading.  

One thing to note is that, the sintering temp of TaC is around 1900-2000C.  It was clear that the container was fully sintered with TGHT at 450A.

Will need to gather more data with different material to understand the slope setting better. 

Try: 

SiC at 1700C, slope at 1.04

ZrC at 1900C, slope at 104

Ta at 1900C, slope at 0.98.

Compare the data...


 

    Reply  Monday, November 09, 2015, 14:22, Laura Lambert, , 41077-3, LP-SIS, Done, Sintering TaC coating on 'temporary endcaps' springs (Slope changed to 1.04) Evernote_Camera_Roll_20151110_113123.jpg

John Wong wrote:

Laura Lambert wrote:

 Thursday, November 05, 2015, 16:19

Springs coated with TaC and loaded into container for sintering.

3x Ta heat shield.

EVAP2 currently pumping down.


 Friday, November 06, 2015, 08:39

Opened HS water valves, no leaks detected.

Tapped up manually to 35A.

IGP1 = 5.5e-7 Torr.


 Friday, November 06, 2015, 10:08

IGP1 = 5.8e-7 Torr.

Vacuum stable.

Initiating auto-ramp at 0.2A/min and 0.1A/min with final setpoints of 450A and 230A for the TGHT and TBHT respectively.

See photos attached to view how springs were coated and loaded into container.


 Monday, November 09, 2015, 09:07

TGHT reached 450A, 7.2V ~8pm sat, nov 7th.

OMEGA = 1775C

IGP1 = 3.2e-7 Torr.

Tapping up manually to 1900C.


 

 Monday, November 09, 2015, 12:30

Checked the temp on the inner surface (not at the spring) of the container was around 2050C at 500A. 

The TaC coated spring is reading at 1900C; that's what the OMEGA is reading with the setting for 2-colors and slope at 0.98.

Lower TGHT to 450A/ 7.12V.

By comparing the data from the previous temp curve (OMEGA slope at 0.98) with no material inside the container,  the voltage and current plot is aligned with the curve.

Changed OMEGA setting slope to 1.04.  Current temp is reading at 1917C at 450A.

For 2-Color setting, the emissivity should be negligible.  That makes me believe that different materials has different slope setting for the temp reading.  

One thing to note is that, the sintering temp of TaC is around 1900-2000C.  It was clear that the container was fully sintered with TGHT at 450A.

Will need to gather more data with different material to understand the slope setting better. 

Try: 

SiC at 1700C, slope at 1.04

ZrC at 1900C, slope at 104

Ta at 1900C, slope at 0.98.

Compare the data...


 

 Monday, November 09, 2015, 14:20

IGP1 = 3.3e-7 Torr.

TGHT = 450A, 7.12V

OMEGA = 1915C

Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


 Tuesday, November 10, 2015, 13:23

Vented and opened this morning.

springs look [mostly] sintered.

see photo attached.

 

Entry  Thursday, January 14, 2016, 11:48, Laura Lambert, , , , Maintenance, Backing Pump Replaced 

 Thursday, January 14, 2016, 11:47

Backing pump was making very loud high pitched noises during last couple processes in the evaporator.

Replaced with a new one this morning.


 

Entry  Wednesday, March 30, 2016, 11:32, John Wong, , Target boat, TARGET BOAT, Done, Thermostablization Polycarbosilane Fibers (UBC MTRL Samples) 

Wednesday, March 30, 2016, 11:30

Polycarbosilane fibers were prepared by UBC MTRL. 

Two samples with different fiber sizes were loaded in target boat and wrapped with heat shields.

Samples will be heated up to 1600C.

Chamber is currently being pumped down


 Thursday, March 31, 2016, 16:49

Ramping up TGHT to 300A at 1A/min


 Tuesday, April 05, 2016, 13:02

Samples was heated at 1600C for about 3 hours.  

Then it was cooled down at 2A/min. 

The process is complete. 


 

Entry  Tuesday, May 03, 2016, 14:44, Laura Lambert, , , , , VACUUM PUMP REPLACEMENT 

 Tuesday, May 03, 2016, 14:29

Turned vacuum pump on this morning, sounded awful: loud grinding bad noises.

