  Evaporator_2, Page 18 of 34  Not logged in ELOG logo
  ID Date Author Target Material Target Oven W.O# Sourcedown Status Subject
  312   Monday, August 08, 2016, 15:22 Laura LambertSiC40860-3LP-IG-LISProblemsConditioning SiC#34

 Monday, August 08, 2016, 15:19

Previously sintered over weekend [see elog i.d 311]

Target container contains 471 discs of SiC [6 x 5 packs + 441 single discs]

Target packed length = 16cm. 

Mass of 533 discs SiC(green)  = 52.7172g

Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.

Conditioning temp = 1800C.

TGHT max = 450A.  TBHT max = 230A. 

Chamber is currently being pumped down. 


 Monday, August 08, 2016, 16:38

Target was not removed from evap2 after sintering, vented and cleaned windows only.

IGP1 = 5.5e-6 Torr

Stepped up manually to 80A, vacuum stable.

IGP1 = 3.2e-6 Torr

Initiating auto-ramp at 0.2A/min for the TGHT and 0.1A/min for the TBHT.


 Thursday, August 11, 2016, 14:14

Tues the TGHT reached ~280A via auto-ramp

Evap2 was then tapped up manually to 480A/ ~1800C

Temperature readings on OMEGA have fluctuated up and down during conditioning process which was also observed for SiC#33

Also consistent with SiC#33, a lower current was required to reach 1800C during the conditioning process compared to the sintering process.

See attached link for data.


 Tuesday, August 16, 2016, 16:25

TGHT remained at 480A, 9.2V for ~7 days.

IGP1 = 6.5e-6 Torr

OMEGA = 1470C [with window coating, so temperature reading compromised]

Initiating auto cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


Wednesday, August 17, 2016, 13:40

Vented in air and opened this morning.

Target broke  

Target clearly heated to high.

See attached snapshot of striptool from conditioning process.

Will update later with photos of broken container


 

Attachment 1: conditioning_temperature_graph.xlsx
Attachment 2: striptool_conditioning_target_BROKEN.JPG
striptool_conditioning_target_BROKEN.JPG
  314   Wednesday, August 17, 2016, 17:31 Laura LambertEmpty39814-V2-1LP-IG-LISIn progresssintering TaC coating on SiC#34 container...round2

 Wednesday, August 17, 2016, 17:30

Container coated with TaC using 'flushing technique', cleaned ionizer tube with acetone, so no coating inside ionizer tube

Wrapped with 3 x Ta heat shields, incl center block

Currently pumping down in evap2


Thursday, August 18, 2016, 10:14 

HS water valves opened...leak detected  see attachment for photo from archives

Vented and opened up.

Anders performed leak check, nothing found.

Replaced all seals with blue seals.

Pumping down now


 Thursday, August 18, 2016, 16:12

HS water valves opened...leak detected again  see attachment for photo of striptool

Vented and opened up.

working with Anders on finding leak...


 Monday, August 22, 2016, 10:38

leaks FIXED!

HS water valves opened, NO leaks detected!

Tapped up manually to 70A

Vacuum stable, IGP1 = 2.5e-6 Torr

Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 350A

Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A

Once max setpoints achieved, will tap up manually to final desired temperature of 1900C


 Monday, August 22, 2016, 14:58

TGHT = 115A, 1.3V

TBHT = 89A, 0.97V

IGP1 = 4.1e-7 Torr.

Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.


 Monday, August 22, 2016, 16:01

IGP1 = 1.25e-6 torr

TGHT = 174A, 2.2V

TBHT = 118A, 1.4V

Lowering ramping rate to 0.2A/min and 0.1A/min for the TGHT and TBHT respectively for overnight ramping.


 

Attachment 1: leak.JPG
leak.JPG
Attachment 2: water_leak.JPEG
water_leak.JPEG
  316   Tuesday, August 23, 2016, 12:15 John WongEmpty39814-V2-1LP-IG-LISDonesintering TaC coating on SiC#34 container...round2

Laura Lambert wrote:

 Wednesday, August 17, 2016, 17:30

Container coated with TaC using 'flushing technique', cleaned ionizer tube with acetone, so no coating inside ionizer tube

Wrapped with 3 x Ta heat shields, incl center block

Currently pumping down in evap2


Thursday, August 18, 2016, 10:14 

HS water valves opened...leak detected  see attachment for photo from archives

Vented and opened up.

Anders performed leak check, nothing found.

Replaced all seals with blue seals.

Pumping down now


 Thursday, August 18, 2016, 16:12

HS water valves opened...leak detected again  see attachment for photo of striptool

Vented and opened up.

working with Anders on finding leak...


 Monday, August 22, 2016, 10:38

leaks FIXED!

HS water valves opened, NO leaks detected!

Tapped up manually to 70A

Vacuum stable, IGP1 = 2.5e-6 Torr

Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 350A

Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A

Once max setpoints achieved, will tap up manually to final desired temperature of 1900C


 Monday, August 22, 2016, 14:58

TGHT = 115A, 1.3V

TBHT = 89A, 0.97V

IGP1 = 4.1e-7 Torr.

Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.


 Monday, August 22, 2016, 16:01

IGP1 = 1.25e-6 torr

TGHT = 174A, 2.2V

TBHT = 118A, 1.4V

Lowering ramping rate to 0.2A/min and 0.1A/min for the TGHT and TBHT respectively for overnight ramping.


 

 Tuesday, August 23, 2016, 12:14

Initiate TGHT autoramping to 400A at 2A/min.  Vac 3.5e-7 Torr. 


 Tuesday, August 23, 2016, 14:48

TGHt tapped up to 420A/7.01V.  Local temp read at ~1900C.  Will sinter at this temp for a few hours before cooling down.


