Thursday, March 08, 2018, 17:47, Carla Babcock, , , , , , , , Change of electronics on target and tube power supplies
|
The resistor/varistor combinations across the target + / -, tube + / - and target- / tube + have been remade and moved to the back of the power supplies
to limit the corona discharges at higher voltages. Pictures attached. |
Friday, March 09, 2018, 08:57, Carla Babcock, , , , , , , , HV test with electronics moved to rack
|
First attachment: BIAS/EE/EZL = 63.25/-1.5/31 So far no issues.
Second attachment: BIAS/EE/EZL = 64.25/-1.5/32 Slight spark - bias current jumped from 40uA to 88uA and vacuum jumped from 2e-7 to 2e-6... Steerers
went off. |
Monday, March 12, 2018, 10:07, Aaron Schmidt, , , , , , , , HV Test w-gas
|
Monday, March 12, 2018, 09:45: Gas lines opened. Leak rate set. Vacuum @ 1.16e-06T
Monday, March 12, 2018, 10:00: RGA on
Monday, March 12, 2018, 10:07: RGA off. Manually shut off power as well |
Monday, March 12, 2018, 10:44, Carla Babcock, , , , , , , , Bringing up HV with gas on 8x
|
Pressure:
Previous HV tests done at 2e-7 pressure.
Current pressure 1.1e-6 (see previous entry for RGA stats) - first attachment shows source
gas setup. Argon, neon and He leaks all on.
|
Tuesday, March 20, 2018, 09:14, Aaron Schmidt, , , , , , , Problems/Solutions, Optics issue
|
Tuesday, March 20, 2018, 09:11: TMS:Q5 & TMS:Q2 controllers require repair. Unable to hold a negative voltage.
+ @ 680V
- @ 0V (Should be 680V as well) |
Wednesday, March 21, 2018, 14:11, Fernando Maldonado, , LP-FEBIAD, , , 395530-3, 42752-2, In progress, Test FEBIAD 10x
|
Tests on coil, temperature and the use of silver bolts.
(3) Vented silver bolts on the TBHT and (2) Full silver bolts on the coil
Wednesday, March 21, 2018, 14:10: Roughing. |
Thursday, March 29, 2018, 10:58, Carla Babcock, , , , , , , , 6x
|
Started with Anode at 25V and coil at 0A, bias at 30kV. (attachment 1)
Ramped coil to 60A (0.4V) (attachment 2)
Ramped bias to 51kV, but then TP6 turned off and there was a momentary 0.2A decrease in the TGHT current. No spike in BIAS current seen, maybe |
Wednesday, April 11, 2018, 10:19, Aaron Schmidt, , , , , , , , Pump down empty chamber
|
Wednesday, April 11, 2018, 10:19: Roughing |
Tuesday, April 17, 2018, 09:59, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, , , Test FEBIAD
|
New assembly & target. Same silver bolts.
Tuesday, April 17, 2018, 09:56: Roughing.
Tuesday, April 17, 2018, 10:57: Vacuum not coming down. @ 1.514T . Backing valves have been closed. |
Tuesday, April 17, 2018, 11:02, Aaron Schmidt, , , , , , , Done, Roughing pump issue.
|
Tuesday, April 17, 2018, 10:57: Vacuum not coming down. @ 1.514T . Backing valves have been closed.
TSG:CG1A @ 1.515T
TSG:CG1B @ 1.529T. |
Thursday, April 19, 2018, 12:55, Fernando Maldonado, , , , , , , Done, Re-wiring Anode PS
|
Thursday, April 19, 2018, 12:52: Pin J1 was reconnected into the anode power supply. All jumpers were put back to remote control.
NOTE: the cable EXTLKT is still not connected. I will ask Carla about this one.
Thursday, April 19, 2018, 18:00: Cable EXTLKT connected. |
Friday, April 20, 2018, 13:20, Carla Babcock, , , , , , , Done, BIAS* fan sounds like it is dying
|
The fan in the EZL power supply is making a terrible noise - keep an eye on it, it sounds like it might give up soon.
Monday, April 23, 2018, 10:47: The back panel was opened. Original entry stated EZL power supply issue. Corrected to BIAS PS. High voltage
group notified. Fan replacement required. |
Wednesday, April 25, 2018, 09:50, Aaron Schmidt, Ta (test), LP-SIS, , , 41177-3, , In progress, Ta test and window change
|
Window changed on view port. Ta target prepared for Aurelia's tests.
***Note*** No Ta window foils on the end plates. Initial ramping to on the TGHT to 300 A. Follow up in increments of 50 A and check the right
door window temperature. |
Monday, April 30, 2018, 12:07, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test ready
|
Ready for C-seals or FEBIAD work
Monday, April 30, 2018, 12:05: Roughing.
Monday, April 30, 2018, 13:11: Turbo pumps on. |
Tuesday, May 08, 2018, 10:36, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, C-seal Test
|
2 C-Seals installed with SS springs on water blocks. The SS springs are also used in the module.
Long pkg seal (A):
T: 0.098" x 0.429" Diameter. |
Tuesday, May 22, 2018, 08:48, Anders Mjos, , , , , , , Problems/Solutions, TSG:TP1A not running
|
Pump found off on Tuesday morning.
Tuesday, May 22, 2018, 08:40: Starting TP1A
Tuesday, May 22, 2018, 08:47: TP1A at speed |
Thursday, May 24, 2018, 08:38, Anders Mjos, , , , , , , Problems/Solutions, Venting beamline for IG6 replacement
|
Thursday, May 24, 2018, 08:38: TPs stopped
Thursday, May 24, 2018, 09:18: Venting
Thursday, May 24, 2018, 14:30: IG6 replaced (second attempt) by Anthony. System pumping down |
Thursday, May 24, 2018, 15:28, Anders Mjos, , , , , , , Problems/Solutions, Reconfigured FEBIAD coil for testing new source tray
|
Thursday, May 24, 2018: Configured coil to be (-) E&F, (+) G&H. Water should be supplied to both terminals in either configuration. |
Monday, June 04, 2018, 16:02, Anders Mjos, , , , , , , Problems/Solutions, MB1 timeout
|
Mass separator magnet timed out. Tried reconfigure. Called Kyle from controls who power cycled the CANbus card. This resolved the issue
(From the Source tray swap out.) - AS
Tuesday, June 05, 2018, 11:25: BIAS / EZL / EE @ 52 / 24 / 2.8 kV. SPARK *knocked out optics, magnet & Turbo TMS:TP6. IV4 closed/opened/reset. |
Wednesday, June 06, 2018, 14:01, Aaron Schmidt, , , , , , , Problems/Solutions, Emittance scanner (E-rig) communication issues.
|
Wednesday, June 06, 2018, 13:50:
It was noted yesterday during the TM2 Source HV tests that the E-rig was not running accordingly through the beam.
Upon turning on the PS, there a 45 second or so delay before the needle drops to the right at +500V and the PS no longer responds. (similar issue |
|