Called vacuum group, will replace pump tomorrow morning.

Sounds like materials coming out from all the out-gassing during sintering processes has ruined the bearings.


 

Entry  Wednesday, May 04, 2016, 13:45, Laura Lambert, , 40282-3, TARGET BOAT, In progress, Conditioning Nb samples for Tobias Nb_samples_in_boat_(2).jpg

 Wednesday, May 04, 2016, 13:28

Target boat has a layer of niobium foil on the bottom of the boat.

A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos

Larger niobium samples are placed in the slots, holding in place, to avoid warping; smaller niobium sample sitting inside the boat by itself.

Smaller sample closest to OMEGA IR reading [right side]

Boat is wrapped with 1 large layer of Ta foil, wrapped around the boat 3x, careful to avoid touching samples.

Loaded into evap2 yesterday.

Vacuum pump bearings gone - pump replaced this morning by vacuum group.

Pumping down now...


 Friday, May 06, 2016, 13:36

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

IGP1 = 2.4e-7 Torr

Setting auto-ramp rate at 0.2A/min to 250A over the weekend.

Will tap up manually monday to final desired temperature of 1400C.


 Monday, May 09, 2016, 09:38

OMEGA = 1128C

IGP1 = 1.3e-7 Torr

TGHT = 250A, 3.7V

Tapping up manually to 1400C...


 Monday, May 09, 2016, 14:05

Evap2 has reached ~1405C

TGHT = 341A, 5.34V

IGP1 = 1.9e-7 Torr

Will remain at max setpoints for min 4hrs then initiate cool down.


 

    Reply  Monday, May 09, 2016, 18:19, John Wong, , 40282-3, TARGET BOAT, In progress, Conditioning Nb samples for Tobias 

Laura Lambert wrote:

 Wednesday, May 04, 2016, 13:28

Target boat has a layer of niobium foil on the bottom of the boat.

A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos

Larger niobium samples are placed in the slots, holding in place, to avoid warping; smaller niobium sample sitting inside the boat by itself.

Smaller sample closest to OMEGA IR reading [right side]

Boat is wrapped with 1 large layer of Ta foil, wrapped around the boat 3x, careful to avoid touching samples.

Loaded into evap2 yesterday.

Vacuum pump bearings gone - pump replaced this morning by vacuum group.

Pumping down now...


 Friday, May 06, 2016, 13:36

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

IGP1 = 2.4e-7 Torr

Setting auto-ramp rate at 0.2A/min to 250A over the weekend.

Will tap up manually monday to final desired temperature of 1400C.


 Monday, May 09, 2016, 09:38

OMEGA = 1128C

IGP1 = 1.3e-7 Torr

TGHT = 250A, 3.7V

Tapping up manually to 1400C...


 Monday, May 09, 2016, 14:05

Evap2 has reached ~1405C

TGHT = 341A, 5.34V

IGP1 = 1.9e-7 Torr

Will remain at max setpoints for min 4hrs then initiate cool down.


 

 Monday, May 09, 2016, 18:18

TGHT at 341A/5.34V for over 4 hours.  Vac stables at 1.78e-7 Torr.

Cooling down at 2A/min


 

    Reply  Tuesday, May 10, 2016, 11:57, Laura Lambert, , 40282-3, TARGET BOAT, Done, Conditioning Nb samples for Tobias 

John Wong wrote:

Laura Lambert wrote:

 Wednesday, May 04, 2016, 13:28

Target boat has a layer of niobium foil on the bottom of the boat.

A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos

Larger niobium samples are placed in the slots, holding in place, to avoid warping; smaller niobium sample sitting inside the boat by itself.

Smaller sample closest to OMEGA IR reading [right side]

Boat is wrapped with 1 large layer of Ta foil, wrapped around the boat 3x, careful to avoid touching samples.

Loaded into evap2 yesterday.

Vacuum pump bearings gone - pump replaced this morning by vacuum group.

Pumping down now...


 Friday, May 06, 2016, 13:36

HS water valves opened, no leaks detected.