 Tuesday, August 23, 2016, 17:20

TGHT at been at 420A/7.01V for over 4 hours.  Vac at 4.8e-7 Torr.

Cooling TGHT and TBHT at 1A/min.


 Wednesday, August 24, 2016, 10:35

TGHT/TBHT at 0A.

Venting chamber.

Container looks good.


 

  317   Wednesday, August 24, 2016, 17:07 John WongSiC39814-V2-1LP-IG-LISDoneSintering process for SiC#34 (2nd round)

Wednesday, August 24, 2016, 17:05

Target container was previously coated with TaC and sintered up to 1900C at 420A/7.01V

Container is loaded with beta-SiC 432 discs at 16cm in length. 

Container is wrapped with Ta-heat shield; no end-caps are used at this time.

Chamber is being pumped down.


 Thursday, August 25, 2016, 12:04

Chamber has been pumped down overnight.  Pressure at 5.9e-7 Torr.

HS water valve opened; no leaks were detected.

Sintering temperature 1800C. TGHT will be set accordingly to get the desired temperature.  TBHT max at 230A.


Thursday, August 25, 2016, 12:12

Tapped up TGHT/TBHT to 40A.  Vac at 7e-6 and slowly going up  but still below limit.


 Monday, August 29, 2016, 11:04

TGHT and TBHT reached to 250A (3.65V)//230A(3.02V), respectively, and kept stable over the weekend. 

Temp measured at 1372C with slope set at 1.04 (1230C at slope 0.98). 

No visible coating on windows. 

Setting up TGHT to reach 1800C; monitoring locally


 Monday, August 29, 2016, 14:35

Stepped up TGHT to 390A/6.54V; light coating was observed on the windows.  The temperature should be around 1800C which should be in line with the power (current) deposited in the container during the TaC coat sintering process (1900A at 420A); however, with the light coating the reading may be off.  

Mikron was used to measured inside of the tube (away from the discs); temperature was measured at ~1800C, (see attachment)  [adjusted slope at 1.00 to compensate the SiC disc and Ta]  

Omega was used to measured the temperature of the discs.  It is difficult to know what's the temperature inside the tube, so this measurement  is only taken as a guideline.  Slope changed from 1.04 to 1.15 to match Mikron's reading.  

After heated at  390A for 30 mins, the windows are now coated.  Temp reading is no longer reliable.  The temperature could be above 1800C.  Keeping a close monitor!!!

No blockage inside the tube was observed.  

Will remain heating at 390A/6.44V for overnight before proceeding with the re-conditioning. 


 Tuesday, August 30, 2016, 10:41

Target was heated at 390A  for over 10 hours and then cool down at 1A/min (see attachment#2).  Windows were fully coated and Omega couldn't register any reading. 

Chamber will be vented and target will be inspected before proceeding with the re-conditioning step.


Tuesday, August 30, 2016, 12:13  

Target was inspected; no visible damage was observed (see attachment)

Material coated on the windows and the cu heat shields;  all parts were wiped off with acetone. 

No visible material build up inside the container. 

Chamber is now being pumped down for re-conditiing.  


 Tuesday, August 30, 2016, 13:05

HS water valves open; no leaks detected.  

Vac at 3.6 e-6 Torr.  

Ready to set up TGHT/TBHT


 Tuesday, August 30, 2016, 16:41

TGHT/TBHT stepped up to 340A (5.40V) /230A (3.1V), respectively. 

Temperature was measured at 1835C at TGHT of 340A.  Omega, Mikron and analogue pyrometer were all reading ~1800C inside the tube (not on the SiC surface).  For that reason, I decided to stop the current at 340A, instead of 390A.  

TGHT voltage is running stable.  

No visible coating or blockage inside the tube was observed.  


Wednesday, August 31, 2016, 11:53

A thin layer of coating is observed on both the side windows (see attachment 5).  The temp reading is no longer reliable.

TGHT remains at 340A/5.45V.  P/S voltage is performing steadily.  

No clogging inside the tube is observed. 

Setting up another Omega reader to measure temperature from the front window since this window is clear and won't get coated (see attachment #6).

Temperature measurement from the front window is ~1140C; this corresponds to the measurement from the analogue pyrometer with the correction of e=~0.2 for tantalum at 1100C.

Note:  The temperature measurements should be taken as relative.  Since the reading from the side windows isn't reliable any longer, the centre window will give some information how stable the temperature is holding during the reconditioning process.  Continue to monitor.


 Wednesday, August 31, 2016, 16:24

About two hours ago, I increased TGHT to 350A and stayed there for a few mins (see attachment 7).  No change in temp was observed - that's mainly due to the coating on the windows.  As for the temp measurement from the center window, a more power current input would require to see the change as heat is slowly propagating through the layers of Ta heatshields.

Local inspection on the target: no clogging inside the tube. Voltage/Current is stable at 340A/5.45V.  Vac at 1.43e-7 Torr.


 Wednesday, August 31, 2016, 23:00

Strange observation:  Temperature readers on both omega have gone up. (see attachment 8).

I'm not sure if the temperature is reiiable.  I actually saw the increase in temperature ~1850C  last night around the same time; no change in TGHT current/voltage.  By the next morning, it went back down to 1400C with significant coating on the windows.


 Wednesday, August 31, 2016, 23:28

I had ISAC Op (Justin) to help me go into the Hotlab and take a look at the reading on Mikron.  Indeed, it is reading about 2000C which is close to the Omega reading.  He also looked into the tube through Mikron scope and found no clogging inside the tube.

To be safe, I am going to lower the TGHT heater down to reach ~1800C.


