  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O#down Status Subject Text Attachments
  634   Tuesday, February 13, 2018, 16:47 Carla Babcock       Ramping to 63kV - some sparksSparks at 62kV on the bias.
Turned it down, turned it back up
and got a spark at 60kV.
  
  635   Friday, February 16, 2018, 15:21 Carla Babcock       Cleaned HV cage - trying bias againI vacuumed inside the HV cage, though it
has many small areas that are difficult to
access so I am not sure how great a job I
  
  636   Monday, February 19, 2018, 08:30 Carla Babcock       TMSTP6 offFound TMSTP6 off, restarted it, seems fine
now (drawing 0.8A)
  
  637   Monday, February 19, 2018, 14:01 Carla Babcock       Attempts to get to higher voltages, summarized.The test stand holds up to 63kV, however
at voltages over 54kV there are small discharges,
rising to a continuous level around 60kV.
  
  638   Tuesday, February 20, 2018, 09:04 Carla Babcock       Trying HV with rubber corona shieldTuesday, February 20, 2018, 09:01: Sparks
at 62.5kV after a couple minutes. Sounds
like they were in the EE spark gap but don't
  
  639   Friday, February 23, 2018, 08:50 Aaron Schmidt       New Al Corona Friday, February 23, 2018, 08:50    
  640   Monday, February 26, 2018, 09:13 Carla Babcock       Running list of changes to the ISAC test stand for >60kV operation1. Al corona shield installed over end
of the HV duct to suppress discharges from
the sharp edge of the duct.
 6x 
  641   Wednesday, February 28, 2018, 11:50 Aaron Schmidt       HV Test NpNew parts installed. Corona Shield, brackets,
and board/spark gap orientation.
Wednesday, February 28, 2018, 11:48:
 2018_HV_test_Np.docx 
  642   Thursday, March 01, 2018, 10:05 Carla Babcock       HV tests with corona discharge problems solvedTurning up bias, no corona discharge at
60kV but a spark at 61.5kV bias, 31kV EZL,
-800V EE
 01032018_10am_61kVspark.PNG 
  643   Tuesday, March 06, 2018, 10:55 Carla Babcock       Trying HV without electronicsI have removed the resistor/varistor combinations
that go between the poles of the target and
tube heaters, and between those two supplies.
 spark_06032018.PNGnospark_06032018_1410.PNG 
  644   Thursday, March 08, 2018, 17:47 Carla Babcock       Change of electronics on target and tube power suppliesThe resistor/varistor combinations across
the target + / -, tube + / - and target-
/ tube + have been remade and moved to the
 IMG_20180308_152637.jpgIMG_20180308_152645.jpgTargetNeg.jpgTubeNegPos.jpg 
  645   Friday, March 09, 2018, 08:57 Carla Babcock       HV test with electronics moved to rackFirst attachment: BIAS/EE/EZL = 63.25/-1.5/31
So far no issues.
Second attachment: BIAS/EE/EZL =
 09032018_830.PNG09032018_835.PNG09032018_850.PNG09032018_855.PNG 
  646   Monday, March 12, 2018, 10:07 Aaron Schmidt       HV Test w-gasMonday, March 12, 2018, 09:45: Gas lines
opened. Leak rate set. Vacuum @ 1.16e-06T
Monday, March 12, 2018, 10:00: RGA
  
  647   Monday, March 12, 2018, 10:44 Carla Babcock       Bringing up HV with gas onPressure:
Previous HV tests done at 2e-7
pressure.
Current pressure 1.1e-6
 8x 
  648   Tuesday, March 13, 2018, 06:00 Aaron SchmidtUC#22LP-SISITETM4  In progressConditioning Heat Shield for UC#22Tuesday, March 13, 2018, 08:50: Roughing.
Tuesday, March 13, 2018, 09:10: Turbo
Pumps started.
  
  650   Tuesday, March 20, 2018, 09:14 Aaron Schmidt      Problems/SolutionsOptics issueTuesday, March 20, 2018, 09:11: TMS:Q5
& TMS:Q2 controllers require repair.
Unable to hold a negative voltage.
  
  652   Thursday, March 29, 2018, 10:58 Carla Babcock        Started with Anode at 25V and coil at 0A,
bias at 30kV. (attachment 1)
Ramped coil to 60A (0.4V) (attachment
 6x 
  653   Wednesday, April 11, 2018, 10:19 Aaron Schmidt       Pump down empty chamberWednesday, April 11, 2018, 10:19: Roughing   
  654   Tuesday, April 17, 2018, 09:59 Aaron Schmidt LP-FEBIAD  41790-9  Test FEBIADNew assembly & target. Same silver
bolts.
Tuesday, April 17, 2018, 09:56: Roughing.
  
  655   Tuesday, April 17, 2018, 11:02 Aaron Schmidt      DoneRoughing pump issue.Tuesday, April 17, 2018, 10:57: Vacuum
not coming down. @ 1.514T . Backing valves
have been closed.
  