119
|
Friday, June 29, 2012, 15:03 |
Friedhelm Ames | | | | | | | | start ramping down heater | |
|
120
|
Friday, June 29, 2012, 16:39 |
Friedhelm Ames | | | | | | | | mass scan finished |
|
|
132
|
Friday, July 06, 2012, 11:04 |
Friedhelm Ames | | | | | | | | source tripped off over night | A big vacuum excursion tripped the source
off at about 1am. The vacuum did not fully
recover afterwards only down to about 1.3e-6T. |
|
133
|
Friday, July 06, 2012, 11:05 |
Friedhelm Ames | | | | | | | | start source again | heater ramping up again with Ne leak closed. |
|
134
|
Friday, July 06, 2012, 11:18 |
Friedhelm Ames | | | | | | | | TSG:TP1B off source off again. | turbo pump TSG:TP1B has tripped off. Cannot
be restarted. Fault report to vacuum. Everything
switched off again |
|
136
|
Monday, July 09, 2012, 11:14 |
Aurelia Laxdal | | | | | | | | Test Stand status | Restarted the PC at the Test Stand.
Restarted the Archivers; currently
pumping down the separator area. |
|
146
|
Thursday, July 12, 2012, 15:49 |
Anders Mjos | | | | | | | | test stand vented for TP1A replacement | see e-fault 6142 |
|
155
|
Thursday, August 09, 2012, 13:08 |
Pierre Bricault | | | | | | | | Test FEBIAD | Waiting Rick for the fitting on the vacuum
pump. |
|
159
|
Friday, August 10, 2012, 14:08 |
Rick Maharaj | | | | | | | | Gas line pump | Gas line vacuum pump reinstalled after
fitting was modified to receive a standard
swagelok connector. The vacuum line was plumbed |
|
160
|
Friday, August 10, 2012, 15:29 |
Pierre Bricault | NA | LP-FEBIAD | | | NA | NA | | finishing the gas installation and its pump | 1524H Start small pump.
1529H stop the pump.
|
|
161
|
Friday, August 10, 2012, 15:57 |
Pierre Bricault | | | | | | | | | Test high voltage to 30 kV ok
Test gas valve open at 6.1 V
Test Ne leak ok |
|
163
|
Saturday, August 11, 2012, 16:18 |
Pierre Bricault | | | | | | | | Test FEBIAD anode biased at 120 V | The ramp up finished.
I have 3.35E-6 Amp out of the source
on FC0. |
|
194
|
Thursday, September 06, 2012, 09:23 |
Friedhelm Ames | NB#7 | | | | | | | | start high voltage and heaters |
|
203
|
Thursday, September 13, 2012, 13:05 |
Friedhelm Ames | Nb#7 | LP-SIS | | | | | | heater ramping up started | |
|
215
|
Tuesday, September 25, 2012, 16:10 |
Aurelia Laxdal | | | | | | | | Conditioning - SiC-HP-FEBIAD for operator training | Did the HV conditioning up to 30kV.
Started the heaters conditioning:
for TSH:TGHT up to 580A |
|
225
|
Thursday, November 01, 2012, 11:16 |
Aurelia Laxdal | TiC#3 | LP-SIS | ITW | TM1 | | | | TiC#3-LP-SIS Startup | Did the HV conditioning for the TiC#3 up
to 30kV.
Heaters ramp up in progress. |
|
226
|
Thursday, November 01, 2012, 14:57 |
Aurelia Laxdal | TiC#3 | LP-SIS | ITW | TM1 | | | | TSH:TGHT readback stopped at 264.5A (for a higher setpoint) | The TSH:TGHT stopped at 263.7A, but the
setpoint is still ramping (now at 421A).
The voltage is set correctly: have 6.238V |
|
227
|
Friday, November 02, 2012, 14:20 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | | Mass scan done |
Normal
0
false
false
false
|
|
233
|
Monday, November 19, 2012, 10:20 |
Aurelia Laxdal | Test-SiC | HP-FEBIAD | | | | | | Preparations for E-Fault#6389 investigations | Prepared the Test Stand for Controls to
investigate E-Fault#6389.
|
|
234
|
Thursday, November 22, 2012, 12:52 |
Aurelia Laxdal | Test-SiC | HP-FEBIAD | | | | | | E-Fault#6389 re-directed to PS | Evgeniy and Kazuya investigated the problem
with TSH:TGHT readbacks and they came to
the conclusion that the PS is faulty, and |
|