  124   Wednesday, July 04, 2012, 13:07 Anders Mjos      Problems/Solutionswater lines purged

    

       
            
  
  123   Wednesday, July 04, 2012, 09:22 Friedhelm Ames      Problems/Solutionsturbo pumps stoppedturbo pumps stopped to prepare for venting
for anode short investigation.
  
  122   Tuesday, July 03, 2012, 19:05 Friedhelm Ames      Problems/Solutionsshort in anodeA short in the anode has developed during
the heater ramp up. Increasing the current
limit did not cure it. Start heater ramp
  
  121   Tuesday, July 03, 2012, 09:23 Friedhelm Ames      In progressstart up againpurged Ne line and started cathode heater
ramp up to 295 A
  
  120   Friday, June 29, 2012, 16:39 Friedhelm Ames       mass scan finished

    

       
            
  
  119   Friday, June 29, 2012, 15:03 Friedhelm Ames       start ramping down heater    
  118   Friday, June 29, 2012, 15:02 Friedhelm Ames       mass scan finishedmass spectrum saved as
plotdump-local-clean.txt_Jun29_12_14-55-43.txt


 mass_spectrum_2012_06_29.PNG 
  117   Friday, June 29, 2012, 13:39 Friedhelm Ames       start mass scanstart mass scan to do new mass calibration   
  116   Friday, June 29, 2012, 08:57 Pierre Bricault LP-FEBIAD    In progressContinue cathode heating This morning the pressure was 3.5E-7
T. Current at 275 A is 30nA.
Continue cathode heating to 290 A
  
  115   Thursday, June 28, 2012, 17:18 Pierre Bricault LP-FEBIAD    In progressLeave the cathode heater at 275 A overninght.    
  114   Thursday, June 28, 2012, 17:00 Pierre Bricault LP-FEBIAD    In progressCathode heater reached its value of 230 A and stoped. good test.Now ramp cathode current up to 290 A. The
total current out is 1.e-7 A.
 
  
  113   Thursday, June 28, 2012, 15:14 Aurelia Laxdal LP-FEBIAD     Quick checkJust a quick check at the Test Stand:
1. The system operational ( 
white out not present ) with TSH:TBHT heating
  
  112   Thursday, June 28, 2012, 11:29 Pierre Bricault LP-FEBIAD    In progressLost all cnntrol interface, complete whiteout of the epics system.    
  111   Thursday, June 28, 2012, 11:27 Pierre Bricault LP-FEBIAD    In progressCathode heating in progress, pressure 8.3e-7 T    
  110   Thursday, June 28, 2012, 11:19 Pierre Bricault LP-FEBIAD    In progressCathode ramping to 230 A in progress    
  109   Thursday, June 28, 2012, 11:13 Pierre Bricault LP-FEBIAD     ISAC test stand ready for cathode heatingThe ISAC test stand is ready for cathode
heating.
Bias voltage: 30000 V
  
  108   Thursday, June 28, 2012, 11:04 Pierre BricaultTest FEBIADLP-FEBIAD    In progressReady to bias the high voltage.    
  107   Tuesday, June 26, 2012, 18:30 Anders Mjos      Problems/SolutionsCrack in source tray insulator A crack in the insulator ITD0054
was observed while mounting the target assembly.
See attachment.
 Cracked_insulator.pdf 
  106   Tuesday, June 26, 2012, 18:04 Anders MjosFEBIAD anode end cap test   Tube only38307-9In progressFEBIAD anode end cap test - readyTesting FEBIAD anode end cap as per dwg
ITD0304 REV C
Target with TUBE ONLY. Do not use
  
  105   Tuesday, June 26, 2012, 16:06 Anders Mjos      DoneVented

    

       
            
  