920
|
Wednesday, April 20, 2022, 13:42 |
Aaron Schmidt | | | | | | | | Vent Beamline half | Aurelia to do a visual test later.
Wednesday, April 20, 2022, 13:41:
IG6 Off. TP6 & TP2 off. |
|
921
|
Thursday, April 21, 2022, 13:38 |
Aaron Schmidt | | | | | | | Problems/Solutions | Leak checks | https://elog.triumf.ca/TIS/Test-Stand/919
Vacuum Group LD#1
(A) Top feed through fittings upgraded |
|
922
|
Monday, May 02, 2022, 14:10 |
Aaron Schmidt | | P2N-SIS | | | | | | Empty Chamber PS test. | No P2N is loaded. Testing the power supplies.
Tuesday, May 03, 2022, 10:07
In the past few days, the ITS has |
|
924
|
Monday, May 09, 2022, 10:08 |
Luca Egoriti | | P2N-SIS | ITE | TM4 | | | In progress | P2N heating test | Beginning of May:
The cabling on the top of the test
stand was changed to adapt for P2N testing. |
|
929
|
Friday, May 27, 2022, 07:19 |
Fernando Maldonado | | | | | | | Done | FEBIAD parameter scan web-app and brief description (with links) | A web-app for systematic FEBIAD parametrizations
has been develop and now includes the
ISAC Test Stand (ITS) : |
|
930
|
Tuesday, May 31, 2022, 13:35 |
Aaron Schmidt | UCx HS | | ITW | TM2 | | 44378-19 | In progress | Conditioning UC#38 assembly | Using a broken LP-FEBIAD source. TGHT only.
Tuesday, May 31, 2022, 13:24: Roughing.
Tuesday, May 31, 2022, 13:54: TP1B |
|
933
|
Monday, June 20, 2022, 11:49 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Monday, June 20, 2022, 11:49: Water line
loop installed. Roughing.
Thursday, June 23, 2022, |
|
935
|
Thursday, June 30, 2022, 13:50 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Thursday, June 30, 2022, 13:46: Roughing.
Thursday, July 07, 2022,
15:00: Venting. |
|
936
|
Thursday, July 07, 2022, 16:52 |
Aaron Schmidt | | LP-IG-LIS | ITW | TM2 | | 42132-3 | In progress | Conditioning UC#39 assembly | No UCx target installed. Straight / blank
oven in use for out gassing.
Thursday, July 07, 2022, 16:50: Roughing. |
|
937
|
Sunday, July 10, 2022, 22:19 |
Aaron Schmidt | | | | | | | Problems/Solutions | TP2 Trip / TMS:RP2 issue | Sunday, July 10, 2022, 22:19: A trip
was noted on TP2. the backing pressure is
quite high. Shutting off the turbo pumps |
|
938
|
Monday, July 11, 2022, 09:17 |
Aaron Schmidt | | | | | | | In progress | Pump down empty chamber | Monday, July 11, 2022, 09:15: Roughing. |
|
941
|
Thursday, September 29, 2022, 13:50 |
Aaron Schmidt | | | | | | | In progress | Pump down empty chamber | Water loop installed.
Thursday, September 29, 2022, 13:50:
Roughing |
|
943
|
Wednesday, October 19, 2022, 12:16 |
Aaron Schmidt | | | | | | | | Test Stand controls changed | genepicsas.triumf.ca
x11 enabled.
Then use login credentials. |
|
945
|
Tuesday, November 15, 2022, 15:32 |
Sam Gupta | | | | | | | | ATTS tantalum Bracket Heating test | Heated up sample 01 for the second time
and measured the temperature with increasing
current. Used pyrometre to measure temperature |
|
946
|
Wednesday, November 16, 2022, 13:28 |
Aaron Schmidt | | | | | | | Problems/Solutions | TSG:TP1A Replaced | See elog 944
Wednesday, November 16, 2022, 13:23:
TP1 A replaced |
|
947
|
Wednesday, November 23, 2022, 13:52 |
Aaron Schmidt | | | | | | 44378-14 | In progress | FEBIAD Coil Tests | Sam G. & Navid N.
Work Permit# C2022-11-23--1
Wednesday, November 23, 2022, 13:51 |
|
948
|
Monday, December 05, 2022, 15:41 |
Aaron Schmidt | | | | | | | | Source tray insulator replacement | Monday, December 05, 2022, 15:38:
Source Tray TGHT & TBHT insulators replaced.
Torqued @ 75 in-lbs. (Reference image |
7x |
952
|
Monday, December 19, 2022, 12:49 |
Carla Babcock | | HP-FEBIAD | | | | | | HP-FEBIAD tests | Monday, December 19, 2022, 12:06 : Tomislav
changed the polarity of the anode power supply
last week and everything has been closed |
|
953
|
Wednesday, December 21, 2022, 17:06 |
Carla Babcock | | | | | | | | Prep for power outage | Source and beamline power supplies turned
off in EPICS
HV cage power off |
|
954
|
Tuesday, January 03, 2023, 10:03 |
Carla Babcock | | | | | | | | Recovery from power outage | Easy recovery after power outage, just
had to power cycle the ground PLC IOC and
the BiRa IOC. |
|