Tuesday, July 27, 2021, 12:57, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD parameter scan - efficiency measurements
|
Assembly has new gas tube to the target for better fit and clearance to the HS.
Electric checks before closing shows no short between TIS and HS.
Tuesday, July 27, 2021, 12:57: Venting |
Wednesday, July 28, 2021, 08:48, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD parameter scan - efficiency measurements
|
Modified spiral tube from VCR to counteract torque towards the HS. Now points towards TBHT.
Electric checks before closing shows no short between TIS and HS. |
Monday, July 26, 2021, 17:35, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD efficiency measurements.
|
Monday, July 26, 2021, 17:23: Roughing
Monday, July 26, 2021, 17:55: Turbos on.
Monday, July 26, 2021, 18:03 : TP1A timed out ...again |
Thursday, July 22, 2021, 17:43, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD efficiency measurements
|
Thursday, July 22, 2021, 17:43: Roughing
New argon gas bottle installed.
Thursday, July 22, 2021, 18:16: Turbos on. |
Monday, July 06, 2020, 05:28, Fernando Maldonado, Test FEBIAD , HP-FEBIAD, , , 38295-8 , 42752-5 , Done, FEBIAD development part 3/3
|
Reminder. Mini pump still linked to SV1. DO NOT OPEN SV2!!!
The plan for today Monday, July 06, 2020 is:
|
Tuesday, June 30, 2020, 21:59, Fernando Maldonado, Test FEBIAD, HP-FEBIAD, , , 38295-8 , 42752-5 , Done, FEBIAD development part 2/3
|
Reminder. Mini pump still linked to SV1. DO NOT OPEN SV2!!!
The plan for today Wednesday, July 01, 2020 ( |
Thursday, June 25, 2020, 08:57, Fernando Maldonado, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, Done, FEBIAD development part 1/3
|
Reminder. Mini pump still linked to SV1. DO NOT OPEN SV2!!!
The plan for today Thursday, June 25, 2020 is:
Optimize (tune) the beam to FC0 and then to FC6.
Compensate |
Thursday, December 05, 2024, 15:38, Dave Neilson, , LP-FEBIAD, , , 44692-4, 42972-10, , FEBIAD development
|
Tuesday, December 02, 2024, 15:35 - Target loaded into the test stand
Thursday, December 03, 2024, 14:33 - as per elog entry 1033, test stand has been changed to CATHODE mode, and wiring within the Faraday cage has
been altered appropriately. Additionally, a GeMov resistor has been added to potentially reduce the sparking problems that have previously tripped the |
Tuesday, January 07, 2025, 17:06, Dave Neilson, , LP-FEBIAD, , , 44692-4, 42972-10, In progress, FEBIAD development
|
Tuesday, January 07, 2025, 16:00 - Target assembly installed in test stand. electrical connections assessed:
Prior to installation: oven and cathode isolated from heatshield. no shorts
After installation: Oven and Cathode 35kΩ from HVC. |
Tuesday, October 24, 2017, 11:38, Anders Mjos, , , , , , , , FEBIAD coil magnetic field measurment 
|
with Fernando
Tuesday, October 24, 2017: Testing setup with triple coil
Wednesday, October 25, 2017: Field mapping at 70 A and current/field measurements on triple coil. |
Tuesday, July 16, 2013, 16:01, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD coil connector insulator fracture
|
The right side of the insulator cracked/fractured either as the bolt was tightened or loosened. |
Tuesday, June 26, 2012, 18:04, Anders Mjos, FEBIAD anode end cap test, , , , Tube only, 38307-9, In progress, FEBIAD anode end cap test - ready
|
Testing FEBIAD anode end cap as per dwg ITD0304 REV C
Target with TUBE ONLY. Do not use target heater.
Tuesday, June 26, 2012, 18:03: Roughing |
Thursday, April 25, 2013, 13:32, Anders Mjos, Empty, LP-FEBIAD, , , Tube Only, 38307-9 , In progress, FEBIAD Coil test  
|
Same target as in e-log entry https://elog.triumf.ca/TIS/Test-Stand/106
Thursday, April 25, 2013, 13:54: Roughing
Thursday, April 25, 2013, 14:25: Started turbos |
Monday, May 04, 2015, 09:51, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD Coil power supply replaced
|
Power supply did not work after high voltage conditioning. On Friday May 1st John Chow replaced the power supply with a 12 V 100 A power supply temporary while the other supply is being repaired. EPICS controls have not been adjusted. |
Wednesday, November 23, 2022, 13:52, Aaron Schmidt, , , , , , 44378-14, In progress, FEBIAD Coil Tests
|
Sam G. & Navid N.
Work Permit# C2022-11-23--1
Wednesday, November 23, 2022, 13:51 FS#5 on (HS bypassed with a water loop) |
Friday, July 19, 2013, 14:14, Anders Mjos, , , , , Tube only, 38307-9, In progress, FEBIAD Coil Test
|
Friday, July 19, 2013, 14:14 : Stopping Turbos. Vacuum at 1.3E-7 T
Friday, July 19, 2013, 15:14: Venting
Friday, July 19, 2013, 16:22: Target installed. Roughing. |
Tuesday, August 20, 2013, 08:24, Anders Mjos, , , , , Tube only, 38307-9, In progress, FEBIAD Coil Test
|
Tuesday, August 20, 2013, 08:13: Roughing gas lines
Tuesday, August 20, 2013, 08:22: Gas lines roughed. Valve closed |
Saturday, June 03, 2017, 09:34, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD Cathode bias configuration
|
Anders Mjos wrote:
The Test Stand has been configured for Anode bias. John Chow changed the power supply and the |
Tuesday, May 20, 2014, 12:39, Anders Mjos, , , , , , , Done, FEBIAD Cathode Negative BIAS configuration
|
As per ISK4562 Rev 3 and ISK4563 Rev 3
By Ray D. and co. |
Thursday, September 15, 2011, 13:46, Anders Mjos, FEBIAD Test, HP-FEBIAD, , , , , Failed, FEBIAD Broken Tube
|
See attached file for photos of the broken tube |
|