  1043   Friday, December 20, 2024, 09:37 Dave Neilson       Winter holiday shutdownFriday, December 20, 2024, 09:37 
  turned off all 4 turbopumps. winding
down prior to evacuating.
  
  1044   Tuesday, January 07, 2025, 17:06 Dave Neilson LP-FEBIAD  44692-442972-10In progressFEBIAD development Tuesday, January 07, 2025, 16:00
-  Target assembly installed in test
stand. electrical connections assessed:
  
  1045   Thursday, January 23, 2025, 17:12 Dave Neilson       CATHODE ANODE current leak testingRecent tests have shown that CATHODE voltage
breaks down at ~130V, continually leaking
current and progressively dropping voltage,
  
  1046   Friday, February 28, 2025, 17:16 Dave Neilson LP-SIS  45447-1742972-2In progressUCx heat shield conditioningFriday, February 28, 2025, 15:54 : installed
target assembly in test stand
Friday, February 28, 2025, 15:54 
  
  1047   Tuesday, March 11, 2025, 14:36 Brady Borrmann    44691-844378-2In progressMass Marker Test TargetTuesday, March 11, 2025, 14:36 Roughing.
Target installed.
Tuesday, March 11, 2025, 15:06 TP1B
  
  1048   Thursday, April 17, 2025, 16:11 Dave NeilsonC#5    45235 - 5 LPSIS C#5 conditioningThursday, April 17, 2025, 15:46  target
installed. now roughing
Thursday, April 17, 2025, 17:12 Turbo
  