  Test-Stand, Page 6 of 53  Not logged in ELOG logo
ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subjectdown Text Attachments
  571   Tuesday, February 21, 2017, 10:35 Aaron Schmidt    42218-1141751-6Problems/SolutionsWater leak (E)(G)Water leak found on water block lines (E)
& (G) on FS #3.
Both lines were removed at the water
  
  919   Wednesday, April 13, 2022, 07:46 Aaron Schmidt      Problems/SolutionsWater leakWednesday, April 13, 2022, 07:38: Appears
to have a water leak. Vacuum @ 8.48e-06T.
All power / sources shut off. (Had already
  
  418   Tuesday, December 23, 2014, 09:08 Anders Mjos       Water closed for ChristmasShutting of water supply to the source
box. Water not needed.
  
  88   Tuesday, May 15, 2012, 08:16 Rick Maharaj       Water circuits flushed    
  678   Tuesday, August 14, 2018, 11:03 Aaron Schmidt LP-SIS  41177-342752-6 Voltage Tests (Ta target)Tuesday, August 14, 2018, 10:55: Auto ramping
TGHT @ 6 A per min to 40 A.
Tuesday, August 14, 2018, 11:03:
  
  680   Wednesday, August 22, 2018, 15:20 Aaron Schmidt LP-SIS  41177-3  Voltage Tests (Ta Target)  Wires reconfigured / set 
Wednesday, August 22, 2018, 13:10:
Roughing. 
  
  316   Thursday, June 13, 2013, 11:04 Anders Mjos      Problems/SolutionsViton seals on vacuum chamber doors replacedSee PO# TR193650    
  72   Monday, April 16, 2012, 11:16 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling linesVenting chamber and purging cooling lines
in preparation for target removal
  
  73   Monday, April 16, 2012, 11:56 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling lines

    

       
            
  
  191   Friday, August 31, 2012, 11:39 Anders MjosNiO#1HP-FEBIADITETM4  DoneVenting vacuum chamber - source changeFriday, August 31, 2012, 11:39: Stopped
turbos.
Friday, August 31, 2012, 13:06: Venting.
  
  171   Thursday, August 16, 2012, 15:30 Anders Mjos      Problems/SolutionsVenting to investigate short between anode - cathodeThursday, August 16, 2012, 15:29: Turbos
off
Thursday, August 16, 2012, 15:50
  
  151   Thursday, July 19, 2012, 09:35 Anders Mjos      DoneVenting to investigate leak on front doorThursday, July 19, 2012, 09:35: Switched
off both turbos.
Thursday, July 19, 2012, 10:23: Venting
  
  356   Friday, January 24, 2014, 10:49 Anders Mjos      Problems/SolutionsVenting the optics section to investigate Emittance Rig installationFriday, January 24, 2014, 10:49 : Stopped
turbos. Vacuum at 2.5E-7 T 
Friday, January 24, 2014, 12:52:
  
  230   Monday, November 05, 2012, 13:26 Aurelia Laxdal LP-SISITWTM1  DoneVenting the Test StandVenting the Test Stand.
TiC#3 will be ready to be removed
in few minutes. 
  
  50   Friday, March 02, 2012, 13:28 Anders MjosFEBIAD test      Venting test standVenting for target exchange   
  100   Thursday, May 31, 2012, 14:46 Anders Mjos       Venting in preparation for Ta#38Thursday, May 31, 2012, 14:46: Switching
off turbos
Thursday, May 31, 2012, 15:05: Venting
  
  235   Thursday, November 29, 2012, 14:15 Anders Mjos      In progressVenting in preparation for RFQ work Thursday, November 29, 2012, 14:15:
Stopping turbos
Thursday, November 29, 2012, 15:57:
  
  861   Wednesday, March 10, 2021, 11:10 Carla Babcock       Venting for installation of emittance metersWednesday, March 10, 2021, 10:48 
: Venting beamline section only for installation
of emittance meters.
  
  81   Thursday, May 10, 2012, 08:13 Anders Mjos      Problems/SolutionsVenting for TSGIG1 repair

    

       
            
  
  222   Thursday, October 25, 2012, 11:13 Anders MjosTestHP-FEBIAD    In progressVenting chamber for installation of TiC#3Thursday, October 25, 2012, 11:11: Vacuum
at 1.3E-7 T
Thursday, October 25, 2012, 11:12:
  