20
|
Tuesday, May 15, 2012, 17:06 |
John Wong | | | | Problems resolved | TBHT power supply faulty | Tuesday, May 15, 2012, 17:03
The tube heater power supply current
readback and setpoint are not matching. Ray |
|
|
21
|
Wednesday, May 16, 2012, 14:04 |
John Wong | | | | Problems resolved | TBHT cooling line leaky |
|
|
|
96
|
Thursday, November 07, 2013, 09:38 |
Anders Mjos | | | | Problems resolved | Heat Shield cooling line twisted | See attached photo.
The Heat Shield has been taken to
the Machine Shop for repair. |
|
|
110
|
Thursday, January 23, 2014, 16:22 |
Laura Lambert | Empty | 40282-4 | TARGET BOAT | Problems resolved | Sintering Ta target boat with TaC coating |
|
|
|
120
|
Friday, March 07, 2014, 10:34 |
Anders Mjos | | | | Problems resolved | TGHT2 water flow signal | There was no signal going from the coils
to the PLC. After manipulating the connection
points on the coil a signal could again be |
|
|
124
|
Monday, March 10, 2014, 11:52 |
John Wong | | | | Problems resolved | The Chiller is down | Monday, March 10, 2014, 11:45
The chiller tripped off on March
7, 2014. |
|
|
175
|
Thursday, January 22, 2015, 14:21 |
Anders Mjos | Empty | | | Problems resolved | CG1A replaced | See previous e-log entry
for details |
|
|
345
|
Monday, February 06, 2017, 11:17 |
Anders Mjos | | | | Problems resolved | IOC restart after power outagae | Dave Morris did a remote restart
of the IOC after the outage. Turbo pump started. |
|
|
348
|
Tuesday, February 14, 2017, 15:44 |
Laura Lambert | Endcaps | | TARGET BOAT | Problems resolved | Sintering TaC coating on Ta endcaps and springs |
|
|
|
356
|
Thursday, April 06, 2017, 11:15 |
Laura Lambert | Empty | | TARGET BOAT | Problems resolved | Sintering TaC coating on evap1 target boat |
|
|
|
362
|
Wednesday, May 03, 2017, 16:09 |
Laura Lambert | SiC | 39530-10 | HP-FEBIAD | Problems resolved | Sintering SiC#36 |
|
|
|
385
|
Tuesday, August 08, 2017, 15:00 |
Laura Lambert | Empty | | | Problems resolved | Wiring in PLC replaced re: IGP1 mis-communicating | Tuesday, August 08, 2017, 14:57
See elog i.d's #384 and #381
Investigated wiring in PLC. |
|
|
397
|
Friday, December 08, 2017, 15:29 |
Laura Lambert | Endcaps | | TARGET BOAT | Problems resolved | Sintering TaC coating on endcaps and springs |
|
|
|
411
|
Friday, June 08, 2018, 08:33 |
Aaron Schmidt | | | | Problems resolved | Chiller tripped / Alarm | Alarm noted on passing Hot Lab. RPG notified,
no radiological hazards. ISAC ops contacted,
drop in DI water last night. |
|
|
458
|
Tuesday, September 17, 2019, 13:25 |
Aaron Schmidt | | | LP-SIS | Problems resolved | Turbo pump / roughing troubleshoot. | Swapped out VCRs on HS to tray connection.
(Right one felt slightly off)
Tuesday, September 17, 2019, 13:23: |
|
|
466
|
Friday, November 15, 2019, 13:26 |
Aaron Schmidt | SiC | | HP-FEBIAD | Problems resolved | Temp map testing - 1. (Leak issue) | HS 42752-5 - Setup for Temperature
mapping.
Friday, November 15, 2019, 13:26: |
|
|
472
|
Tuesday, November 26, 2019, 15:43 |
Anders Mjos | SiC | 42464-3 | HP-FEBIAD | Problems resolved | Water to vacuum leak on heat shield line | This morning, the vacuum responded to shutting
of the water of the heat shield circuit (leak
rate without pumping leveling out). The vacuum |
|
|
671
|
Wednesday, August 14, 2024, 16:22 |
Marla Cervantes | C | 44139-5 SK | LP TUBE | Problems resolved | EVAP2 Calibration - Vanadium |
|
|
|
19
|
Tuesday, May 15, 2012, 17:03 |
John Wong | | | | Problems | TBHT cooling line leaky | Tuesday, May 15, 2012, 17:00
It was found that there were water
droplets from the TBHT cooling line. The |
|
|
28
|
Monday, May 28, 2012, 11:15 |
John Wong | | | | Problems | Chiller is leaking water | Monday, May 28, 2012, 11:08
It was discovered this morning that
the Evaporator #2 chiller was leaking water |
|