Wednesday, August 31, 2016, 23:41

Lower TGHT to 305A/4.81V; OMEGA reading at 1830C.  Vac at 1.27e-7 Torr.  Will remain at this current over night. 


 Thursday, September 01, 2016, 12:16

Checked on the target.  

Temperature readings, right windows (omega)= 1726C, centre = 1100C (omega), left (Mikron) = 1720C.  

No blockage inside the tube.  

TGHT stabilizes at 305A/4.79V.  Vac at 1.09e-7 Torr.  


 Thursday, September 01, 2016, 16:32

 About an hour ago, the temp dropped to 1660C with no change in TGHT current/voltage (see attachment 9).

Vac is a 1.06e-7 Torr. 

After consulting with Friedhelm, we decided to cool the target down and inspect it tomorrow.

Ramping TGHT/TBHT at 2A/min.


 Wednesday, September 07, 2016, 15:13

The target was removed from the Evap and inspected. 

Some spots on both ends and ionizer tube were crystalized.  (see attachment 10). 

No blockage inside the tube was observed. 

End caps were inserted.

The target was assembled and tested - All seems fine. 


 

Attachment 1: Screen_Shot_2016-08-29_at_2.35.23_PM.png
Screen_Shot_2016-08-29_at_2.35.23_PM.png
Attachment 2: SiC34_striptool.PNG
SiC34_striptool.PNG
Attachment 3: Screen_Shot_2016-08-30_at_12.13.12_PM.png
Screen_Shot_2016-08-30_at_12.13.12_PM.png
Attachment 4: Screen_Shot_2016-08-30_at_4.41.00_PM.png
Screen_Shot_2016-08-30_at_4.41.00_PM.png
Attachment 5: Screen_Shot_2016-08-31_at_11.51.58_AM.png
Screen_Shot_2016-08-31_at_11.51.58_AM.png
Attachment 6: Screen_Shot_2016-08-31_at_11.52.49_AM.png
Screen_Shot_2016-08-31_at_11.52.49_AM.png
Attachment 7: Capture.PNG
Capture.PNG
Attachment 8: Aug31_11pm.PNG
Aug31_11pm.PNG
Attachment 9: before_cooling.PNG
before_cooling.PNG
Attachment 10: Screen_Shot_2016-09-02_at_12.04.35_PM.png
Screen_Shot_2016-09-02_at_12.04.35_PM.png
  318   Tuesday, August 30, 2016, 15:25 John WongSiC40860-3LP-IG-LISProblemsConditioning SiC#34. Note about the p/s voltage

Laura Lambert wrote:

 Monday, August 08, 2016, 15:19

Previously sintered over weekend [see elog i.d 311]

Target container contains 471 discs of SiC [6 x 5 packs + 441 single discs]

Target packed length = 16cm. 

Mass of 533 discs SiC(green)  = 52.7172g

Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.

Conditioning temp = 1800C.

TGHT max = 450A.  TBHT max = 230A. 

Chamber is currently being pumped down. 


 Monday, August 08, 2016, 16:38

Target was not removed from evap2 after sintering, vented and cleaned windows only.

IGP1 = 5.5e-6 Torr

Stepped up manually to 80A, vacuum stable.

IGP1 = 3.2e-6 Torr

Initiating auto-ramp at 0.2A/min for the TGHT and 0.1A/min for the TBHT.


 Thursday, August 11, 2016, 14:14

Tues the TGHT reached ~280A via auto-ramp

Evap2 was then tapped up manually to 480A/ ~1800C

Temperature readings on OMEGA have fluctuated up and down during conditioning process which was also observed for SiC#33

Also consistent with SiC#33, a lower current was required to reach 1800C during the conditioning process compared to the sintering process.

See attached link for data.


 Tuesday, August 16, 2016, 16:25

TGHT remained at 480A, 9.2V for ~7 days.

IGP1 = 6.5e-6 Torr

OMEGA = 1470C [with window coating, so temperature reading compromised]

Initiating auto cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


Wednesday, August 17, 2016, 13:40

Vented in air and opened this morning.

Target broke  

Target clearly heated to high.

See attached snapshot of striptool from conditioning process.

Will update later with photos of broken container


 

 Tuesday, August 30, 2016, 15:17

A better look at the p/s voltage over the course of the constant heating at 480A.  (see attachment).

The striptool shows the voltage was not giving a stable output.  There were multiple occasions that the voltage dropped and then recovered; the obvious was on Aug 16.  This indicates that  the target was breaking up.

Finally on Aug 17, the voltage dropped and never recovered again - that indicates the target was broken.

Attachment 1: Capture.PNG
Capture.PNG
  350   Tuesday, February 21, 2017, 15:21 Laura LambertEmpty42218-1LP-IG-LISDonesintering TaC coating on UCx#20 container

Tuesday, February 21, 2017, 15:19

Container coated with TaC using 'flushing technique' and let dry overnight.

Cleaned ionizer tube with acetone, no coating inside ionizer tube

Wrapped with 3 x Ta heat shields, incl center block

Currently pumping down in evap2

OMEGA slope = 0.98

Good vac at 3.0e-5, bad vac at 4.0e-5 Torr.


 Wednesday, February 22, 2017, 09:41

HS water valves opened, no leaks detected.

Tapped up manually to 35A

Waited ~45min

Vacuum stable.

IGP1 = 1.2e-6 Torr

Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 350A

Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A

Once max setpoints achieved, will tap up manually to final desired temperature of 1900C


Friday, February 24, 2017 by Anders

Continue manually to 1900 C

Friday, February 24, 2017, 16:24: TGHT at 400 A 6.35V IG1 = 4.5e-7 Torr 1660 C

Friday, February 24, 2017, 16:57: TGHT at 410 A 6.6 V IG1 = 5.0e-7 Torr 1700 C


Sunday, February 26, 2017 by Anders

Sunday, February 26, 2017, 14:13: TGHT at 425 A 6.9 V IG1 = 2.5e-7 Torr 

Lab closed for weekend. No access to temp reading.


