Entry  Monday, February 19, 2018, 14:01, Carla Babcock, , , , , , , , Attempts to get to higher voltages, summarized. 
The test stand holds up to 63kV, however at voltages over 54kV there are small discharges, rising to a continuous level around 60kV. The best guess right
now is that these are coronal discharges coming from the end of the HV duct to the faraday cage. The only way to fix this would be to round out the edges
of the duct, or to move the duct farther away. Since I have heard small discharges in other places, we may need to make a variety of modifications. Things
Entry  Tuesday, May 28, 2013, 09:51, Anders Mjos, , , , , , , Problems/Solutions, Archivers restarted 
COIL and ANODE data added to ISACT Data Archiver
Entry  Thursday, November 08, 2018, 14:13, Aaron Schmidt, , , , , , , , Ar & Ne gas bottle replacement. GasLeak_Datasheet.pdf
Thursday, November 08, 2018, 14:05: Fresh / recently calibrated Neon & Argon bottles installed.
Leak rates: Argon=2.02E-7 atm*cc/sec
                   Neon=1.75E-7 atm*cc/sec
Entry  Tuesday, December 17, 2024, 16:09, Dave Neilson, , , , , , , Done, Anode,TGHT, TBHT power supply investigation. Resolved 
 Note, ground and HVC (high voltage common) are used interchangeably here.
 
 
Entry  Tuesday, December 18, 2012, 12:51, Sebastian Raeder, , , , , , , , Anode powersupply connected to HV-common 
The anode PS is turned off and connected to HV common.
the Target is connected to a -18V PS at the center support (Feed through A) for a on/off test of ion suppression
NOTE: there is a shortcut target <--> HV gnd, most propably due to the thermocouple touching something after pumping.
Entry  Wednesday, December 12, 2018, 13:22, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, In progress, Anode leak current check. 
Wednesday, December 12, 2018, 13:15: Power / Sources on.
Wednesday, December 12, 2018, 13:20: RGA on / set.
Wednesday, December 12, 2018, 13:29: BIAS / EZL / EE @ 30 / 13.5 / 1.5 kV.
Entry  Monday, December 17, 2018, 12:03, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, , Anode leak current check. 
Monday, December 17, 2018, 12:01: Connected Multimeter through feedthroughs J & L. Blue wire removed.
To run TGHT, TBHT, Anode ONLY. HV will remain locked with yellow tape over the keyhole. Currently locked out.

Tuesday, December 18, 2018, 08:37: Power / sources on
Entry  Monday, October 15, 2018, 14:38, Aaron Schmidt, , , , , , , Problems/Solutions, Anode / Cathode PS to Negative 
Monday, October 15, 2018, 13:00-14:00 Anode / Cathode BIAS PS polarity reversed by John Chow.
PS: Negative
Entry  Thursday, July 12, 2012, 13:49, Anders Mjos, , , , , , , Problems/Solutions, Aluminum oxide found inside TSHSV1 
Aluminum oxide found inside TSHSV1 and the copper line to TSHUHV1.
SV1 replaced and copper line cleaned.
Entry  Monday, September 16, 2019, 10:05, Fernando Maldonado, , , , , , , Problems/Solutions, Alignment pin reinstalled 20190916_095937.jpg
 Monday, September 16, 2019, 10:03: The rightmost alignment pin has been reinstalled (see picture attached). It was previously removed for Ferran's
test. 
    Reply  Wednesday, July 18, 2012, 14:08, Anders Mjos, , , , , , , Problems/Solutions, Air supply leak on manifold fixed 


    
        
            Anders Mjos wrote:
        
        
            
            Leak found on the Ne supply line. 1E-4 - 1E-5 range. Replaced fittings. Had to use one brass piece.
Entry  Tuesday, November 15, 2022, 15:32, Sam Gupta, , , , , , , , ATTS tantalum Bracket Heating test 
Heated up sample 01 for the second time and measured the temperature with increasing current. Used pyrometre to measure temperature and calibrated it
with the emmissivity values from cassidy
Entry  Friday, April 15, 2016, 16:07, Anders Mjos, , , , , , , Problems/Solutions, ANODE polarity switched to positive 
to test the effect of extraction when biasing of the target.
    Reply  Wednesday, April 20, 2016, 08:27, Anders Mjos, , , , , , , Problems/Solutions, ANODE polarity switched to negative 


    
        
            Anders Mjos wrote:
        
        
            
            to test the effect of extraction when biasing of the target.
Entry  Thursday, October 31, 2019, 13:22, Fernando Maldonado, , , , , , , Problems/Solutions, 9pin connector not fully in contact with baseplate 20191031_130003.jpg20191031_130028.jpg
Thursday, October 31, 2019, 13:20: After inspecting the interior, the 9 pin bracket was found not making full contact with the  baseplate (pic attached).
After pushing it and re doing the bolts conctact works.
Entry  Friday, September 23, 2011, 16:40, Anders Mjos, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray 
Friday, September 23, 2011, 16:3: The connection on the 9-pin connector for FEBIAD targets showed burn marks from the previous FEBIAD tests. Corresponding
mark was found on the connector on the target side. Because of this the upper and lower 9-pin connectors were swapped to have a clean connector for the
next FEBIAD target.
    Reply  Monday, September 26, 2011, 14:56, John Wong, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray 9-pin-connector.jpg


    
        
            Anders Mjos wrote:
        
        
            
            Friday, September 23, 2011, 16:3: The connection on the 9-pin connector for FEBIAD targets showed burn
Entry  Friday, November 30, 2012, 12:04, Anders Mjos, , , , , , , In progress, 9-pin connector installation work in progress 
in preparation for RFQ testing. By Sebastian and Anders
An insulated  9-pin D-sub connector was installed on the service cap in port Q (as labeled in ISK4523). The connector mating to the target
assembly was placed in the upper slot on the source tray.
Entry  Thursday, August 15, 2019, 16:33, Fernando Maldonado, , , , , , , Problems/Solutions, 9-pin connection modification 
Thursday, August 15, 2019, 16:17: Q FT undone to remove the connection to the 9-pin
The idea is to change the cables to have individual signals. This will allow 4 thermocouple readings.
NB: The FT is not vacuum tight as of now  (gasket needs to be replaced and flange needs to be tight)
Entry  Tuesday, May 07, 2019, 13:16, Aaron Schmidt, Ta#58, LP-SIS, ITE, TM2, 43044-4, , In progress, 9-pin connection configuration (Using Ta#58) HV_Tests_2019_-_AL_-_1.docxTS-2019-05-08-08-12.rgaTS-2019-05-08-14-20.rga
Ref:
https://elog.triumf.ca/TIS/Test-Stand/679
Pin configuration between top 9-pin connector on Source Tray and  terminal in high voltage rack. Measured 2018-08-21 by Aaron and Anders