  ID Date Author Target/No.# Source Stationup Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  965   Friday, May 05, 2023, 06:49 Aaron SchmidtTiC#6HP-FEBIADITWTM244692-1045235-12In progressConditioning TiC#6Ceramic elbow installed on the anode.
Friday, May 05, 2023, 06:47: Roughing.
Friday, May 05, 2023, 07:24: TP1B
 TiC#6_Anode_&_Coil_checks.docx 
  971   Thursday, July 06, 2023, 16:55 Aaron SchmidtNb#10LP-IG-LISITWTM245447-742132-2In progressConditioning Nb#10Thursday, July 06, 2023, 16:13: Roughing.
Thursday, July 06, 2023, 16:41: TP1B
on.
 Nb#10_Conditioning.docx 
  978   Friday, August 25, 2023, 17:21 Aaron SchmidtNb#11LP-IG-LISITWTM245447-942132-4In progressConditioning Nb#11Replacement for Nb#10
Friday, August 25, 2023, 17:15: Roughing.
Friday, August 25, 2023, 17:57: Vacuum
 Nb#11_Conditioning.docx 
  980   Monday, September 25, 2023, 16:31 Aaron SchmidtTa#66LP-SISITWTM245220-545235-9DoneConditioning Ta#66 & HV Tests.Thermocouples installed on the left end
plate x 2.
Monday, September 25, 2023, 16:23:
 Ta#66_HV_Test_1.docxTa#66_HV_test_2.docxTa#66_Conditioning.docx 
  1002   Tuesday, April 09, 2024, 16:01 Aaron SchmidtEmpty (Online)LP-FEBIADITWTM445447-2442972-8In progressConditioning empty FEBIAD for online useTuesday, April 09, 2024, 15:25: Roughing.

Wednesday, April 10, 2024,
05:41: TP1B on. 
 EE_issue_-_Conditioning_LP-FEBIAD_ITW-TM4.docx2024_-_ITW-_TM4_LP_FEBIAD.docx 
  1004   Wednesday, April 17, 2024, 14:16 Aaron SchmidtEmpty (Online)LP-FEBIADITWTM445447-2442972-8In progressConditioning empty FEBIAD for online use - Run 2https://elog.triumf.ca/TIS/Test-Stand/1003
EE Issue resolved. TS closed up.
Wednesday, April 17, 2024, 14:08:
 2024_-_ITW-_TM4_LP_FEBIAD_-_2.docx 
  1007   Friday, April 26, 2024, 13:49 Aaron SchmidtTiC#7HP-FEBIADITWTM445447-545235-15In progressConditioning TiC#7FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B
  