44
|
Wednesday, February 29, 2012, 17:26 |
Friedhelm Ames | | | | | | | | gas inlet valves closed |
|
43
|
Wednesday, February 29, 2012, 17:22 |
Friedhelm Ames | | | | | | | | mass scan |
mass scan with valve at 7.2 to let in Al(CH3)3 saved as
plotdump-local-clean.txt_Feb29_12_17-19-20.txt
|
42
|
Wednesday, February 29, 2012, 15:08 |
Friedhelm Ames | | | | | | | | connected Al(CH3)3 |
connected A(CH3)3 instead of He, pumped line and valve with pump on the high voltage rack.. Opened regulating valve first response at mass 27 with valve set point at 7.0. |
41
|
Wednesday, February 29, 2012, 09:43 |
Friedhelm Ames | | | | | | | | checking gas inlet valve for FEBIAD |
|
40
|
Tuesday, February 28, 2012, 16:32 |
Brandon Humphries | | | | | | | | Initial settings for FEBIAD on Test Stand |
ISAC Test Stand FEBIAD Ion Source and ISACT optics screen grabs before practicing tuning. Tune saved as: data/febiaddata/tune/120228-1620_0.snap and data/isactdata/tune/120228-1620_0.snap respectively.<br>
Seeing 1.93e-06 on TMS:FC0 and 3.30e-09 on TMS:FC6. |
37
|
Tuesday, February 28, 2012, 11:04 |
Pierre Bricault | | | | | | | | |
Calibrating the gas valve |
36
|
Tuesday, February 28, 2012, 10:29 |
Pierre Bricault | | LP-FEBIAD | | | | | In progress | Test FEBIAD at ISAC test statnd |
|
35
|
Monday, February 27, 2012, 17:39 |
Friedhelm Ames | | | | | | | In progress | target and tube heaters ramped up |
ramping up target to 300 A and tube to 270 A |
34
|
Friday, February 17, 2012, 10:27 |
Aurelia Laxdal | | | | | | | Done | Started the Archivers |
Started both ISACT and SOURCES Archivers. |
33
|
Thursday, February 16, 2012, 15:59 |
Anders Mjos | | | | | | | Problems/Solutions | He and Ne installed and gas lines leak checked |
New supply of He and Ne was installed yesterday and gas lines leak checked. The He bottle is currently closed.
UPDATE Monday, June 17, 2013, 15:17
Specifications for the currently installed Ne leak (SN: 11-231) can be found on DocuShare
https://documents.triumf.ca/docushare/dsweb/Get/Document-46969 |
32
|
Wednesday, February 08, 2012, 18:16 |
Friedhelm Ames | | | | | | | Failed | TSG:TP1B and TSG:TP1A failure |
Friedhelm Ames wrote: |
Both turbo pumps at the source box were found off. TSG:TP1A has been started normally. TSG:TP1B does not spin up above 3KRPM even after several attemps. A fault report has been send to vacuum group.
|
after about 30 minutes running at normal speed TP1A failed as well. Both pumps will be kept off over night. |
31
|
Wednesday, February 08, 2012, 17:39 |
Friedhelm Ames | | | | | | | Failed | TSG:TP1B failure |
Both turbo pumps at the source box were found off. TSG:TP1A has been started normally. TSG:TP1B does not spin up above 3KRPM even after several attemps. A fault report has been send to vacuum group.
|
30
|
Tuesday, January 24, 2012, 09:44 |
Friedhelm Ames | | | | | | | | turbo pumps restarted |
All turbo pumps have been restarted after cooling water is back and running.
|
29
|
Friday, January 20, 2012, 10:37 |
Friedhelm Ames | | | | | | | | vacuum pumps shut off |
turbo pumps shut off due to work on cooling water system |
28
|
Tuesday, December 20, 2011, 16:09 |
Anders Mjos | | | | | | | Problems/Solutions | Variable leak valve repaired |
Anders Mjos wrote: |
Anders Mjos wrote: |
Variable leak valve with serial number F3-592 has been replaced by F3-649 due to regulating problems described previously by Fridhelm Ames.
|
The variable leak valve F3-592 has been repaired. Contaminated diaphragm was replaced. See attachment for details.
|
The leak valve has been tested with He and a leak detector. The leak valve could regulate in the complete range of the leak detector. 10^-11 to 10^-4 atm cc/s |
27
|
Monday, December 19, 2011, 13:09 |
Aurelia Laxdal | | | | | | | | Test Stand updates |
In January Controls will install a new firewall for ISAC Test Stand. Until then ISAC Test Stand can be used, but it may require an IOC reboot once in while. |
26
|
Tuesday, December 13, 2011, 14:10 |
Aurelia Laxdal | | | | | | | | Test Stand IOC reboot |
Evgeniy rebooted the ISAC Test Stand IOC. Re-started EPICS at the Test Stand.
Found all 4 turbo pumps off and their backing valves closed. Re-started the pumps. |
25
|
Monday, November 14, 2011, 15:40 |
Anders Mjos | | | | | | | Problems/Solutions | Variable leak valve repaired |
Anders Mjos wrote: |
Variable leak valve with serial number F3-592 has been replaced by F3-649 due to regulating problems described previously by Fridhelm Ames.
|
The variable leak valve
F3-592
has been repaired. Contaminated diaphragm was replaced. See attachment for details. |
24
|
Monday, October 17, 2011, 10:22 |
Anders Mjos | FEBIAD | | | | | | Problems/Solutions | Variable leak valve replaced |
Variable leak valve with serial number F3-592 has been replaced by F3-649 due to regulating problems described previously by Fridhelm Ames. |
23
|
Thursday, October 13, 2011, 15:42 |
Anders Mjos | Training | HP-FEBIAD | | | | | Problems/Solutions | Target ready to be heated |
Rick Maharaj wrote: |
test stand vented
|
Thursday, October 13, 2011, 15:40: Pumping down
Friday, October 14, 2011, 10:00: Cooling water is on. Pressure increase from 8e-7 to 3e-6 torr. Venting.
Friday, October 14, 2011, 11:10: Replaced seals on cooling lines with new silver plated SS seals. Pumping down.
Friday, October 14, 2011, 13:25: Cooling water is on. Vacuum at 1.35e-6 torr.
Monday, October 17, 2011, 09:00: Vacuum at 5.4e-7 torr. target ready to be heated. |