Entry  Thursday, November 28, 2024, 13:47, Isaiah Rabuka, , , , , , , ,  
 November 28, 2024 1:46PM
Checked in on sample in ATTS.
Entry  Tuesday, December 03, 2024, 15:49, Isaiah Rabuka, , , , , , , ,  
  Tuesday, December 03, 2024, 15:48
Switched out pellets in ATTS, brought pressures down to ~10 uTorr, heated and cooled sample.
Entry  Wednesday, December 04, 2024, 15:43, Isaiah Rabuka, , , , , , , ,  
  Wednesday, December 04, 2024, 15:42 Depressurized the ATTS
Entry  Thursday, December 05, 2024, 14:06, Isaiah Rabuka, , , , , , , ,  
 Thursday, December 05, 2024, 14:05 Pressurized ATTS with argon, swapped out samples, and repressurized and heated chamber.
Entry  Friday, December 06, 2024, 16:03, Isaiah Rabuka, , , , , , , ,  
  Friday, December 06, 2024, 16:03 Heated and cooled a sample in the ATTS
3x
Entry  Tuesday, December 10, 2024, 14:38, Isaiah Rabuka, , , , , , , ,  
  Tuesday, December 10, 2024, 14:38 Depressurized ATTS using argon, switched
out samples, and repressurized ATTS. Heated new sample to 1000 degrees Celsius.
 
Entry  Wednesday, September 28, 2011, 14:11, Friedhelm Ames, SiC#26, , ITE, TM4, , , , gas system checked and pumped 
The gas system has been checked. The variable valve opens at about 7.55 very fast. Please be careful when using it. Stepsize for opening around this
value should be 0.01. Gas lines have been pumped with pump in the high voltage rack. Ne leak was opened to release pressure.
Entry  Friday, January 20, 2012, 10:37, Friedhelm Ames, , , , , , , , vacuum pumps shut off 
turbo pumps shut off due to work on cooling water system
Entry  Tuesday, January 24, 2012, 09:44, Friedhelm Ames, , , , , , , , turbo pumps restarted 
All turbo pumps have been restarted after cooling water is back and running.
 
Entry  Wednesday, February 08, 2012, 17:39, Friedhelm Ames, , , , , , , Failed, TSG:TP1B failure 
Both turbo pumps at the source box were found off. TSG:TP1A has been started normally. TSG:TP1B does not spin up above 3KRPM even after several attemps.
A fault report has been send to vacuum group.
 
    Reply  Wednesday, February 08, 2012, 18:16, Friedhelm Ames, , , , , , , Failed, TSG:TP1B and TSG:TP1A failure  


    
        
            Friedhelm Ames wrote:
        
        
            
            Both turbo pumps at the source box were found off. TSG:TP1A has been started normally. TSG:TP1B does not spin up above
Entry  Monday, February 27, 2012, 17:39, Friedhelm Ames, , , , , , , In progress, target and tube heaters ramped up 
ramping up target to 300 A and tube to 270 A
Entry  Wednesday, February 29, 2012, 09:43, Friedhelm Ames, , , , , , , , checking gas inlet valve for FEBIAD 
 
Entry  Wednesday, February 29, 2012, 15:08, Friedhelm Ames, , , , , , , , connected Al(CH3)3 
connected A(CH3)3 instead of He, pumped line and valve with pump on the high voltage rack.. Opened regulating valve first response at mass 27 with valve
set point at 7.0.
Entry  Wednesday, February 29, 2012, 17:22, Friedhelm Ames, , , , , , , , mass scan  grab.BI5978.png
mass scan with valve at 7.2 to let in Al(CH3)3 saved as
plotdump-local-clean.txt_Feb29_12_17-19-20.txt


Entry  Wednesday, February 29, 2012, 17:26, Friedhelm Ames, , , , , , , , gas inlet valves closed 
 
Entry  Thursday, March 01, 2012, 17:04, Friedhelm Ames, , , , , , , , new mass scan grab.S19441.png
bigger mass scan after separator optimization and with finer step size
 
Entry  Thursday, March 01, 2012, 17:05, Friedhelm Ames, , , , , , , , start heater ramping down 
 
    Reply  Thursday, March 01, 2012, 17:09, Friedhelm Ames, , , , , , , , new mass scan 


    
        
            Friedhelm Ames wrote:
        
        
            
            bigger mass scan after separator optimization and with finer step size
Entry  Thursday, March 01, 2012, 17:10, Friedhelm Ames, , , , , , , , start ramping down of heaters 
 