Tapped up manually to 35A.

IGP1 = 2.4e-7 Torr

Setting auto-ramp rate at 0.2A/min to 250A over the weekend.

Will tap up manually monday to final desired temperature of 1400C.


 Monday, May 09, 2016, 09:38

OMEGA = 1128C

IGP1 = 1.3e-7 Torr

TGHT = 250A, 3.7V

Tapping up manually to 1400C...


 Monday, May 09, 2016, 14:05

Evap2 has reached ~1405C

TGHT = 341A, 5.34V

IGP1 = 1.9e-7 Torr

Will remain at max setpoints for min 4hrs then initiate cool down.


 

 Monday, May 09, 2016, 18:18

TGHT at 341A/5.34V for over 4 hours.  Vac stables at 1.78e-7 Torr.

Cooling down at 2A/min


 

 Tuesday, May 10, 2016, 08:45

Vented in air and opened up this morning.

Samples look good!


 

Entry  Friday, August 12, 2016, 11:08, Laura Lambert, , , , Maintenance, NEW PUMP FOR GLOVE BOX 

Wednesday, August 03, 2016, 16:16

Tues July 26th had some problems with the transfer chamber

Transfer chamber was not going below -20in pressure, when usually it will drop all the way to -30in

To by pass and put the uranium target into the glove box, the transfer chamber was flushed 10x - when opened, no change in H2O and O2 in glove box; therefore, 'bypass' worked.

Pump removed and tested by vacuum group - showed no reading on gauge when being tested, how was it even pumping?

New pump installed July 27th.

New pump = bigger/ faster/ quieter 


 

Entry  Thursday, August 18, 2016, 10:37, Anders Mjos, , , , Maintenance, New cooling lines for Heat Shield 

 Dan made a set of new cooling lines for the Source Tray Heat Shield cooling yesterday. No joints on the lines. Use same VCR fitting 3/8 -> 1/4" as for the Heat Shield. The old lines had worn threads on the male VCR nut.

Entry  Tuesday, December 20, 2016, 15:04, Laura Lambert, , , , Maintenance, RETURN and SUPPLY valves CLOSED for xmas break 

Tuesday, December 20, 2016, 15:05

confirmed ~full tank of Ar for glove box --> ~1600psi 

Entry  Monday, February 06, 2017, 11:17, Anders Mjos, , , , Problems resolved, IOC restart after power outagae 

 Dave Morris did a remote restart of the IOC after the outage. Turbo pump started.

Entry  Thursday, February 09, 2017, 11:49, Laura Lambert, , , , Maintenance, New heatshield with flexible water lines 

 Thursday, February 09, 2017, 11:47

A new heatshield with flexible water lines has been put into evap2 last Friday Feb3rd


 

Entry  Monday, May 08, 2017, 10:05, Laura Lambert, , , , Maintenance, Turbo pump control box replaced 

 Monday, May 08, 2017, 10:05

Turbo pump control box died last week.

Replaced with a new one.


 

Entry  Thursday, May 11, 2017, 11:30, Laura Lambert, , , , Maintenance, New Ion Gauge for IGP2 

 Thursday, May 11, 2017, 11:25

IGP2 has been having problems where sometimes it turns off and requires simply unplugging and plugging back in.

Ion gauge has been replaced.

At first the vacuum box appeared red on epics and when attempting to reset everything nothing would work and the backing pump would try and turn on then timeout.

Apparently this new ion gauge draws slightly more than the old one and this blew a fuse in the PLC.

Old fuse was 2A, so a new 3A fuse has been replaced - seems to be working fine now. 


 

Entry  Tuesday, July 18, 2017, 15:30, Laura Lambert, , , , Maintenance, Paddle wheel replacement for all evap2 water supplies 

 Tuesday, July 18, 2017, 15:26

Problems occured with TGHT water supply paddle wheel stopped and therefore tripped off evap2 last week.

All paddle wheels were replaced today for evap2 [other than the chiller].

A build up of dirt was found on all wheels replaced.

Evap2 good to go.

Will test flow meters before heating up to higher setpoints to confirm everything is working.


 