 Monday, February 27, 2017, 16:12

Tapped up manually to 1900C this morning.

TGHT = 490A, 8.14V

TBHT = 230A, 2.98V

MIKRON = 1911C

OMEGA = 1904C

evap2 has remained at max setpoints for ~6hrs

Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


 Tuesday, February 28, 2017, 11:57

Container finished sintering.

Vented in air and opened up this morning.

Container looks good 


 

Attachment 1: IMG_1562.JPG
IMG_1562.JPG
Attachment 2: IMG_1564.JPG
IMG_1564.JPG
  418   Monday, September 10, 2018, 15:09 Marla CervantesEmpty42218-3LP-IG-LISDoneTaC coating/sintering for UC target container

 Monday, September 10, 2018, 15:09

Container is coated with TaC and wrapped with Ta heat-shield ( 3 layers)

Desired temp = 1900 C (expected TGHT ~445A/7.5V), TBHT will be set fixed at 230A (max).

Good vac at 3.00-5 Torr

Bad vac at 5.0e-5 Torr.

Chamber is currently being pumped down


 Tuesday, September 11, 2018, 09:27

Pressure at IGP1 8.61e-7 Torr. 

Auto ramping TGHT at 1A/min to reach 400A, and TBHT at 1A/min to reach 230A.


 Tuesday, September 11, 2018, 12:05

Pressure increased to 6.9e-e5 Torr and auto-ramp reduced the current:

TGHT from 94.6 A to 84.86 A

TBHT from 87.8 A to 78.87 A

(see figure EVAP2-_01)

EPICS automatically started ramping up TBHT and TGHT current when the pressure was between the good limit.


 Tuesday, September 11, 2018, 14:29

TBHT current reached ~230 A and EPICS stopped inputting current automatically. 

TBHT current reading on:

EPICS 232.8 A

Power supply: 235 A


 Tuesday, September 11, 2018, 16:53

TGHT reached 400 A, EPICS stopped auto-ramping automatically. (Fig. Heater-ramp and Plot_400A-230A)

Temperature read by OMEGA 1837 C (Fig. Tempeature-at-400A)


 Tuesday, September 11, 2018, 17:40

TGHT current was increased manually to 419 A (power supply current 422 A, EPICS plot 421.6 A) in steps of ~5A/2min

The temperature after ~30 min of being at 419 A is 1898 C.

The container will stay 5 hours at 1898 C 


Wednesday, September 12, 2018, 09:05 

EVAP2 remained at max setpoints for 5hrs

Auto-cool was set to 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.

The automatic ramp decreased the TBHT current to 0A, but not so for TGHT, 

TGHT only reduced to 22 A, the TGHT was manually tapped to 0A


 Wednesday, September 12, 2018, 18:30

Process completed (fig. TaC-coating). 

Chamber was vented.

Attachment 1: EVAP2-_01.JPG
EVAP2-_01.JPG
Attachment 2: Heater-ramp.jpg
Heater-ramp.jpg
Attachment 3: Plot_400A-230A.jpg
Plot_400A-230A.jpg
Attachment 4: Tempeature-at-400A.jpg
Tempeature-at-400A.jpg
Attachment 5: TaC-coating.png
TaC-coating.png
  556   Tuesday, September 14, 2021, 09:33 Darwin Ortiz Rosales 42218-5LP-IG-LISDoneTaC coating/sintering

Tuesday, September 14, 2021, 09:32

Ta IGLIS tube was coated with TaC and wrapped with Ta heat-shields (3 layers)

Desired temperature = 1900 C (expected TGHT ~430 A), TBHT will be set fixed at 230A (max).

Evap 2 was pumped down over previous night

Good vacuum = 3.00 e-5 Torr

Bad vacuum = 5.00 e-4 Torr

IGP1= 1.12 e-06 Torr

Initiate manual ramp to 50 A @ 1A/min


Tuesday, September 14, 2021, 14:44

 IGP1= 1.25e-06 Torr

TGHT = 50A, 0.58V  TBHT = 49A, 0.56V

Start autoramp to 400 A TGHT and 230A TBHT @ 1A/min


Heated to 1880 C and held for 4 hours.  Log info written down but could not be found in system later.

Coating proceeded without issues.

  573   Thursday, April 21, 2022, 09:45 Darwin Ortiz RosalesTaC42218-2LP-IG-LISDoneTaC coating

Thursday, April 21, 2022, 09:43

TaC coated Target container was placed in Evaporator 2 yesterday and left pressuring down.

Ta Heatshields: 3

Target temperature on OMEGA = 1800-1850 C

OMEGA slope: 0.990

Target time at temperature = 4 hours

Target final TBHT current: 230A

Approximate final TGHT current: 420A (will adjust manually)

Heating autoramp started @ ~2A/min on both TGHT and TBHT

initial IGP1 = 9.3e-7 Torr

 


Thursday, April 21, 2022, 10:38

Pressure trending down after peak.  Start autoramp at 1A/min to 50A on both TGHT and TBHT.


Thursday, April 21, 2022, 10:56

Pressure continues to decrease.  Will ramp up faster @4A/min to 90A for both TGHT and TBHT.


Thursday, April 21, 2022, 11:07

Second peak has  begun to form .  Will keep at 90A awaiting stabilization


Thursday, April 21, 2022, 11:35

pressure stable.  Continue to autoramp at 1A/min and if pressure stable increase ramp to 4A/min


Thursday, April 21, 2022, 11:49

small peak observed and stabilizing.  Autoramp @ 6A/min to 400A on TGHT and to 230A on TBHT


Thursday, April 21, 2022, 12:35

 

Regression plot .  1800C should be reached ~1800C. 


