  20   Wednesday, May 11, 2011, 16:23 John WongSiC38481-8HP-FEBIADProblems Organics burnoff & Sintering Wed May 11 16:20:21 2011:  The HP-FEBIAD
(w.o#38481-8) was filled with SiC (8.5mm,
555 discs).  The target is wrapped with
 9x 
  21   Tuesday, May 17, 2011, 16:43 John Wong   MaintenanceEvaporator Ion gauge replaced The evaporator ion gauge filament burnt
out on May 11, 2011.  A target was in
the evaporator at that time and was about
  
  22   Wednesday, May 18, 2011, 13:13 John WongSiC38295-8HP-FEBIADProblemsOrganics burnoff & Sintering Wed May 18 13:12:24 2011:  Target
is wrapped with 3 Ta-heat shields and is
installed in the evaporator which is being
 6x 
  23   Wednesday, May 25, 2011, 14:42 John WongUO2/CUCx-heatboat#1LP-SISDoneBatch#1: UO2/C mixing & carbonizationBefore began the carbonization process,
two cameras were setup in the hotlab for
monitoring the evaporator and the power supply.
 Screen_shot_2011-05-26_at_3.14.00_PM.pngauto_ramping.pngUCx_2011_A_carbonization.pngEvaporator_Ar_flow.pngUC2.png 
  24   Thursday, June 30, 2011, 12:42 John WongUO2/CUCx-heatboat#1LP-SISDoneBatch#2: UO2/C for carbonizationBefore began the
carbonization process, two cameras were setup
 startup_vac.jpgstartup_current.jpgparameter.jpgUCx_2011_b_3days.pnggrab.S13888.png 
  25   Monday, July 18, 2011, 15:55 John WongEmpty38634-3LP-SISDoneSintering TaC coating for UCx#2 Monday, July 18, 2011, 15:53:  Target
oven was coated with TaC and let dry over
the weekend.  The target is now installed
 striptool.jpg 
  26   Wednesday, July 27, 2011, 13:02 John WongUC238634-3LP-SISProblemsUCx#2 conditioning Wednesday, July 27, 2011, 12:58: 
Target length = 11.2cm
Total UC2/C foils = 245 discs
 striptool_july31.pngTarget_with_3_heat_shields.jpgstriptool_july31_600A.jpgUCx#2-conditioning.jpg 
  27   Wednesday, August 03, 2011, 17:16 John WongEmpty38634-8LP-SISDoneSintering TaC coating Wednesday, August 03, 2011, 20:27 :  Target
was wrapped with 3 new Ta-heat shields and
2 around the back block.  The tar from
 striptool.JPG 
  28   Thursday, August 04, 2011, 17:46 John WongUC238634-8LP-SISProblems resolvedRepacking UCx in new target ovenThursday, August 04, 2011, 17:44: 
All the UCx material from target oven  38634-3
was recovered and repacked in this new oven. 
 200A.jpgreconditioning.jpg 
  29   Monday, August 29, 2011, 11:21 John WongEmpty38634-6LP-SISDoneSintering TaC coating oven for TaC#1 Monday, August 29, 2011, 13:16: Target
oven was coated with TaC and let dry over
night.  The target oven is in the evaporator
 TaC_target_oven.JPG 
  31   Tuesday, August 30, 2011, 16:30 John WongEmptyTarget BoatLP-SISDoneSintering of End Caps


   
        
            
  
  32   Tuesday, September 06, 2011, 17:05 John WongEmpty38634-6LP-SISDoneSintering TaC coating oven for TaC#1


   
        
            
 striptool.JPG 
  33   Wednesday, September 07, 2011, 13:33 John WongEmpty  MaintenanceChanged Evaporator#1 Backing Pump oil Wednesday, September 07, 2011, 11:18:  
IEVAP:CG2 @ 52mT before oil change. 
Edi D.V changed the oil for the backing
  
  34   Wednesday, September 07, 2011, 13:41 John WongTaC38634-6LP-SISDoneTaC#1: Sintering and Organics burn-off Wednesday, September 07, 2011, 15:31
125 discs of TaC/C
Total discs mass = 125
 TaC#1.jpgendcaps_after_sintering.pngTaC_aftersintering.jpg 
  36   Friday, September 09, 2011, 10:05 John WongEmpty HP-FEBIADDoneSintering TaC coatingFriday, September 09, 2011, 10:05
Target oven coated with TaC, and
wrapped with 3-Ta heat shields.  Chamber
 striptool.JPG 
  37   Monday, September 12, 2011, 13:08 John WongEmptyTarget Boat DoneSintering TaC coating on End CapsMonday, September 12, 2011, 13:07
Target boat is loaded with coated
TaC end caps for sintering.  Target
 striptool.JPG 
  38   Tuesday, September 13, 2011, 16:53 John WongSiC38295-9HP-FEBIADDoneReady Tuesday, September 13, 2011, 16:51
Target is wrapped with 3-Ta heat
shields. 
 9x 
  39   Wednesday, September 21, 2011, 13:23 John WongEmpty38634-10LP-SISDoneSintering TaC coating on target oven for UCx#3 Wednesday, September 21, 2011, 13:23
Target oven was wrapped with 3-Ta
heatshields including the back block. 
 archiver_TGHT0-580A.JPG 
  40   Thursday, September 22, 2011, 20:34 John WongEmpty38634-9LP-SISDoneSintering TaC coating for UCx#2 (spare) Thursday, September 22, 2011, 20:21
Target oven was wrapped with 3 Ta-heat
shields and has been pumping down.
  
  41   Thursday, September 29, 2011, 10:58 John WongUO2/CUCx-heatboat#2 DoneUCx#3: Batch#1 - UO2/C mixture of carbonization Thursday, September 29, 2011, 10:54
UO2/C mixture was made on Tuesday
Sept 27, casted on a piece of glass and let
 6x 