Wednesday, May 06, 2015, 13:59, Laura Lambert, , 40282-4, TARGET BOAT, Done, Sintering two different ZrC samples
|
Wednesday, May 06, 2015, 13:54
Two different samples of ZrC are wrapped in graphite sheet and loaded into the target boat.
Sample #1 = ZrC |
Friday, May 08, 2015, 15:56, Laura Lambert, , 40282-4, TARGET BOAT, Done, Sintering four different ZrC samples
|
John Wong wrote:
|
Wednesday, May 13, 2015, 16:01, Laura Lambert, , 40282-4, TARGET BOAT, Done, Sintering three different ZrC samples
|
Wednesday, May 13, 2015, 15:21
Three different samples of ZrC are loaded into a target boat.
Sample A: ZrC + NO graphite |
Thursday, June 18, 2015, 11:39, Rick Maharaj, , , , , Installation of Extraction Electrode Insulator - New Material
|
Tuesday June 16, 2015
An Extraction Insulator ITD0381 made from a different grade of AiN was installed in Evaporator 2 for testing purposes. The sub assembly included
the SIS Restraint Housing ITD0389, New Extraction Insulator ITD0381, Repeller Electrode ITD0377, Extraction Electrode ITD0374 with fingerstock mounted. |
Thursday, July 30, 2015, 17:07, John Wong, , , , Maintenance, Connect NALCW to EVAP1
|
Thursday, July 30, 2015, 17:02
EVAP1 cooling system is now on the NALCW. The city water has been removed from the system.
Tested all the cooling system interlocks by shutting off each individual valve, and the main supply valve to the lab - All Passed! |
Friday, July 31, 2015, 15:10, John Wong, , , , Maintenance, Installed leftside port
|
Friday, July 31, 2015, 15:09
The left side port was installed on the evaporator #2. Leak check was performed and no leak was detected.
|
Monday, August 24, 2015, 12:58, John Wong, , , , Maintenance, Replacing turbo pump, IEVAP2TP1
|
Monday, August 24, 2015, 12:54
The turbo pump was found to be faulty. The pump couldn't get on full speed and eventually timed out. Vacuum group inspected the pump
and it is time for a service. |
Thursday, November 05, 2015, 16:20, Laura Lambert, , 41077-3, LP-SIS, In progress, Sintering TaC coating on 'temporary endcaps' springs   
|
Thursday, November 05, 2015, 16:19
Springs coated with TaC and loaded into container for sintering.
3x Ta heat shield. |
Monday, November 09, 2015, 12:56, John Wong, , 41077-3, LP-SIS, In progress, Sintering TaC coating on 'temporary endcaps' springs (Slope changed to 1.04)
|
Laura Lambert wrote:
Thursday, November 05, 2015, 16:19 |
Monday, November 09, 2015, 14:22, Laura Lambert, , 41077-3, LP-SIS, Done, Sintering TaC coating on 'temporary endcaps' springs (Slope changed to 1.04)
|
John Wong wrote:
|
Thursday, January 14, 2016, 11:48, Laura Lambert, , , , Maintenance, Backing Pump Replaced
|
Thursday, January 14, 2016, 11:47
Backing pump was making very loud high pitched noises during last couple processes in the evaporator.
Replaced with a new one this morning. |
Wednesday, March 30, 2016, 11:32, John Wong, , Target boat, TARGET BOAT, Done, Thermostablization Polycarbosilane Fibers (UBC MTRL Samples)
|
Wednesday, March 30, 2016, 11:30
Polycarbosilane fibers were prepared by UBC MTRL.
Two samples with different fiber sizes were loaded in target boat and wrapped with heat shields. |
Tuesday, May 03, 2016, 14:44, Laura Lambert, , , , , VACUUM PUMP REPLACEMENT
|
Tuesday, May 03, 2016, 14:29
Turned vacuum pump on this morning, sounded awful: loud grinding bad noises.
Called vacuum group, will replace pump tomorrow morning. |
Wednesday, May 04, 2016, 13:45, Laura Lambert, , 40282-3, TARGET BOAT, In progress, Conditioning Nb samples for Tobias
|
Wednesday, May 04, 2016, 13:28
Target boat has a layer of niobium foil on the bottom of the boat.
A niobium foil has been made with slots to hold samples [similar to when sintering endcaps] *See attached photos |
Monday, May 09, 2016, 18:19, John Wong, , 40282-3, TARGET BOAT, In progress, Conditioning Nb samples for Tobias
|
Laura Lambert wrote:
Wednesday, May 04, 2016, 13:28 |
Tuesday, May 10, 2016, 11:57, Laura Lambert, , 40282-3, TARGET BOAT, Done, Conditioning Nb samples for Tobias
|
John Wong wrote:
|
Friday, August 12, 2016, 11:08, Laura Lambert, , , , Maintenance, NEW PUMP FOR GLOVE BOX
|
Wednesday, August 03, 2016, 16:16
Tues July 26th had some problems with the transfer chamber
Transfer chamber was not going below -20in pressure, when usually it will drop all the way to -30in |
Thursday, August 18, 2016, 10:37, Anders Mjos, , , , Maintenance, New cooling lines for Heat Shield
|
Dan made a set of new cooling lines for the Source Tray Heat Shield cooling yesterday. No joints on the lines. Use same VCR fitting 3/8 -> 1/4"
as for the Heat Shield. The old lines had worn threads on the male VCR nut. |
Tuesday, December 20, 2016, 15:04, Laura Lambert, , , , Maintenance, RETURN and SUPPLY valves CLOSED for xmas break
|
Tuesday, December 20, 2016, 15:05
confirmed ~full tank of Ar for glove box --> ~1600psi |
Monday, February 06, 2017, 11:17, Anders Mjos, , , , Problems resolved, IOC restart after power outagae
|
Dave Morris did a remote restart of the IOC after the outage. Turbo pump started. |
|