Thursday, April 21, 2022, 12:44

Target current reached. 

OMEGA = 1762 C

Will manually bump current to 415 A

OMEGA = 1802 @ 415 A @ 12:51 pm


Thursday, April 21, 2022, 16:50

 OMEGA=1823 C

IGP1= 2.9e-06 Torr

TGHT= 417 A, 7.2 V

TBHT= 232A, 3.0V

Rampdown will start at -2A/min for both TGHT and -1A/min TBHT

 

  638   Wednesday, June 21, 2023, 10:37 Aaron SchmidtNb45447-7LP-IG-LISIn progressConditioning Nb#10

Nb#10 LP-IG-LIS target description:

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm (0.001")

Target density =  7.36 g/cm3

Target length = 3.5 cm

Total Mass = 25.7576 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven=  438 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack

Dimpling direction on foils/ Packs.                                                               --> Center <--

End caps installed (Not expanded). No Ta foil heat shield added


Wednesday, June 21, 2023, 10:37: Roughing.

Wednesday, June 21, 2023, 13:39: TP1 on. 

Wednesday, June 21, 2023, 13:55: TGHT / TBHT PS on. Vacuum @ 3.35e-05T


Thursday, June 22, 2023, 13:16: TGHT / TBHT Manually set to 5 / 5 A. Vacuum @ 8.17e-07T.

Final desired temperature = 1900C.

Thursday, June 22, 2023, 13:49: OMEGA slope = 0.98.


Friday, June 23, 2023, 06:24: Auto-ramping TGHT / TBHT to 580 / 230 @ 2 A per min. 

Friday, June 23, 2023, 12:11: TGHT / TBHT @ 580 / 230 A (568 / 233 A). Auto-ramping TGHT to 610 A @ 2 A per min (600 A w/ offset). Temperature @ 1697 C. Vacuum @ 3.38e-06T.

Friday, June 23, 2023, 12:32: TGHT / TBHT @ 610 / 230 A (600 / 233 A). Auto-ramping TGHT to 630 A @ 2 A per min (620 A w/ offset). Temperature @ 1748 C. Vacuum @ 4.61e-06T.

Friday, June 23, 2023, 12:44: TGHT / TBHT @ 630 / 230 A (617 / 233 A). Auto-ramping TGHT to 650 A @ 2 A per min (640 A w/ offset). Temperature @ 1790 C. Vacuum @ 5.74e-06T.

Friday, June 23, 2023, 13:07: TGHT / TBHT @ 650 / 230 A (638 / 233 A). Auto-ramping TGHT to 670 A @ 2 A per min (660 A w/ offset). Temperature @ 1825 C. Vacuum @ 5.90e-06T.

Friday, June 23, 2023, 13:22: TGHT / TBHT @ 670 / 230 A (658 / 233 A). Auto-ramping TGHT to 680 A @ 2 A per min (668 A w/ offset). Temperature @ 1858 C. Vacuum @ 6.75e-06T. 

Friday, June 23, 2023, 13:29: TGHT / TBHT @ 680 / 230 A (667 / 233 A). Auto-ramping TGHT to 690 A @ 2 A per min (677 A w/ offset). Temperature @ 1877 C. Vacuum @ 6.99e-06T. 

Friday, June 23, 2023, 13:37: Manually tap up to temperature. 

Friday, June 23, 2023, 13:38: Vacuum @ 7.54e-06T. TGHT /  TBHT @ 694 / 230 A (680.5 / 233 A direct w/ offset). Temperature @ 1901-1902 C. Desired Temperature Reached.

 

Friday, June 23, 2023, 13:42: Auto-cooling @ 2 A per min. 

  641   Thursday, August 24, 2023, 14:18 Aaron SchmidtNb45447-9LP-IG-LISIn progressConditioning Nb#11

 Nb#11 LP-IG-LIS target description:

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm (0.001")

Target density =  7.13 g/cm3

Target length = 3.53 cm

Total Mass = 25.165 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven=  434 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack

Dimpling direction on foils/ Packs.                                                               --> Center <--

End caps installed (Not expanded). No Ta foil heat shield added

Final desired temperature = 1900C.

Replacement for Nb#10


Thursday, August 24, 2023, 14:16: Roughing.

OMEGA slope = 0.98.

Thursday, August 24, 2023, 14:31: Turbo pump started. 

Thursday, August 24, 2023, 14:41: TGHT / TBHT PS on. Manually test @ 5 / 5 A. ok. Tap back to 0 A. 

Thursday, August 24, 2023, 18:26: Vacuum @ 4.35e-06T. Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per minute. 

Thursday, August 24, 2023, 22:00: TGHT / TBHT @ 414 / 230 A (406 / 233 A - Offset). Auto-ramping TGHT to 580 A @ 2 A per min continued. Temperature @ 1353 C. Vacuum @ 4.03e-06T. 

Thursday, August 24, 2023, 23:29: TGHT / TBHT @ 580 / 230 A (569 / 233 A). Auto-ramping TGHT to 610 A @ 2 A per min (approx 600 A w/ offset). Temperature @ 1708 C. Vacuum @ 6.61e-06T. 

Thursday, August 24, 2023, 23:49: TGHT / TBHT @ 610 / 230 A (598 / 233 A). Auto-ramping TGHT to 630 A @ 2 A per min (620 A w/ offset). Temperature @ 1765 C. Vacuum @ 7.22e-06T. 


