Entry  Thursday, September 19, 2024, 22:48, Darwin Ortiz Rosales, UO2/C, conditioning oven#3, LP TUBE, Done, UCx240917 reduction 
Thursday, September 19, 2024, 22:44
 
Cartridge #21 loaded with 211 discs including 3 analysis discs
Entry  Tuesday, January 14, 2025, 16:28, Darwin Ortiz Rosales, UO2/C, conditioning oven#3, LP TUBE, In progress, UCx250113 reduction 
Tuesday, January 14, 2025, 16:26
 
Cartridge #22 loaded with 211 discs including 3 analysis discs
Entry  Thursday, September 29, 2011, 10:58, John Wong, UO2/C, UCx-heatboat#2, , Done, UCx#3: Batch#1 - UO2/C mixture of carbonization  6x
Thursday, September 29, 2011, 10:54
UO2/C mixture was made on Tuesday Sept 27, casted on a piece of glass and let dried in the fume hood for ~2days. 
Dried UO2/C mass = 61.72g
Entry  Thursday, October 06, 2011, 12:22, John Wong, UO2/C, UCx-heatboat#2, , Done, UCx#3: Batch#2 - UO2/C mixture of carbonization  UCx#3_batch#2_tripped@40A.jpgUCx#3_batch#2_TGHT@317A.JPGUO2_C_batch#2_Archive_overall_process.JPG
 Thursday, October 06, 2011, 12:19
 
UO2/C mixture was made on Oct 4 and casted on a piece of glass costed with WD40, and let dried in the fume hood for 2days. 
Entry  Wednesday, June 06, 2012, 16:58, John Wong, UO2/C, UCx-heatboat#2, , Done, UC2 flakes for UCx#4: batch#01-04062012 7x
Wednesday, June 06, 2012, 16:55
The UO2/C green was prepared on June 04, 2012. 
UO2 powder used = 50.26g
    Reply  Monday, June 11, 2012, 10:48, John Wong, UO2/C, UCx-heatboat#2, , Problems, UC2 flakes - batch#01-04062012: broken seal & TGHT power supply 


    
        
            John Wong wrote:
        
        
            
            Wednesday, June 06, 2012, 16:55
    Reply  Tuesday, June 12, 2012, 11:38, John Wong, UO2/C, UCx-heatboat#2, , Problems resolved, UC2 flakes - batch#01-04062012: broken seal & TGHT power supply 


    
        
            John Wong wrote:
        
        
            
            
            
              
    Reply  Sunday, June 24, 2012, 22:52, John Wong, UO2/C, UCx-heatboat#2, , Problems, UC2 flakes - batch#01-04062012: IOC problems IOC_problem.png


    
        
            John Wong wrote:
        
        
            
            Wednesday, June 06, 2012, 16:55
    Reply  Monday, June 25, 2012, 16:00, John Wong, UO2/C, UCx-heatboat#2, , Problems resolved, UC2 flakes - batch#01-04062012: Fiber converters failed 


    
        
            John Wong wrote:
        
        
            
            
            
Entry  Wednesday, May 25, 2011, 14:42, John Wong, UO2/C, UCx-heatboat#1, LP-SIS, Done, Batch#1: UO2/C mixing & carbonization Screen_shot_2011-05-26_at_3.14.00_PM.pngauto_ramping.pngUCx_2011_A_carbonization.pngEvaporator_Ar_flow.pngUC2.png
Before began the carbonization process, two cameras were setup in the hotlab for monitoring the evaporator and the power supply.  On duty ISAC Ops
also helps to monitor on a regular basis and to grab the striptools + cameras (twice/shift) and put this information in the ISAC Logbook with subject header:
 "UCx_2011_A 'date time'", for easy search.  
Entry  Thursday, June 30, 2011, 12:42, John Wong, UO2/C, UCx-heatboat#1, LP-SIS, Done, Batch#2: UO2/C for carbonization startup_vac.jpgstartup_current.jpgparameter.jpgUCx_2011_b_3days.pnggrab.S13888.png
Before began the carbonization process, two cameras were setup in the
hotlab for monitoring the evaporator and the power supply.  On duty ISAC Ops also helps to monitor on a regular basis and to grab the striptools +
cameras (twice/shift) and put this information in the ISAC Logbook with subject header:  "UCx_2011_B 'date time'", for easy search.  
Entry  Thursday, July 19, 2012, 17:14, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes for UCx#5 - (batch#02-13062012) TGHT_100A.pngUC2_flakes_0-520A.GIF
Thursday, July 19, 2012, 17:09
UO2/C green was prepared on June 13, 2012. 
UO2 powder used = 50.32g (Inventory R-00835A UO2 + bottle = 946.48g left)
Entry  Tuesday, April 02, 2013, 17:46, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes for UCx#6 (batch#03 - 02042013) 
Tuesday, April 02, 2013, 17:25
UO2/C green was prepared on Mar 11, 2013.
UO2 powder used = 50.32g (Inventory R-00835A UO2 + bottle = 896.16
Entry  Monday, May 06, 2013, 14:34, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#04 - 05032013)  UC2_flakes_batch#04-05032013.PNG
Monday, May 06, 2013, 14:29
UO2/C green was prepared on May 2, 2013 and let dry over the weekend.
UO2 powder used = 50.36g   (Inventory R-00835A UO2 + bottle = 896.30)
Entry  Tuesday, June 25, 2013, 14:49, Laura Lambert, UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013) 
 Tuesday, June 25, 2013, 14:35
UO2/C green was prepared on June 18, 2013 and let dry over the weekend.
UO2 powder used = 50.25g (Inventory R-00835A UO2 + bottle = 845.94g - before use)
    Reply  Tuesday, June 25, 2013, 16:28, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013) 


    
        
            Laura Lambert wrote:
        
        
            
             Tuesday, June 25, 2013, 14:35
Entry  Tuesday, July 02, 2013, 11:13, Peter Kunz , UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013) UO2-C-01.png
 
1. stage - burning off organics complete
2. stage - carbonization began 1-8 am 2013/07/02
    Reply  Thursday, July 11, 2013, 16:22, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013) 


    
        
            Peter Kunz  wrote:
        
        
            
             
    Reply  Monday, July 15, 2013, 09:45, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013) 


    
        
            John Wong wrote:
        
        
            
            
            
              
Entry  Monday, May 14, 2012, 15:22, John Wong, , Target boat, , , Testing the new graphite foil from Ceramaterial parameter.JPGTGHT_0-820A.GIFgraphite_test_target_boat.pdfGraphite_Foil-Certifcate_of_Compliance-Triumf_Order-1-16-12.pdf
Monday, May 14, 2012, 15:04
Due to the differences in the use of the graphite foils in past SiC targets (C-grv foil from Alpha Aesar) and the newly prepared SiC#27 (C-grv
foil from Ceramaterial), the out-gassing period for SiC#27 took over 6 days compared to 3 days for the vacuum to come down (see https://elog.triumf.ca/TIS/Evaporator_1/47). 