  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Statusdown Subject Text Attachments
  316   Thursday, June 13, 2013, 11:04 Anders Mjos      Problems/SolutionsViton seals on vacuum chamber doors replacedSee PO# TR193650    
  318   Thursday, July 11, 2013, 08:38 Anders Mjos      Problems/SolutionsBias & EL P/S cleanedThe power supplies were "de-dusted"
yesterday by Ray Dube and team. 
  
  319   Friday, July 12, 2013, 15:52 Anders Mjos      Problems/SolutionsTMS:MB1 fuse latched after mass scanA flash and "thumb" was observed
at the end of the mass scan.
Friday, July 12, 2013, 15:51: Ray
  
  321   Tuesday, July 16, 2013, 16:01 Anders Mjos      Problems/SolutionsFEBIAD coil connector insulator fractureThe right side of the insulator cracked/fractured
either as the bolt was tightened or loosened. 
 Photo_2013-07-16_3_36_45_PM.jpg 
  322   Wednesday, July 17, 2013, 12:55 Anders Mjos      Problems/SolutionsControls are removing dust/cleaning their devicesThursday, July 18, 2013, 08:41: Restarting
archivers
  
  324   Monday, July 22, 2013, 14:08 Anders Mjos      Problems/Solutions20V 60A COIL PS installed for FEBIAD Coil TestBy Ray. Note that controls have not been
updated yet.
  
  326   Tuesday, August 20, 2013, 08:27 Anders Mjos      Problems/SolutionsTP1B noise - TP1B replacementTP1B high frequency noise is coming and
going. Power is 22W , current 1.1A (other
pumps are 11W and 14W, 0.7A)
  
  327   Friday, August 23, 2013, 11:16 Anders Mjos      Problems/SolutionsPossible leak between BV1A, BV1B and PV1CG1A is climbing from 0.016 to 0.130 in
30 seconds when isolated.
The leak was confirmed to be between
  
  328   Monday, August 26, 2013, 13:49 Anders Mjos      Problems/SolutionsTP1A time out/fault sometime this weekendMonday, August 26, 2013, 14:07: The turbo
could be restarted, but it does not sound
happy (Dimo was consulted earlier today).
  
  329   Wednesday, August 28, 2013, 11:28 Anders Mjos      Problems/SolutionsHall probe controller for MB1 removedJens Lassen provided a new controller for
the Hall prove. With the help from Graham
from controls it was reconfigured and is
  
  331   Monday, September 09, 2013, 09:12 Anders Mjos      Problems/SolutionsCoil power supply backRay D. installed the "standard"
6V 200A FEBIAD COIL P/S on Friday morning.It
has not yet been tested as water supply was
  
  332   Monday, September 09, 2013, 09:14 Anders Mjos      Problems/SolutionsGround Electrode cleanedMonday, September 16, 2013, 17:04: Cleaned
GE. Copper shavings were removed from below
the guide pins for the Heat Shield. The shavings
 Dirty_GE.pdf 
  334   Tuesday, September 17, 2013, 10:06 Anders Mjos      Problems/SolutionsTGHT insulator crackedThe coil insulator has been observed to
have cracked earlier. 
 Photo_2013-09-16_3_53_19_PM.jpg 
  335   Wednesday, September 18, 2013, 14:54 Anders Mjos      Problems/SolutionsHall probe calibrationNew calibration of the m/q based on
the hall probe after exchanging the controller(MASSOVERQ2).
Based on NiO#2-HP-FEBIAD with Ne supplied
 2013-09-18_NiOcalibration.png 
  338   Monday, September 30, 2013, 15:19 Anders Mjos      Problems/SolutionsNew purging valves installed on Heat Shield water circuitThe Heat Shield circuit can now be separately
purged for water. Use valves on heat shield
circuit to purge the lines for target exchanges
  
  339   Thursday, October 03, 2013, 08:43 Anders Mjos      Problems/SolutionsTMS:TP2 tripped off - controller replaced.This morning the turbo was found tripped
off. 
The controller was replaced by Edi
  
  340   Thursday, October 03, 2013, 14:15 Anders Mjos      Problems/SolutionsTMS:Q1 and Q6 tripped    
  342   Tuesday, October 22, 2013, 15:20 Rick Maharaj      Problems/SolutionsTarget Heater Conductor Block Insulators ReplacedThe Conductor insulating blocks - ITD053C
and ITD054C - that secure the target heater
and coil conductor blocks were replaced.
 Source_Tray_TGHT_and_COIL_insulators_replaced_2013-10.pdf 
  343   Tuesday, November 05, 2013, 15:50 Anders Mjos      Problems/SolutionsBacking pressure TSG:CG1A and CG1B elevatedPressure around 140 mTorr. The pressure
started increasing early November 2nd. Will
continue to monitor.
 Vacuum.png 
  344   Tuesday, November 12, 2013, 12:38 Anders Mjos      Problems/SolutionsVacuumed desk, on and around the beam line    