Friday, August 25, 2023, 00:04: TGHT / TBHT @ 630 / 230 A (618 / 233 A). Auto-ramping TGHT to 650 A @ 2 A per min (640 A w/ offset). Temperature @ 1808 C. Vacuum @ 7.54e-06T. 

Friday, August 25, 2023, 00:16: TGHT / TBHT @ 650 / 230 A (638 / 233 A). Auto-ramping TGHT to 670 A @ 2 A per min (660 A w/ offset). Temperature @ 1845 C. Vacuum @ 7.72e-06T. 

Friday, August 25, 2023, 00:27: TGHT / TBHT @ 670 / 230 A (657 / 233 A). Auto-ramping TGHT to 680 A @ 2 A per min (668 A w/ offset). Temperature @ 1880 C. Vacuum @ 8.46e-06T. 

Manually tap up to temperature.

Friday, August 25, 2023, 00:34: TGHT / TBHT @ 682 / 230 A (669 / 233 A). Temperature @ 1900-1901 C. Vacuum @ 8.59e-06T. Desired Temperature Reached.

Friday, August 25, 2023, 00:37: Auto-cooling @ 2 A per min. 

Friday, August 25, 2023, 06:15: 

 

Friday, August 25, 2023, 07:40: PS & TP off.

 

  674   Friday, August 30, 2024, 11:33 Darwin Ortiz RosalesTa45447-8LP-IG-LISDoneTaC coating sintering

Friday, August 30, 2024, 11:31

The coated container was wrapped in 4 Ta foil heatshields.

Vacuum IGP1 initial =3.1 e-07 Torr

Target temperature on OMEGA= 1850-1900 C

OMEGA slope:= 0.990

Target time at max temperature = 4 hours

Final Current TBHT= 230 A

Final TGHT current= ~400A (adjustable)

Heating autoramp starged at 1A/min on  TGHT  100A and TBHT

Then at 1A/min  to =400 A TGHT and 230A TBHT

Good vacuum = 5.0 e-04 Torr

Bad vacuum = 5.0E-02 Torr

note: Left TBHT hole is off from center by a good margin

 



Sunday, September 01, 2024, 07:32

Starting initial ramp at 1A/min to 50A



Sunday, September 01, 2024, 15:20

have ramped ;up at 1A/min on both TGHT and TBHT but had two issues.

1) Set current and readback current have discrepancies but the TBHT discrepancy is significant (TBHT Set at 188 while RD is 231.9 A @ 1.9V)

   TGHT also has odd behavior with set point 405 giving 392A RD and 0.067V.  Will hold until 430pm before starting ramp down


Sunday, September 01, 2024, 16:30

Started rampdown at -2A/min TGHT and -1A/min TBHT

Note: OMEGA not able to give any reasonable readings


Tuesday, September 03, 2024, 13:51

After troubleshooting EVAP2 it was found that a copper line was touching the metal encasement grid most likely resulting in a short.  A short was seeing and it disappeared after moving the copper line away from the grid.  

Upon restarting on epics the PS went to maximum current and it was shut off after 30seconds to a minute.  The system was checked again by Arthur and TGHT was manually increased to 5A and then set to Zero again.  Arthur thinks that the PS probably requires this step after switching from local controls to remote.  Will start the sintering again as the container is coated but not sintered.


Tuesday, September 03, 2024, 14:03

ramping at 1A/min on both TGHT and TBHT to 90A. 


Tuesday, September 03, 2024, 22:25  

Started rampdown at -2A/min TGHT and -1A/min TBHT.  HIgh temperature from OMEGA was 1825 C at 430A readback on TGHT. 

  36   Thursday, July 19, 2012, 17:05 John WongEmpty37918-3LP-FEBIADDoneCoating target oven /w TaC & sintering for UCx#5

Thursday, July 19, 2012, 16:58

The target container was coated with TaC. 

It's wrapped with 3 layers of Ta as the heat-shield, including the backblock.

TGHT will be ramped up to 580A at 0.2A/min.

TBHT will be ramped up to 230A at 0.2A/min.

Currently, IGP1 = 1.5e-6 Torr.  BP = 15mTorr


 Friday, July 20, 2012, 13:56

TGHT and TBHT reached to 580A & 230A, respectively, and stayed for ~ 2hrs. 

Measured temperature at the ionizer tube to be 1630C.

Cooling down in process at 2A/min...


 Sunday, July 22, 2012, 20:53

The chamber was vented earlier around 14:00hr.  

The target container looks good! 


 

  171   Wednesday, November 19, 2014, 15:10 Laura LambertEmpty39530-2LP-FEBIADDonetest#1. direct voltage and OMEGA temperature measurements

 Wednesday, November 19, 2014, 15:10

currently pumping down


 Wednesday, November 19, 2014, 15:28

container is wrapped with 3 x Ta-heat shield

leak check done

Starting voltage = -0.017mV

TGHT = 0A, 0V

TBHT = 0A, 0V

IGP1 = 1.7e-6 Torr


 Wednesday, November 19, 2014, 16:33

Tapped TGHT up manually to 100A

DV [direct voltage] = 0.33V

TGHT = 109A

TBHT = 0A

IGP1 = 1.3e-6 Torr

Initiating auto-ramp of TGHT to 400A at 2A/min


 Thursday, November 20, 2014, 09:49

DV = 3.47V

OMEGA = 1645C

TGHT = 401A, 6.49V

TBHT = 0

IGP1 = 4.5e-7Torr

TGHT finished auto-ramping ~19:00 last night

initiating manual tap up to 2000 celsius or 580A [whichever is higher] and recording activity


 Friday, November 21, 2014, 12:50

TGHT was ramped up to 580A yesterday and left overnight.

In the picture attached one can see the TGHT current has remained constant at 578A [red = TGHT current, green = TGHT voltage]

The vacuum has slowly gone down as expected.

However, the DV, TGHT voltage and temperature have deviated. They have dipped up and down several times throughout the night. The first deviation was observed ~3.5hours after it reached its target of 580A.

DV reached 6.02V [when TGHT initially hit 580A] and increased to 6.27V after 3.5hrs and is currently sitting at 5.94V

OMEGA reached 2111C [when TGHT initially hit 580A] and increased to 2154C after 3.5 hrs and is currently sitting at 2094C

TGHT voltage reached 10.4V [when TGHT initially hit 580A] and increased to 10.6V after 3.5hrs and is currently sitting at 10.3V


 Friday, November 21, 2014, 17:59

EVAP2 sat at max setting: TGHT = 580A and TBHT = 230A for ~4hours

Initiating auto-cool TGHT 2A/min, TBHT 1A/min


 Monday, November 24, 2014, 14:28

Vented and opened this morning.

No notable changes on target container.

[See attachments for more detailed information of results]


 

Attachment 1: test#1_TGHT_[without_vacuum].JPG
test#1_TGHT_[without_vacuum].JPG
Attachment 2: test#1_excel.JPG
test#1_excel.JPG
Attachment 3: test#1_graph1.JPG
test#1_graph1.JPG
Attachment 4: test#1_graph2.JPG
test#1_graph2.JPG
  341   Friday, December 16, 2016, 14:14 Laura LambertTa39530-3LP-FEBIADDoneConditioning Ta FEBIAD target for shutdown tests

 Friday, December 16, 2016, 14:08

Target consists of 470 discs.

Total packed length 3.4cm [exactly 7.8cm space on both sides]

Total mass 45.9091g [Incl foils + Ta wire on 6 packs]

Target consists of 350 single discs and 6x20 packs of Ta discs

Discs in target are arranged as follows: 1pack / 75singles / 1pack / 100singles / 2packs / 100singles / 1pack / 75singles / 1pack

3x Ta Heat shields.

LP-FEBIAD container with large center block.

No endcaps inserted, no Rh foil inserted.

Chamber currently pumping down.

TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 350A at 2.0A/min.

Final desired temperature = 1900C


 Friday, December 16, 2016, 14:32

HS water valves opened, no leaks detected
 
Tapped up manually to 35A
 
Vacuum stable, IGP1 = 2.1e-6 Torr
 
Initiating auto-ramp.
 
OMEGA slope = 0.98

 Monday, December 19, 2016, 11:52

Tapped up manually to ~1900C [see attached excel for details on data collected - interesting temperature fluctuations]

 Will remain at max setpoints for min 4hrs then auto-cool


 Monday, December 19, 2016, 15:20

Target has remained at max setpoints for just over 4hrs

TGHT = 520A, 8.67V

OMEGA = 1820C

IGP1 = 5.2e-7 Torr

Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


 Tuesday, December 20, 2016, 11:52

Vented in air and opened up this morning.

Looks like the windows was coated in evap2, unsure if this was missed and coated before conditioning target or if this is from materials coming out during conditioning process...

Target looks good.

Endcaps inserted but not expanded.


 

Attachment 1: Ta-FEBIAD.xlsx
Attachment 2: Evernote_Camera_Roll_20161220_145947.jpg
Evernote_Camera_Roll_20161220_145947.jpg
  394   Wednesday, November 29, 2017, 16:18 Laura LambertEmpty39530-3LP-FEBIADDoneTemperature measurements for ARIEL

 Wednesday, November 29, 2017, 16:17

LP-FEBIAD loaded into evap2 today and currently pumping down.

Temperature measurements of the ionizer will be done by Fernando for ARIEL development.

Ta foil covering side holes on heat shield so no temp measurements can be done using OMEGA on side ports of evaporator as per request of Fernando

No Ta heat shields on container.

Final desired temperature of ionizer = 2000C


 Thursday, November 30, 2017, 09:51

HS water valves opened, no leaks detected.

IGP1 = 2.1e-7 Torr

IGP2 = 1.7e-7 Torr

Tapped up to TGHT = 350A, 5.83V; TBHT = 230A, 3.31V

IGP1 = 6.3e-7 Torr

IGP2 = 3.7e-7 Torr

Will check temp measurements in lab after lunch before proceeding...


 Friday, December 01, 2017, 11:04

Temperature measurements done.

Initiated auto-cool this morning.

TGHT cooling at 2.0A/min and TBHT at 1.0A/min.


Monday, December 04, 2017, 11:04

Removed from evap2 this morning.

  400   Wednesday, December 13, 2017, 10:55 Laura LambertEmpty39530-3LP-FEBIADDoneTemperature measurements for ARIEL

 Wednesday, December 13, 2017, 10:36

LP-FEBIAD loaded into evap2 this morning and pumped down.

Temperature measurements of the ionizer will be done by Fernando for ARIEL development.

Ta foil covering side holes on heat shield so no temp measurements can be done using OMEGA on side ports of evaporator as per request of Fernando

No Ta heat shields on container.

HS water valves opened, no leaks detected.

IGP1 = 2.3e-6 Torr

IGP2 = 1.7e-6 Torr

Tapped up to TGHT = 50A, 0.30V; TBHT = 50A, 0.59V

IGP1 = 1.8e-6 Torr

IGP2 = 1.4e-6 Torr

Initiating auto ramp for TGHT at 2.0A/min up to 350A and TBHT at 1.0A/min up to 210A


 Wednesday, December 13, 2017, 14:53

IGP1 = 7.6e-7 Torr

IGP2 = 6.4e-7 Torr

TGHT = 350A, 5.85V

TBHT = 210A, 3.02V

TGHT and TBHT will be adjusted accordingly for temperature measurements...


Thursday, December 14, 2017, 09:16 

IGP1 = 2.1e-7 Torr

IGP2 = 1.7e-7 Torr

TGHT = 385A, 6.80V

TBHT = 210A, 3.01V

Tapped up to TGHT = 400A, 7.11V

Stopped for temperature measurements.

Tapped up to TGHT = 450A, 8.20V


 Friday, December 15, 2017, 09:50

IGP1 = 1.2e-7 Torr

IGP2 = 9.6e-8 Torr

TGHT = 350A, 5.82V

TBHT = 210A, 2.94V

Initiating auto-ramp to TGHT = 650A


Monday, December 18, 2017, 10:43

Temperature measurements done.

Initiated auto-cool.

TGHT cooling at 2.0A/min and TBHT at 1.0A/min.


 Tuesday, December 19, 2017, 11:40

Vented in air and removed from evap2 today.


 

  401   Monday, February 19, 2018, 14:16 Laura LambertEmpty39530-3LP-FEBIADDoneTemperature measurements for ARIEL

Monday, February 19, 2018, 13:39

LP-FEBIAD loaded into evap2 this morning and pumped down.

Temperature measurements of the ionizer will be done by Fernando for ARIEL development.

Ta foil covering side holes on heat shield so no temp measurements can be done using OMEGA on side ports of evaporator as per request of Fernando

No Ta heat shields on container.

HS water valves opened, no leaks detected.

IGP1 = 2.75e-6 Torr

IGP2 = 1.42e-6 Torr

Tapped up to TGHT = 50A, 0.53V; TBHT = 50A, 0.56V

IGP1 = 2.64e-6 Torr

IGP2 = 1.35e-6 Torr

Initiating auto ramp for TGHT at 2.0A/min up to 350A and TBHT at 1.0A/min up to 210A


 Tuesday, February 20, 2018, 09:15

IGP1 = 6.9e-7 Torr

IGP2 = 3.8e-7 Torr

TGHT = 350A, 5.98V

TBHT = 210A, 3.02V

TGHT and TBHT will be adjusted accordingly for temperature measurements...


 Tuesday, February 27, 2018, 14:55

Temperature measurements done.

Initiated auto-cool.

TGHT cooling at 2.0A/min and TBHT at 1.0A/min.


 Wednesday, February 28, 2018, 10:39

Tuesday, December 19, 2017, 11:40

Vented in air and removed from evap2 today.


 

  403   Thursday, March 08, 2018, 11:05 Marla CervantesEmpty39530-3LP-FEBIADDoneTemperature measurements for ARIEL

 Friday, March 09, 2018, 11:03

LP-FEBIAD loaded into evap2 and pumped down.

Temperature measurements of the ionizer will be done by Fernando for ARIEL development.

Ta foil covering side holes on heat shield so no temp measurements can be done using OMEGA on side ports of evaporator as per request of Fernando

No Ta heat shields on container.

HS water valves opened, no leaks detected.

IGP1 = 1.72e-7 Torr

 

 

IGP2 = 1.36e-7 Torr

Tapped up to TGHT = 50 A, 0.54 V; TBHT = 50 A, 0.45 V

IGP1 = 1.8e-6 Torr

IGP2 = 1.4e-6 Torr

Initiating auto ramp for TGHT at 2.0A/min up to 310A and TBHT at 1.0A/min up to 210A


Monday, March 12, 2018, 10:16 

IGP1 = 8.8e-8 Torr

IGP2 = 6.6e-8 Torr

TGHT = 310A, 5.06V

TBHT = 210A, 2.98 V

TGHT and TBHT will be adjusted accordingly for temperature measurements


Tuesday, March 13, 2018, 16:00 

Temperature measurements done.

Initiated auto-cool.

TGHT cooling at 2.0A/min and TBHT at 1.0A/min.


 

 

 

 

 

 

 

 

 

 

 

Wednesday, March 14, 2018, 16:03

Removed from evap2.

  421   Wednesday, October 31, 2018, 19:35 Marla CervantesTaC39530-1LP-FEBIADDoneTaC coating/sintering for graphite insert test

 Wednesday, October 31, 2018, 19:35

Container is coated with TaC and wrapped with Ta heat-shield (3 layers)

Desired temp = 1900 C (expected TGHT ~445A/7.5V), TBHT will be set fixed at 230A (max).

Chamber is currently being pumped down


 Thursday, November 01, 2018, 10:31

Pressure at IGP1 9.44e-7 Torr. 

Tapped up TGHT and TBHT manually to 40 A


Thursday, November 01, 2018, 12:32

Waited ~1 hr for vacuum to stabilize.

IGP1 = 1.42e-6 Torr

Good vac at 3.00-5 Torr

Bad vac at 5.0e-5 Torr.

Initiating auto ramp for TGHT @ 1 A/min to a max setpoint of 350 A

Initiating auto ramp for TBHT @ 0.5 A/min to a max setpoint of 230 A

Once max setpoints achieved, will tap up manually to final desired temperature of 1900 C


 Tapped manually to 445 A, Temperature 1896 C.


Friday, November 02, 2018, 07:35

TGHT 7.86 V 445.6 A

TBHT 3.22 V 233.3 A

IGP1 1e-6 Torr

Ramping down TGHT and TBHT to 0 A @ 2 A/min.  


Friday, November 02, 2018, 17:28

Monday, October 29, 2018, 12:39

Venting EVAP2, TaC coat sintering completed. 

Attachment 1: Capture.JPG
Capture.JPG
Attachment 2: Coating.jpg
Coating.jpg